Nu-Way Mobile Home Manufacturing, Inc.

General-industry fall citation vacated because construction standards applied

Nu-Way built mobile homes from the ground up on an assembly line, and OSHA cited the general-industry personal-protective-equipment rule after employees worked on a roof without safety belts. The Commission held that the work was construction because the nature of the work, not its factory…

February 4, 1986
Citations vacated
COMM

L.R. Willson & Sons, Inc.

Perimeter-net citation reinstated after court remand

The Commission had previously vacated a serious citation alleging that L.R. Willson failed to use perimeter netting against exterior falls during structural steel erection. The D.C. Circuit reversed that decision and directed the Commission to reinstate the citation. Following the court's mandate…

January 30, 1986
Citations affirmed
COMM

A. Amorello & Sons, Inc.

Backup-alarm violation affirmed as other-than-serious after court remand

On remand from the First Circuit, the Commission reconsidered whether a front-end loader operated in reverse without a working backup alarm. Two OSHA officials observed the loader backing without hearing an alarm, and a later demonstration showed that the alarm did not sound until an operator…

January 28, 1986
Modified
COMM

New Boston Coke Corporation

Settlement approved after bankruptcy authorization

New Boston Coke submitted proof that the bankruptcy court had authorized its trustee to execute a settlement agreement. Counsel for the Secretary, the company, and the union had already signed the agreement. The Commission approved the settlement, and the short release does not identify the…

January 16, 1986
Settled
COMM

The L.E. Meyers Co., High Voltage Systems Division

Three ladder and fall-protection items vacated

L.E. Meyers, an electrical contractor, was installing protective rubber hosing on power lines when an apprentice fell from a ladder, contacted an energized jumper, and was electrocuted. Another employee was injured when he jumped from the ladder. The Commission held that changing § 1926.28(a) from…

January 16, 1986
Citations vacated
COMM

Cleveland Electric Illuminating Co.

Settlement order remanded to remove a penalty

The administrative law judge approved the parties’ settlement but assessed a $150 penalty for item 3. Cleveland Electric told the Commission that the order conflicted with the settlement because item 3 should assess no penalty. The Secretary agreed and stated an intention to withdraw the citations…

January 13, 1986
Remanded
COMM

Schwarz-Jordan, Inc.

Serious scaffold citation reinstated after court reversal

The Commission had previously vacated a citation alleging that Schwarz-Jordan violated the scaffold standard by using an unguarded scaffold. The Fifth Circuit reversed that decision and directed the Commission to reinstate the citation. Following the court’s mandate, the Commission reinstated…

January 3, 1986
Citations affirmed
COMM

Metro Waterproofing, Inc.

Consolidated cases remanded for factual inquiry

Metro Waterproofing’s president, acting without counsel, stipulated that certain violations existed on the inspection date. The judge relied on that stipulation to affirm five citations and assess $17,120 in penalties. A later affidavit asserted that the conditions violated communicated and…

December 26, 1985
Remanded
COMM

Simplex Time Recorder Company

Solvent violation reduced from willful to serious

Simplex used lacquer thinner with a four-degree Fahrenheit flash point to clean a spray-booth floor, contrary to a standard requiring at least a 100-degree flash point for that cleaning use. A fire occurred in the booth and an employee died. The Commission held that the standard was validly…

December 16, 1985
Modified
COMM

Burk Well Service Company

Citation vacated for lack of commerce evidence

OSHA cited Burk Well Service for a willful violation of the general duty clause, and the judge affirmed the citation with a $2,000 penalty. Burk had specifically denied that it was engaged in a business affecting commerce, a fact required for coverage under the Act. The Commission explained that…

December 12, 1985
Citations vacated
COMM

General Electric Company

Settlement affirmed over union’s abatement objections

OSHA cited General Electric for exposing employees to burn hazards from hot slag in a molten-metal furnace. The Secretary and GE settled, with GE agreeing to monitor furnaces for slag buildup and address safety precautions for maintenance. The participating union objected that the agreement did not…

December 11, 1985
Settled
COMM

Ernie's Esquire, Inc.

Dismissal remanded for another chance to certify notice

The judge dismissed Ernie’s Esquire’s contest of its citations because the company had not certified that it posted or served the notice of contest for affected employees. The company president sought reconsideration and explained that he had posted materials but believed an affected employee meant…

December 6, 1985
Remanded
COMM

Cardinal Industries, Inc.

