🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242

Montana: Mechanic's Lien Waiver Form and Advance-Waiver Rules

verified against the statute 2026-07-23 2 statute sources

The short answer

Montana bans advance lien waivers. A construction contract may not require a contractor, subcontractor, or material supplier to waive the right to a construction lien or a payment-bond claim before it has been paid for the labor or materials furnished (MCA § 28-2-723). Once payment is made, a waiver is an ordinary contract document — Montana prescribes no statutory waiver form.

Ask Ezel about your situation

This is the general rule in Montana. Ezel applies current Montana law to your specific facts and answers with citations to the statutes.

Governing law and project scopeMontana Code Annotated Title 71, ch. 3, part 5 (Construction Liens, §§ 71-3-521 to 71-3-563). This part is the exclusive means by which a nonconsensual construction lien arises for a person furnishing services or materials under a 'real estate improvement contract' (§ 71-3-521). The advance-waiver ban is in the contracts title, MCA § 28-2-723. Private real-property work; public-project payment runs through payment bonds.
Advance or prospective waiverVoid. A construction contract 'may not contain provisions requiring a contractor, subcontractor, or material supplier to waive the right to a construction lien or a right to a claim against a payment bond before' that party 'has been paid for the labor, materials, or both … furnished' (MCA § 28-2-723). A pre-payment 'no-lien' or bond-waiver clause forced by the contract is unenforceable; only a waiver given after payment is allowed.
Statutory form requirementNone. Neither part 5 nor § 28-2-723 prescribes a waiver form. Part 5 supplies sample forms for the notice of the right to claim a lien (§ 71-3-532) and the lien notice itself (§ 71-3-536), but no conditional/unconditional or progress/final waiver form, warning, or field list. A post-payment waiver's wording is set by contract.
Waiver types and payment stageNo statutory conditional/unconditional or progress/final waiver labels and no statutory partial/through-date release. The statutory dividing line is timing, not form: a contract cannot require a waiver 'before' the claimant is paid (§ 28-2-723). Any conditional structure exists only if the parties draft it.
Payment and effectivenessSection 28-2-723 keys enforceability of a required waiver to whether the claimant 'has been paid'; a contract clause demanding a waiver before payment is void. There is no statutory cleared-check, actual-receipt, or evidence-of-payment condition, so any fund-clearance condition on a post-payment waiver must be written into the document.
Required contents, exceptions, and through dateNone prescribed. Neither § 28-2-723 nor part 5 lists required claimant, owner, amount, or through-date fields for a waiver, or any default carve-out for retainage, extras, change orders, or later work. A post-payment waiver reserves only what its own text reserves.
Rights released and reservedSection 28-2-723 protects two rights from a forced advance waiver: the construction lien under part 5 and 'a right to a claim against a payment bond.' A post-payment waiver reaches whatever of those rights its text releases. Part 5 does not create a separate stop-notice right to release.
Signature, authority, notary, and formatNot specified for a waiver. No statute requires a claimant's or agent's signature, an authority statement, notarization, a warning, an electronic-form rule, or attachments for a lien waiver. (The recorded lien notice must be signed and, under § 71-3-537, satisfaction acknowledged — those govern the lien filing, not a waiver.)
Noncompliance, remedies, and transition trapsA construction-contract provision requiring an advance (pre-payment) lien or bond waiver is 'void' (MCA § 28-2-723) — it cannot be enforced against the claimant, who keeps the lien and bond rights the clause tried to strip. There is no separate statutory penalty or nonconforming-waiver form rule. No pending bill would change this.

Compare this rule across all 50 states + DC →

Requirements one by one

An advance waiver is void

Montana's construction-lien rules live in Title 71, chapter 3, part 5, but the
rule that matters most for waivers sits in the contracts title. MCA § 28-2-723
says a construction contract "may not contain provisions requiring a contractor,
subcontractor, or material supplier to waive the right to a construction lien or
a right to a claim against a payment bond before" that party "has been paid for
the labor, materials, or both … furnished." So an owner or general contractor
cannot use the contract to force a "no-lien" promise up front. A clause that
tries to do so is void, and the worker keeps the lien — and the payment-bond
claim — that the clause tried to take away.

Two features are worth noting. First, the ban is not limited to the lien; it also
protects a claim against a payment bond, so a contract cannot force a party to
sign away bond rights in advance either. Second, the line the statute draws is
about timing. It does not forbid waivers; it forbids requiring one before
payment. After the claimant has been paid, a waiver is fully allowed.

There is no statutory waiver form

Montana prescribes no waiver form. The construction-lien part supplies a sample
"notice of the right to claim a lien" (§ 71-3-532) and a sample lien notice
(§ 71-3-536), but nothing for a waiver. There is no statutory conditional-versus-
unconditional wording, no progress-versus-final form, no required warning, and no
field list. A post-payment waiver is an ordinary contract document, and it means
what it says. Because no default statutory rule ties a waiver's effect to a check
actually clearing, a signer who wants that protection must write the condition
into the waiver.

What trips people up

The § 28-2-723 ban targets what the contract can require, not every waiver a
claimant might sign. A subcontractor who voluntarily signs an unconditional
waiver at a progress draw is not protected by the statute the way it would be
against a forced up-front "no-lien" clause. The protection is against advance
waivers extracted through the contract before payment; a waiver given at or after
payment is valid and can permanently release the lien.

Watch the payment-bond half of the rule. Section 28-2-723 voids an advance
waiver of "a right to a claim against a payment bond" just as it voids an advance
lien waiver. A contractor asked to sign broad "waiver of all claims" language
before payment should know that a pre-payment demand to give up bond rights is
also unenforceable under this section.

Common questions

Can a Montana construction contract make me waive lien rights before I'm paid?
No. MCA § 28-2-723 voids any contract provision requiring a contractor,
subcontractor, or material supplier to waive a construction lien or a payment-bond
claim before being paid for the work furnished.

Does Montana have a required lien-waiver form?
No. The construction-lien statutes include sample notice and lien forms but no
waiver form. A post-payment waiver's wording is set by contract.

If I sign a waiver after payment, is it effective even if the check bounces?
There is no statutory rule making a waiver ineffective when payment fails, so a
waiver can release the lien on its own terms. Tie the waiver to actual receipt and
clearance of the payment if you need that protection.

Statutes and sources

  • MCA § 28-2-723 (construction contracts requiring a lien or payment-bond waiver
    before payment are void) —
    https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0070/section_0230/0280-0020-0070-0230.html
    (accessed 2026-07-23)
  • MCA § 71-3-521 (scope; part 5 is the exclusive source of a construction lien on
    real estate) —
    https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0210/0710-0030-0050-0210.html
    (accessed 2026-07-23)

Source links

Every statute quoted above, linked, with the date we checked it.

MCA § 28-2-723 · accessed 2026-07-23
MCA § 71-3-521 · accessed 2026-07-23
This page is general legal information about pre-recording construction-lien waivers, not legal advice about a payment, draw, project, claim, or document. A waiver can permanently surrender lien, stop-notice, bond, payment, or other rights, and the result can depend on project type, claimant status, contract date, payment stage, actual receipt or clearance of funds, through date, exceptions, statutory wording, signature authority, and form presentation. A waiver is different from releasing or satisfying an already recorded lien. Verified against official sources on the date shown; use the current statutory form and have a qualified construction attorney review any disputed or high-value waiver before signing or relying on it.

Get the answer for your situation

You just read how Montana handles this in general. Ezel applies current Montana law to your facts and answers your specific question, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.