🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242

Federal agency decisions, searchable in plain English.

Workplace-safety cases from the Occupational Safety and Health Review Commission (OSHRC) and mine-safety cases from the Federal Mine Safety and Health Review Commission (FMSHRC), each with a plain-English summary, the standards it cites, and whether it counts as precedent. More agencies are coming.

5,577 decisions and counting · Latest decision July 17, 2026
51 decisions 29 C.F.R. § 1926.451(g)(1)

No decisions match these filters

Try a different search term or clear the filters.

ALJ

Elite Builders, Inc.

Willful residential fall violation affirmed

Elite Builders' owner and four workers were framing the owner's two-story house in Gretna, Nebraska. OSHA found workers without eye protection, on an unsecured forklift-supported platform without fall protection, using an unguarded stairway, and framing on a roof without fall protection. The judge…

September 5, 2024 ·Patrick B. Augustine
Mixed result
ALJ

Ireland Contracting, LLC

Roofing citations vacated because subcontractors controlled the work

Ireland Contracting sold and scheduled two residential roof replacements in Gibsonia, Pennsylvania, then hired separate subcontractors to supply and supervise the roofing crews. OSHA cited Ireland Contracting for fall protection, eye protection, powered-industrial-truck, and scaffold violations…

October 12, 2023 ·Keith E. Bell
Citations vacated
COMM

Suncor Energy (U.S.A.) Inc.

Controlling-employer scaffold citation vacated

A contractor employee fell about 25 feet from an unguarded scaffold platform inside a refinery heater while not using personal fall protection. Suncor was the controlling employer but had no employees performing the work inside the confined space. The Commission found that the violative condition…

February 1, 2019
Citations vacated
ALJ

LM Sanderson Construction, Inc.

Three residential fall violations affirmed

LM Sanderson Construction employees framed townhomes while working about 20 feet above lower levels. Employees stood on stacked roof sheathing supported by an elevated telehandler fork, a foreman worked from the top plate of an exterior wall, and other employees installed sheathing on a steep roof…

October 13, 2017 ·William S. Coleman
Citations affirmed
ALJ

Georgia Carolina Stucco, Inc.

Three repeat scaffold violations affirmed

Georgia Carolina Stucco used another contractor's scaffolds while applying stucco to an assisted-living facility in Evans, Georgia. Three employees, including the company's foreman and competent person, worked as high as 20 feet 9 inches on platforms that were not fully planked and had no…

August 7, 2015 ·Sharon D. Calhoun
Citations affirmed
ALJ

DeMouy General Contracting, Inc.

Scaffold fall-protection item affirmed against owner and employee

The owner of DeMouy General Contracting and an employee worked about 20 feet above ground on a pump-jack scaffold without effective fall protection. The judge held that the owner was an employee under the OSH Act while performing construction work for the corporation, despite his belief that owners…

November 20, 2014 ·Heather A. Joys
Mixed result
ALJ

Absolute Roofing & Construction, Inc.

Four scaffold and fall-protection items affirmed

Absolute Roofing's worker repaired a steep church roof without fall protection above a scaffold that lacked base plates and guardrails. The judge treated Absolute Roofing and Absolute Exteriors as a single employer because they shared ownership, management, an office, employees, work, and their…

September 23, 2013 ·Carol A. Baumerich
Citations affirmed
ALJ

D & D Masonry Services, Inc.

Scaffold violations largely affirmed with reduced penalties

D & D Masonry used a multilevel scaffold for masonry work at a Georgia construction site. OSHA found wide platform gaps, damaged planks, unsecured scaffold legs, missing fall protection and a midrail, and a closed stepladder used as access. The judge affirmed those scaffold and ladder conditions as…

June 21, 2012 ·Stephen J. Simko, Jr.
Mixed result
ALJ

P.J. Spillane Company, Inc.

Respirator and scaffold citation items split

P.J. Spillane employees performed masonry tuck-pointing from scaffolds at a Boston worksite. The judge affirmed a serious respirator-program item after OSHA found a dirty, deteriorated respirator and facial hair that interfered with face seals. A missing safety data sheet for a corrosive cleaner…

June 13, 2012 ·John H. Schumacher
Mixed result
ALJ

Virginia Construction & Management Company, Inc.