General-industry fall items vacated as preempted

Cardinal built modular housing units on an indoor assembly line using carpentry, plumbing, roofing, and electrical work. OSHA cited two unguarded platforms under the general-industry guardrail standard and the lack of safety belts under the general-industry personal-protective-equipment standard…

December 6, 1985
Citations vacated
COMM

Gulf States Utilities Company

Grounding citation vacated because insulator work was maintenance

A Gulf States crew replaced vandalism-damaged porcelain insulators with epoxy insulators on a deenergized power line. While the crew removed grounding chains, one chain was taken off out of sequence and a lineman holding a spliced chain was electrocuted by induced current. OSHA cited the utility…

November 20, 1985
Citations vacated
COMM

Sharon Steel Corporation

Flying-steel citation vacated for lack of a current hazard

OSHA alleged that Sharon Steel exposed maintenance employees to flying steel fragments while they changed a bridle roll and sheet steel moved through a temper mill from a payoff reel. The Commission found that earlier reported incidents fell outside the Act’s six-month limitations period. On the…

November 19, 1985
Citations vacated
COMM

FMC Corporation

Additional plant inspection allowed with cost reimbursement

OSHA cited FMC under the general duty clause for allegedly failing to control potential exposure from an uncontrolled methyl isocyanate reaction at its pesticide plant. After numerous inspections and extensive cooperation by FMC, the Secretary sought another plant inspection by expert witnesses to…

November 13, 1985
Procedural
COMM

MLB Industries, Inc.

Fall-protection citation vacated because Crown controlled the work

MLB supplied three union laborers to Crown Zellerbach for emergency concrete-floor removal work at Crown’s construction project. The workers used no fall protection, and one fell about 14 feet when the concrete beneath him gave way and later died from his injuries. The judge treated MLB as the…

October 31, 1985
Citations vacated
COMM

Adams Steel Erection, Inc.

Two citation items reinstated after court review

The Commission had previously reversed the administrative law judge and vacated two citation items against Adams Steel Erection. The Third Circuit granted the Secretary’s petition for review and directed the Commission to reinstate the judge’s decision. The Commission therefore affirmed a serious…

October 23, 1985
Citations affirmed
COMM

Bechtel Power Corporation

Crane-barricade citation vacated

Bechtel used rope-and-flag barricades around cranes while building a power plant. A crane oiler was killed when he was caught between the tracks and rotating superstructure of a crawler crane, and OSHA cited the barricading standard. The Secretary conceded that the physical barricade was the type…

October 2, 1985
Citations vacated
COMM

RSR Quemetco, a Division of RSR Corporation, A Corporation

Remanded proceedings authorized to resume

The Commission had previously severed these four consolidated RSR matters and remanded them to administrative law judges. The Fifth Circuit stayed those remand orders while it reviewed RSR’s petition. After the court affirmed the Commission’s orders, the Commission directed the assigned judges to…

October 1, 1985
Remanded
COMM

Red Star Marine Services, Inc.

Noise citation withdrawn and case dismissed

Red Star operated tugboats and marine towing services. An administrative law judge found that an engineer aboard the tugboat Stamford was exposed to excessive engine-room noise and that Red Star lacked a continuing, effective hearing-conservation program. The judge affirmed those two items as other…

September 4, 1985
Citations vacated
COMM

Eastern Steel Erectors, Inc.

EAJA fee claim settled for $4,330

Eastern Steel Erectors had an application pending for attorney’s fees and expenses under the Equal Access to Justice Act. The parties agreed to end the fee dispute without further litigation. The Department of Labor agreed to pay $4,330 without conceding that the company was entitled to fees. In…

August 8, 1985
Procedural
COMM

Four Flags Drilling Company

Kelly-bushing citation withdrawn under abatement settlement

Four Flags drilled oil and gas wells and was cited for failing to guard a smooth rotary-table kelly bushing, with a proposed $300 penalty. The judge affirmed the serious item and penalty, and Commission review followed. In settlement, Four Flags agreed either to use a contact-preventing guard or to…

May 16, 1985
Settled
COMM

National Engineering & Contracting Company

Settlement approved

The Commission approved the parties’ stipulation and settlement agreement. It issued no separate explanation of the agreement or the reasons for approval. The short official release does not identify the cited standards, alleged conditions, settlement terms, abatement obligations, or penalty result.

May 16, 1985
Settled
COMM

Hahnel Brothers Co.

