🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242

Arkansas: Mechanic's Lien Waiver Form and Advance-Waiver Rules

verified against the statute 2026-07-23 4 statute sources

The short answer

Arkansas's mechanics'- and materialmen's-lien statutes do not expressly prohibit an advance waiver and do not prescribe conditional or unconditional progress or final forms. The required residential owner notice says the owner may demand lien waivers from all suppliers and service providers stating that they have been paid in full before paying the contractor in full, or may use a joint check. The statute states no separate waiver wording, clearance, exception, signature, notarization, or noncompliance rule.

Ask Ezel about your situation

This is the general rule in Arkansas. Ezel applies current Arkansas law to your specific facts and answers with citations to the statutes.

Governing law and project scopeArk. Code tit. 18, ch. 44, subch. 1 (§§ 18-44-101 to -135), general private-property mechanics' and materialmen's liens. Section 18-44-115(a)(7)'s residential owner notice is the only operative waiver reference; § 18-44-131 concerns satisfaction of a lien already recorded.
Advance or prospective waiverNo express subchapter 1 statute voids or restricts a claimant's advance or prospective lien waiver. Statutory silence does not establish that every privately drafted no-lien term is enforceable.
Statutory form requirementNo statutory waiver form or required wording. The residential owner notice says the owner may require the contractor to present lien waivers from all suppliers and service providers stating they have been paid in full (§ 18-44-115(a)(7)).
Waiver types and payment stageNo statutory conditional/unconditional or progress/final categories. The only payment-stage reference is the residential owner's option to require paid-in-full waivers before paying the contractor in full (§ 18-44-115(a)(7)).
Payment and effectivenessThe owner-notice wording describes waivers stating that suppliers and service providers have been paid in full and offers a joint check to an unpaid provider and contractor. It states no check-clearance, failed-payment, evidence-of-payment, consideration, or effectiveness rule (§ 18-44-115(a)(7)).
Required contents, exceptions, and through dateThe only stated content is that all supplier and service-provider waivers say they have been paid in full for supplies and services under the contract. No claimant, owner, property, amount, check, through-date, retainage, extra, change-order, prior-payment, or disputed-claim field is prescribed.
Rights released and reservedThe statutory owner notice calls them 'lien waivers' but does not define which lien, bond, contract, payment, or other rights are released and supplies no automatic reservations (§ 18-44-115(a)(7)).
Signature, authority, notary, and formatNo waiver-specific signer, authorized-agent, title, notarization, acknowledgment, warning, type-size, attachment, delivery, or electronic-format rule appears in subchapter 1. The signature and all-caps rules in § 18-44-115 govern the owner notice itself, not the separate waivers it mentions.
Noncompliance, remedies, and transition trapsNo statute makes a premature or nonconforming pre-recording waiver void, unenforceable, or enforceable by its terms, and no waiver-specific damages or fees are stated. After a recorded lien is paid, § 18-44-131 separately requires record satisfaction within 10 days or liability for resulting injury and suit costs.

Compare this rule across all 50 states + DC →

Requirements one by one

Subchapter 1 does not create a waiver regime

Arkansas's general private-property lien scheme runs from §§ 18-44-101 to
18-44-135. Its official index covers lien entitlement and extent, notices,
filing, enforcement, bonds, fees, and satisfaction of recorded liens. It does
not list a section governing advance no-lien clauses or creating payment-stage
waiver forms.

That statutory silence answers the survey's advance-waiver and form questions,
but it does not promise that any private clause or form will be enforced. The
chapter simply does not state the rule.

The residential owner notice mentions paid-in-full waivers

Section 18-44-115(a)(7) prescribes an all-caps warning for owners of
residential real estate containing four or fewer units. As part of that warning,
the owner is told that they may require the contractor to present lien waivers
from every supplier and service provider stating that each has been paid in
full for supplies and services under the contract before the owner pays the
contractor in full (§ 18-44-115(a)(7)).

If a provider remains unpaid, the same notice tells the owner they may issue a
check jointly to that provider and the contractor. The statute does not turn
either option into a waiver form or state when the separate waiver becomes
effective.

The statute supplies no conditional or unconditional categories

The owner-notice sentence gives only one piece of content: the waivers state
that covered suppliers and service providers have been paid in full. It does
not name a through date, payment amount, check number, property description,
retainage, extras, change orders, disputed claims, signer authority, or notary.

It also does not define conditional progress, unconditional progress,
conditional final, or unconditional final waivers. Those labels in a privately
drafted Arkansas document do not carry a statutory meaning under Subchapter 1.

What trips people up

The all-caps presentation, signature, and certification requirements in §
18-44-115 belong to the statutory owner notice. They do not silently become
format or signature requirements for each supplier's separate lien waiver.

Section 18-44-131 addresses a different document after a lien is already on
record. Once the lien debt is paid, the creditor must enter satisfaction in the
circuit clerk's record; refusing or neglecting to do so for 10 days creates
liability for resulting injury and suit costs. That recorded-lien cleanup rule
does not prescribe a pre-recording payment-stage waiver (§ 18-44-131).

Common questions

Does Arkansas require four statutory lien-waiver forms?
No. Chapter 44, Subchapter 1 does not prescribe conditional or unconditional
progress or final forms.

Does Arkansas expressly void a no-lien clause signed before work?
No express anti-waiver provision appears in the mechanics'- and materialmen's-
lien statutes. The absence of a statute is not a guarantee that a particular
contract clause is enforceable.

What may a residential owner ask for before final contractor payment?
The statutory notice says the owner may require paid-in-full lien waivers from
all suppliers and service providers, or use a joint check when one remains
unpaid.

Statutes and sources

  • Arkansas Code Title 18, Chapter 44, Subchapter 1, complete official index —
    https://unicourt.github.io/cic-code-ar/transforms/ar/ocar/r78/gov.ar.code.title.18.html#t18c44sc01
    (accessed 2026-07-23)
  • Ark. Code § 18-44-115(a)(7), residential owner notice and paid-in-full waiver
    option —
    https://unicourt.github.io/cic-code-ar/transforms/ar/ocar/r78/gov.ar.code.title.18.html#t18c44s18-44-115
    (accessed 2026-07-23)
  • 2021 Ark. Act 984, post-release amendment limited to § 18-44-115(a)(4) —
    https://arkleg.state.ar.us/Home/FTPDocument?path=%2FACTS%2F2021R%2FPublic%2FACT984.pdf
    (accessed 2026-07-23)
  • Ark. Code § 18-44-131, satisfaction of a paid recorded lien —
    https://unicourt.github.io/cic-code-ar/transforms/ar/ocar/r78/gov.ar.code.title.18.html#t18c44s18-44-131
    (accessed 2026-07-23)

Source links

Every statute quoted above, linked, with the date we checked it.

Ark. Code § 18-44-115(a)(7) · accessed 2026-07-23
2021 Ark. Act 984 · accessed 2026-07-23
Ark. Code § 18-44-131 · accessed 2026-07-23
This page is general legal information about pre-recording construction-lien waivers, not legal advice about a payment, draw, project, claim, or document. A waiver can permanently surrender lien, stop-notice, bond, payment, or other rights, and the result can depend on project type, claimant status, contract date, payment stage, actual receipt or clearance of funds, through date, exceptions, statutory wording, signature authority, and form presentation. A waiver is different from releasing or satisfying an already recorded lien. Verified against official sources on the date shown; use the current statutory form and have a qualified construction attorney review any disputed or high-value waiver before signing or relying on it.

Get the answer for your situation

You just read how Arkansas handles this in general. Ezel applies current Arkansas law to your facts and answers your specific question, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.