Willful canopy fall violation affirmed

Two Virginia Construction employees chipped concrete on a canopy 16 feet 7 inches above a sidewalk without fall protection, safety-toe footwear, hard hats, or eye protection. They accessed the canopy by climbing an inadequately configured scaffold, and the company lacked qualified scaffold…

March 16, 2012 ·Stephen J. Simko, Jr.
Mixed result
ALJ

Frazier Masonry Corporation

Scaffold fall citation vacated for lack of employee proof

An OSHA compliance officer observed three people working near an unguarded opening on a 38-foot scaffold for about fifteen minutes without other fall protection. The judge found that the scaffold standard applied and that the observed condition violated its terms. OSHA did not identify the three…

August 9, 2010 ·Benjamin R. Loye
Citations vacated
ALJ

Denny Maize Construction

Eight serious construction items affirmed

Denny Maize Construction did not appear at the hearing, and OSHA's inspection evidence was undisputed. Workers lacked hard hats and eye protection, used circular saws with blade guards wedged open, and used damaged or improperly spliced extension cords. OSHA also documented an undersized scaffold…

March 22, 2010 ·Sidney J. Goldstein
Mixed result
ALJ

Masonry Arts, Inc.

Scaffold planking, access, and repeat guardrail items totaled $12,500

Masonry Arts employees performed block repair work from a scaffold platform approximately 12.5 feet above the ground at a new Florida high school gymnasium. The judge found a five-inch gap between planks, no safe ladder access, and no guardrail or other fall protection on the platform. He rejected…

September 29, 2008 ·Ken S. Welsch
Mixed result
ALJ

Standard Building Company, Inc., and Standard Systems, Inc.

Three items affirmed against one company and all items vacated against the other

Standard Building managed a restaurant renovation, and Standard Systems was identified as a related stucco contractor. The judge found that a subcontractor owner acted in part as Standard Building's site superintendent but lacked scaffold and powered-industrial-truck safety training. Standard…

December 20, 2007 ·Ken S. Welsch
Mixed result
ALJ

Africo Manufacturing, Inc.

Missing scissor-lift guardrails exposed workers to a 20-foot fall

Two Africo employees installed sprinkler piping from a scissor lift about 20 feet above a concrete floor with guardrails missing from one side and one end. The ALJ credited the OSHA officers' testimony and rejected the company president's claim that the employees had switched lifts without his…

November 23, 2007 ·Covette Rooney
Citations affirmed
COMM

Salco Construction, Inc.

Attorney-fee application denied

Salco Construction prevailed on one scaffold fall-protection item after the judge found that the Secretary had not proved a platform moved more than 14 inches from a building's eaves. Salco then sought $29,735.82 in fees and expenses under the Equal Access to Justice Act. The Commission found that…

July 18, 2007
Procedural
ALJ

Cipriano Martinez d/b/a Martinez Masonry

Illness did not excuse late contest and $38,000 penalty

OSHA issued Martinez Masonry serious, repeat, and other-than-serious citations involving scaffolds and hazard communication. The owner filed the notice of contest after the 15-working-day deadline and argued that flu-like symptoms prevented timely action. The medical records did not show that he…

January 17, 2007 ·Ken S. Welsch
Procedural
COMM

Martin C. Heck Brick Contracting Co.

Scaffold fee request partly granted and remanded

OSHA cited Heck for repeat scaffold fall-protection violations after observing employees on an unguarded scaffold about 21 feet above the ground. The underlying citation was vacated because testimony showed the employees were raising the scaffold, an activity governed by a different provision. In…

August 2, 2006
Remanded
ALJ

SALCO Construction, Inc.