Roofing citation withdrawn under fall-protection agreement

Hahnel Brothers sought Commission review of an administrative law judge’s decision involving a roofing citation. In settlement, the Secretary withdrew the citation. Hahnel agreed that, during built-up roofing work on low-pitched roofs more than 16 feet above ground, it would use an MSS system or a…

May 2, 1985
Settled
COMM

Du-Mor Enterprizes, Action Utility Company, Inc., Du-Mor Drilling and Blasting

Training citation remains vacated after Commission impasse

Du-Mor used a trenching machine with a power-driven digging chain. A laborer was killed when the operator restarted the chain while the laborer was nearby, and OSHA cited Du-Mor for inadequate hazard instruction. The judge vacated the citation after crediting testimony that employees had been…

April 26, 1985
Citations vacated
COMM

F. A. Gray, Inc.

Roof safety-belt item affirmed, scaffold item vacated

F. A. Gray employees painted a hotel exterior from a two-point suspension scaffold and from the edge of a 60-foot-high flat roof without safety belts. Both Commission members agreed to vacate the scaffold item because the employer had communicated and enforced a belt rule, supervisors inspected…

April 26, 1985
Mixed result
COMM

Phoenix Forging Company Division

Programmed-inspection warrant challenge rejected

Phoenix stipulated that 13 safety violations occurred but sought to suppress the inspection evidence and invalidate the warrant. It argued that the warrant exceeded the programmed-inspection plan, improperly allowed private employee interviews and record review, and relied on an unpublished OSHA…

April 26, 1985
Citations affirmed
COMM

General Motors Corporation, Rochester Products Division

Unshored-trench and training items affirmed

GM employees dug and shored a deep trench inside a manufacturing building to install an oil-collection trough. A worker was injured when an unshored wall collapsed as he used an unshored leg of the trench to leave the work area. The Commission affirmed a serious trenching violation because GM left…

April 26, 1985
Mixed result
COMM

Smith Steel Casting Co.

Evidence from invalid warrant admitted

OSHA inspected Smith Steel’s foundry under an ex parte warrant and cited silica, copper-fume, noise, and respirator-program conditions. The Fifth Circuit later held that the warrant was invalid under the inspection regulation then in effect and returned the case for the Commission to decide whether…

April 23, 1985
Procedural
COMM

Equitable Shipyards, Inc.

Welding-respirator dispute remanded for subpoenaed testimony

OSHA cited Equitable Shipyards for inadequate mechanical ventilation and respirator protection against welding fumes. The Commission rejected Equitable’s request to suppress inspection evidence obtained under a limited warrant based on an employee complaint. It held, however, that the judge should…

April 18, 1985
Remanded
COMM

Curt Bullock Builders, Inc.

Mixed guarding and grounding rulings left in place

Curt Bullock manufactured prefabricated garages and was cited over an unguarded storage surface, an unguarded conveyor chain and sprocket, circular saws with lower guards wired back, and ungrounded employee-owned equipment. The judge treated the storage-surface item as de minimis and the…

April 17, 1985
Mixed result
COMM

Thermal Reduction Corporation

Willful refusal to produce injury log affirmed

During a warranted OSHA inspection, Thermal Reduction’s vice president twice refused to provide the company’s OSHA Form 200 injury and illness log unless the inspector promised that no disclosed information would ever be used against the company. The Commission held that the Act and recordkeeping…

April 17, 1985
Citations affirmed
COMM

Hayes-Albion Corporation

Molten-metal explosion citation remains vacated

A fire in Hayes-Albion’s iron foundry required water to be sprayed into exhaust ductwork, and the water drained onto the floor near molten-metal operations. OSHA alleged a willful general duty clause violation based on the risk that molten metal could encapsulate water and cause an explosion. The…

April 17, 1985
Citations vacated
COMM

J.L. Foti Construction Co., Inc.

Three construction items affirmed, one vacated

J.L. Foti performed masonry work as a subcontractor on a hospital project and objected when OSHA inspected its enclosed elevator-shaft work area without a warrant. The general contractor consented to the inspection, but the two Commission members divided on whether that consent overrode Foti’s…

April 15, 1985
Mixed result
COMM

Davis Metal Stamping, Inc.

