🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242

Indiana: Mechanic's Lien Waiver Form and Advance-Waiver Rules

verified against the statute 2026-07-23 4 statute sources

The short answer

Indiana voids covered construction-contract terms that require a lien claimant to waive lien or payment-bond rights before the claimant is paid, and it separately voids an agreement not to file a notice of intention to hold a lien. The statute prescribes no conditional, unconditional, progress, or final waiver form and no check-clearance rule. Class 2 structures and specified utility property are outside the anti-waiver section; qualifying no-lien clauses for those projects follow separate writing, acknowledgment, legal-description, and five-day recording rules.

Ask Ezel about your situation

This is the general rule in Indiana. Ezel applies current Indiana law to your specific facts and answers with citations to the statutes.

Governing law and project scopeInd. Code Title 32, art. 28, ch. 3, especially §§ 32-28-3-0.2, -1, -16, and -18. Section 16 covers Indiana building and structure improvement contracts but excludes Class 2 structures, their auxiliary improvements, and specified utility property.
Advance or prospective waiverFor covered projects, a contract term requiring a claimant to waive a real-estate lien or payment-bond claim before being paid is void; an agreement not to file a lien notice is also void (§ 32-28-3-16(b)-(c)).
Statutory form requirementNo statutory payment-stage waiver form or mandatory wording. Chapter 3 states the prepayment anti-waiver rule and special-project no-lien-clause rules but supplies no conditional, unconditional, progress, or final form.
Waiver types and payment stageNo statutory conditional/unconditional or progress/final forms. Section 32-28-3-16 uses payment as the dividing line but does not prescribe a post-payment waiver type or format.
Payment and effectivenessA covered contract cannot require waiver before the claimant is paid. The statute states no actual-receipt, cleared-check, joint-check, written-acknowledgment, or partial-payment effectiveness test for a separate waiver (§ 32-28-3-16(b)).
Required contents, exceptions, and through dateNo statutory claimant, owner, project, amount, check, through-date, retainage, extras, change-order, or disputed-claim fields for a payment-stage waiver. Special-project no-lien clauses instead require a writing, legal description, deed-style acknowledgment, and recording within five days (§ 32-28-3-1(f)).
Rights released and reservedBefore payment, § 32-28-3-16 protects both the real-estate lien and a payment-bond claim and voids an agreement not to file the lien notice. It does not prescribe release or reservation language for contract, delay, extras, retainage, or other claims.
Signature, authority, notary, and formatNo statutory signer-title, agent-authority, notarization, warning, type-size, attachment, or electronic-format rule for a payment-stage waiver. Deed-style acknowledgment applies only to the separate special-project no-lien contract under § 32-28-3-1(f).
Noncompliance, remedies, and transition trapsA prohibited provision is void. The anti-waiver provisions apply to contracts and subcontracts entered after June 30, 1999; § 32-28-3-16 excludes specified Class 2/utility work, while § 32-28-3-1(e)-(f) permits qualifying no-lien clauses there and preserves liens for work supplied before recording.

Compare this rule across all 50 states + DC →

Requirements one by one

Covered claimants cannot be required to waive before payment

Ind. Code § 32-28-3-16(b) protects both the real-estate lien and a payment-bond
claim:

A provision in a contract for the improvement of real estate in Indiana is
void if the provision requires a person ... to waive a right to ... a lien
against real estate; or ... a claim against a payment bond; before the person
is paid for the labor or materials furnished.

Subsection (c) separately voids a contract provision under which one or more
persons agree not to file the notice of intention that creates the lien.

Indiana prescribes no payment-stage waiver form

Chapter 3 supplies no conditional, unconditional, progress, or final waiver
form. Section 32-28-3-16 draws a line at payment, but it does not define a
cleared-check test, a through date, required reservations, a warning, a
signature block, or notarization for a post-payment waiver.

Certain special projects follow a different no-lien-clause path

Section 32-28-3-16 does not apply to Class 2 structures, their auxiliary
improvements, or specified utility property. Section 32-28-3-1(e)-(f) allows a
no-lien provision for listed projects only if the owner-prime contract is in
writing, identifies the real estate by legal description, is acknowledged like
a deed, and is recorded within five days after execution. Even then, the clause
does not affect a lien for labor, material, or machinery supplied before the
contract was recorded.

A pay-if-paid term cannot defeat the lien on covered work

For contracts within § 32-28-3-18, an obligor's receipt of payment from an
unrelated third person cannot be a condition precedent, limit, or defense to the
provider's right to record or foreclose the lien. That provision carries the
same principal Class 2 and utility exclusions.

What trips people up

The statute does not define what counts as being paid. Section
32-28-3-16(b) uses payment as the threshold but says nothing about whether a
check must clear. A private document's payment condition should not be mistaken
for statutory wording.

The project exception changes the analysis. A clause that is void on an
ordinary covered building project may fall under the separate § 32-28-3-1(e)-
(f) route on listed Class 2 or utility work. That route has recording and formality
requirements of its own.

The anti-waiver enactment has a contract-date rule. Section 32-28-3-0.2(b)
says the provisions now codified as §§ 16 to 18 apply only to contracts and
subcontracts entered after June 30, 1999.

Common questions

Can an Indiana construction contract require a lien waiver before payment?
Not on a project covered by § 32-28-3-16. The required prepayment waiver of
either the real-estate lien or payment-bond claim is void.

Does Indiana require conditional or unconditional waiver forms?
No. Chapter 3 prescribes no payment-stage waiver forms or mandatory waiver
wording.

Can a contract simply say the claimant will never file a lien notice?
Not on covered work. Section 32-28-3-16(c) makes that agreement void.

Statutes and sources

  • Ind. Code § 32-28-3-16, covered-project advance-waiver and no-file-clause
    rules — https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf
    (accessed 2026-07-23)
  • Ind. Code § 32-28-3-1(e)-(f), special-project no-lien clauses and formalities —
    https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf
    (accessed 2026-07-23)
  • Ind. Code § 32-28-3-0.2(b), contract-date transition —
    https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf
    (accessed 2026-07-23)
  • Ind. Code § 32-28-3-18, third-party-payment term cannot limit the lien —
    https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf
    (accessed 2026-07-23)

Source links

Every statute quoted above, linked, with the date we checked it.

Ind. Code § 32-28-3-16 · accessed 2026-07-23
Ind. Code § 32-28-3-1(e)-(f) · accessed 2026-07-23
Ind. Code § 32-28-3-0.2(b) · accessed 2026-07-23
Ind. Code § 32-28-3-18 · accessed 2026-07-23
This page is general legal information about pre-recording construction-lien waivers, not legal advice about a payment, draw, project, claim, or document. A waiver can permanently surrender lien, stop-notice, bond, payment, or other rights, and the result can depend on project type, claimant status, contract date, payment stage, actual receipt or clearance of funds, through date, exceptions, statutory wording, signature authority, and form presentation. A waiver is different from releasing or satisfying an already recorded lien. Verified against official sources on the date shown; use the current statutory form and have a qualified construction attorney review any disputed or high-value waiver before signing or relying on it.

Get the answer for your situation

You just read how Indiana handles this in general. Ezel applies current Indiana law to your facts and answers your specific question, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.