Steel and platform violations result in $3,000 penalty

A SALCO employee bolted purlins while sitting on a steel beam about 18 feet above a concrete floor without fall protection. The judge found that he was not a connector because he was not working with hoisting equipment, so the 15-foot steel-erection fall rule applied. Two other employees worked…

May 30, 2006 ·Ken S. Welsch
Mixed result
ALJ

Benson Associates

Scaffold foundation, inspection, and fall-protection items affirmed

Benson Associates used a pump-jack scaffold and planks 13 to 14 feet above the ground while installing soffit and fascia on a Denver house. OSHA found that the scaffold legs lacked proper base plates and that the makeshift fall protection consisted of an Alumibench and boards attached with…

May 23, 2005 ·Sidney J. Goldstein
Citations affirmed
ALJ

Commercial Painting, Inc.

Forklift-supported work-platform violations affirmed

Commercial Painting used a rough-terrain forklift to support an employee-built work platform about 21 feet above the ground. The judge held that rough-terrain forklifts are equipment similar to front-end loaders under the scaffold standard and may support personnel platforms only when the…

April 11, 2005 ·Stephen J. Simko, Jr.
Citations affirmed
ALJ

S. A. Storer and Sons Co.

Repeat scaffold violation narrowed on remand

After court and Commission review, the judge was directed to narrow a repeat scaffold fall-protection citation. He vacated the allegation concerning a window-opening area but affirmed the violation at a materials-staging area. One employee there was exposed to a fall of about 19 to 20 feet, and the…

July 15, 2004 ·Stephen J. Simko, Jr.
Mixed result
COMM

S.A. Storer and Sons, Co.

Court-directed scaffold remand ordered

The D.C. Circuit vacated part of the Commission's earlier order concerning scaffold fall protection at two work areas. The court affirmed the violation at the materials-staging area but vacated it at the window-opening area. The Commission remanded the case to the ALJ with directions to enter those…

May 27, 2004
Remanded
ALJ

Artistic Enterprises, Inc.

Five scaffold and hard-hat violations affirmed

Two stucco workers used a two-level scaffold without hard hats, full planking, safe ladder access, fall protection, or toeboards at an Alabama hotel project. Artistic Enterprises argued that another company employed the workers, but the judge rejected that claim based on the workers' statements…

January 20, 2004 ·Nancy J. Spies
Citations affirmed
ALJ

Summit Contractors, Inc.

Subcontractor fall-hazard citations vacated for lack of knowledge

OSHA cited Summit, the general contractor for a large apartment project, for several fall hazards affecting subcontractor employees. The judge held that Summit's broad contractual and practical authority made it a controlling employer under the multi-employer worksite doctrine. She vacated the…

February 10, 2003 ·Nancy J. Spies
Citations vacated
ALJ

Kenny Industrial Services, LLC, d/b/a Kenny Manta Industrial Services

Scaffold fall-protection item affirmed

A Kenny Industrial Services employee applied fireproofing from a mobile scaffold near an unprotected fourth-floor edge. Although the scaffold platform itself was under 10 feet high, the worker could have fallen 20 to 24 feet to the second floor, and the scaffold's low toprail did not provide…

September 19, 2002 ·Covette Rooney
Mixed result
ALJ

S. A. Storer and Sons Company

Repeat scaffold fall violation affirmed with reduced penalty

S. A. Storer employees performed masonry work from scaffolding about 19 to 20 feet above the ground. The judge found that the overhand-bricklaying exception did not cover an open window or the materials staging area because employees were not laying block at those openings. A controlled access zone…

September 5, 2002 ·Stephen J. Simko, Jr.
Modified
ALJ

North Dallas Acrylic & Stucco, Inc., and its successors

Scaffold footing citation vacated, ladder-access and fall-protection citations affirmed

North Dallas Acrylic & Stucco was applying stucco from a three-tier scaffold at a WalMart construction site in Keller, Texas, when an OSHA officer inspected and cited three scaffold violations. One item claimed the scaffold legs lacked base plates and mud sills; the judge credited the crew leader's…

March 6, 2002 ·James H. Barkley
Mixed result
ALJ

A & W Construction Services, Inc.

Willful scaffold fall-protection citation affirmed at $20,000

A & W Construction, a Florida stucco and drywall contractor, was inspected while its crew did stucco work from a four-tier scaffold on a Daytona Beach building. Two 10-foot center sections at the second and third tiers, roughly 12 and 20 feet up, had no guardrails, and five employees worked there…

August 27, 2001 ·Ken S. Welsch
Citations affirmed
ALJ

Bredshall Plastering, Inc.