Evidence admitted despite invalid ex parte warrant

OSHA obtained an ex parte warrant to inspect Davis Metal’s plant after company officers refused entry and stated that mechanical power presses were unguarded. Applying Fifth Circuit precedent, the Commission treated the warrant as invalid under OSHA’s inspection regulation then in effect. It…

April 15, 1985
Citations affirmed
COMM

Kut-Kwick Corporation

EAJA fee claim settled for $6,500

Kut-Kwick had an application pending for attorney’s fees and expenses under the Equal Access to Justice Act. The parties settled the entire fee claim without further litigation. The Department of Labor agreed to pay $6,500 without conceding that Kut-Kwick was legally entitled to fees. In exchange…

April 10, 1985
Procedural
COMM

City Oil Well Service Co.

Respirator citations left vacated after Commission impasse

Two City Oil Well Service employees died during swabbing work at an oil well where later testing found hydrogen sulfide at 225 parts per million. City relied on well operators to identify hydrogen-sulfide hazards and supply respirators, and it made no inquiry or respiratory-protection plan of its…

April 10, 1985
Citations vacated
COMM

B.G. Danis Company

Trench-sloping citation remains vacated

B.G. Danis employees installed pipe in a roughly nine-foot-deep trench dug through a mixture of sand, gravel, silt, and clay. OSHA alleged a willful violation because the trench walls were not sloped adequately for soft or unstable soil. The judge vacated the citation based on soil testing, expert…

April 10, 1985
Citations vacated
COMM

Vac-Air Alloys Corporation

Shear-guarding settlement cuts penalty to $150

Vac-Air processed and cut metal using six hydraulic shears that OSHA cited for unguarded points of operation. The judge affirmed the serious violation and proposed $360 penalty. In settlement, Vac-Air agreed to install an adjustable barrier guard on one shear and use that guarded machine for stock…

April 1, 1985
Settled
COMM

Schulte Corporation

Three electroplating-protection violations affirmed

Schulte manufactured bathroom fixtures and finished them in electroplating tanks containing corrosive chemical solutions. The Commission affirmed a nonserious violation because employees exposed to chromic acid received no periodic examinations after their pre-employment physicals. It also affirmed…

March 21, 1985
Citations affirmed
COMM

Metal Bank of America, Inc.

Lead-standard case settled for $2,500

OSHA cited Metal Bank for serious violations of the lead standard and proposed a $4,280 penalty. An earlier stipulation withdrew parts of the citation and reduced the proposed penalty for the remaining items to $3,000. Under the final settlement, Metal Bank withdrew its contest and petition for…

March 20, 1985
Settled
COMM

PPG Industries, Inc., Industrial Chemical Division

Undercharged SCBA item reduced to de minimis

PPG kept self-contained breathing apparatuses for trained employees performing shutdown or repair work during chemical leaks and other emergencies. OSHA found six cylinders charged to 1,850 or 1,900 psi instead of the manufacturer’s full-charge specification of 2,015 psi plus a permitted…

February 27, 1985
Modified
COMM

Mobay Chemical Corporation

Undercharged breathing-apparatus citation remains vacated

Mobay manufactured chemicals and maintained self-contained breathing apparatuses throughout a plant that used highly toxic substances. OSHA found four departmental units that were not fully charged and proposed a $350 serious penalty, although the rescue-team units and employees’ escape respirators…

February 27, 1985
Citations vacated
COMM

Austin Engineering Company, Inc.

Crane and trenching violations affirmed

Austin Engineering installed a water main in a deep trench using a truck crane. The Commission reversed the judge and found a nonserious fire-extinguisher violation because extinguishers on pickup trucks about 100 feet away were not available at the crane cab as the standard required; it assessed…

February 22, 1985
Citations affirmed
COMM

Stripe-A-Zone, Inc.

Traffic-safety case remanded for findings and a merits hearing

Stripe-A-Zone installed ceramic traffic buttons and stripes on a federally funded Texas highway project. OSHA issued four citations concerning traffic-control procedures, practices, and training. The company argued that Department of Transportation authority displaced OSHA jurisdiction, and the…

February 8, 1985
Remanded
COMM

ITT Grinnell Corp.

Court-remanded case returned for additional evidence

The Third Circuit returned ITT Grinnell’s case to the Commission. The Commission then remanded it to the chief administrative law judge for reassignment. The assigned judge was directed to let the parties present additional evidence on the issues covered by the court’s order and to conduct any…

January 31, 1985
Remanded
COMM

Sun Ship, Inc.

Record-disclosure citations vacated as untimely

Sun Ship built and repaired ships and provided its union with OSHA injury and illness logs after deleting employee names under its confidentiality policy. It later refused to provide complete records to OSHA unless the agency signed a nondisclosure agreement. The judge found two willful…

January 28, 1985
Citations vacated
COMM

Concrete Construction Co., Inc.

Backhoe power-line violations affirmed for $500

Concrete Construction used a backhoe to lay large pipe beneath energized power lines. The backhoe’s knuckle joint contacted a 7,620-volt line while an employee assigned to watch clearance was also steadying the pipe, and the employee was electrocuted. The Commission held that the crane…

January 25, 1985
Citations affirmed
COMM

Austin Bridge Company

Cable-guardrail citation vacated

Austin Bridge installed cable guardrails along an elevated highway exit ramp while a concrete-finishing screed moved along the deck. OSHA alleged that the cables deflected six to eight inches under less than 200 pounds of pressure, exceeding the standard’s requirement for minimum deflection. The…

January 22, 1985
Citations vacated
COMM

Westdale, Inc.

Review dismissed after company failed to brief

An administrative law judge affirmed a citation against Westdale after a hearing. Westdale petitioned for Commission review, and the Commission granted review and ordered briefing. The company did not file a brief, did not state that it would decline briefing, and did not respond to a later…

January 11, 1985
Procedural
COMM

Bridge Builders, Inc.

Citation withdrawn during Commission review

Bridge Builders obtained Commission review of its case, and the Commission issued a briefing notice. After further review, the Secretary concluded that continued litigation was not warranted and filed a notice withdrawing the citation. The Commission treated that notice as a motion and granted it…

January 9, 1985
Citations vacated
COMM

New England Container Company, Inc.

Valve item affirmed, noise items vacated

New England reconditioned used 55-gallon drums and operated a noisy blasting machine. The judge affirmed an other-than-serious, no-penalty violation because drums of flammable liquid lacked self-closing valves after installed valves broke and replacements were ordered. Chairman Buckley agreed that…

December 28, 1984
Mixed result
COMM

Schiavone Construction Company

Cord and underground-fire items reduced to de minimis

Schiavone was the prime contractor on a cut-and-cover subway-station project. The Commission found a de minimis extension-cord violation because heavy-duty cords lay near lumber with protruding nails, but the chance of insulation damage and injury was remote. The members divided on whether the…

December 19, 1984
Modified
COMM

Robert K. Bell Enterprises

Amusement-park guarding case remanded after evidence admitted

Bell operated an amusement park where OSHA cited unguarded pulleys and belts on the Scrambler ride. An administrative law judge invalidated the inspection warrant, suppressed the inspection evidence, and vacated the citation for lack of proof that Bell affected interstate commerce. The Commission…

December 19, 1984
Remanded
COMM

Barretto Granite Corporation

Late written contest accepted for a merits hearing

OSHA issued two repeated citations to Barretto Granite. Acting without counsel, the company disputed the citations at an informal conference held within the 15-working-day contest period. It sent letters confirming that dispute after the deadline, and the judge treated the letters as the notice of…

November 30, 1984
Remanded
COMM

Gates & Fox Company, Inc.

Two willful findings reversed and penalties reduced

Gates & Fox was a subcontractor building part of the Washington, D.C., subway system. The judge found willful violations because a truck crane operated within ten feet of a 4,000-volt line and because self-rescuers were not provided in a tunnel area without an advancing face. The Commission members…

November 30, 1984
Modified
COMM

Beauty Craft Tile of the Southwest, Inc.

Suppression reversed and citations remanded

OSHA obtained a warrant to inspect Beauty Craft's Oklahoma plant after complaints about removed machine safeguards and inadequate paint-shop ventilation. The judge suppressed the inspection evidence as the product of an overbroad warrant and then vacated the resulting serious and nonserious…

October 31, 1984
Remanded
COMM

Asbestos Textile Company, Inc.

Asbestos violations affirmed but willful claims rejected or deadlocked

Asbestos Textile processed raw asbestos in a rubber-products plant. OSHA cited exposure-limit, dust-control, monitoring, respirator, protective-clothing, housekeeping, locker, and medical-examination issues under the asbestos standard. The Commissioners agreed that the respirator, clothing…

October 31, 1984
Mixed result
COMM

Con-Agra, Inc.

Direction for review vacated at employee representative's request

The authorized employee representative sent a letter indicating that there might be no party interest in further adjudication of Con-Agra's case. The Commission treated the letter as a motion to vacate its direction for review and granted that motion. The order would become final after ten days…

October 25, 1984
Procedural

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.
  • Where they come from: Every page links the official OSHRC public release, and the full text on the page is that release. The plain-English summaries are written by Ezel.