Unguarded table saw and missing scaffold guardrail affirmed, infeasibility and greater-hazard defenses rejected

Bredshall Plastering is a small Ohio contractor doing exterior insulation and stucco work. During work on a historical society office addition in Wilmington, an OSHA officer driving by saw a foreman on scaffolding without fall protection and stopped to inspect. OSHA issued a serious citation for an…

April 19, 2001 ·Ken S. Welsch
Citations affirmed
ALJ

Watkins Engineers & Constructors, Inc.

General contractor's scaffold citations vacated because the scaffold was being taken down

Watkins Engineers & Constructors was the general contractor building its own office in Tallahassee, Florida. A glass subcontractor's crew was up on a scaffold near a corner of the finished building when an OSHA compliance officer inspected. OSHA cited Watkins, the general contractor, for three…

February 12, 2001 ·Ken S. Welsch
Citations vacated
ALJ

North West Handling Systems, Inc., and its successors

Scissor-lift and fall-training violations affirmed, willful items reduced to serious

North West Handling Systems used a scissor lift while relocating warehouse pallet racks in Sandpoint, Idaho. A company installer removed part of the lift's guardrail, provided little safety training to two temporary workers, and used a forklift to push up the lift platform after it stopped rising…

December 20, 2000 ·Benjamin R. Loye
Modified
ALJ

Big Apple Wrecking and Construction Corp.

Willful scaffold fall-protection citation affirmed at $56,000, most serious items upheld

Big Apple Wrecking & Construction is a New York City demolition contractor. In mid-1998 OSHA inspected its demolition of a six-story theater building, where crews worked on the top level of scaffolding surrounding the structure. OSHA issued a serious citation, a repeat citation, and a willful…

October 13, 2000 ·Irving Sommer
Mixed result
COMM

McDevitt Street Bovis, Inc.

General contractor liable for a subcontractor's scaffold violations

McDevitt Street Bovis was the general contractor building a two-story medical center in Douglas, Georgia. During a 1997 inspection, OSHA found that a scaffold used by employees of subcontractor CPD Plastering was not fully planked, lacked cross-bracing, guardrails, and safe access, and had not been…

September 28, 2000
Citations affirmed
ALJ

The Haskell Company

Scaffold items affirmed for hazards exposing its own employee

The Haskell Company was the general contractor expanding a pilot training center in Savannah, Georgia. OSHA found Haskell's employee working 12 feet above the ground on an exterior tubular-frame scaffold with wide gaps in the planking, missing guardrails, and no access ladder. The superintendent…

September 25, 2000 ·Ken S. Welsch
Citations affirmed
ALJ

Hollywood Pool & Spa

Scaffold violations grouped with a $1,500 penalty

Hollywood Pool & Spa maintained swimming pools and was constructing its own building in Vestavia Hills, Alabama. OSHA cited five serious scaffold conditions involving incomplete planking, inadequate support, improper access, lack of a competent-person inspection, and missing fall protection. The…

June 23, 2000 ·Stephen J. Simko, Jr.
Modified
ALJ

A. Hansen Masonry, Inc.

Repeat scaffold violation affirmed, forklift item vacated

A. Hansen Masonry performed construction work in San Antonio, Texas. OSHA observed an employee making repeated trips on a twelve-foot scaffold whose southwest corner lacked guardrails, and the employee used no other fall protection. The judge found employer knowledge because the foreman knew the…

May 8, 2000 ·James H. Barkley
Mixed result
ALJ

Homes by Bill Simms, Inc.

All seven items vacated because the builder did not control its subcontractors

Homes by Bill Simms was a residential general contractor in Springboro, Ohio, that built custom homes using subcontractors. During an August 1999 inspection of three of its home sites, OSHA saw subcontractor employees committing scaffold and fall protection violations and issued Simms a seven-item…

March 27, 2000 ·Stephen J. Simko, Jr.
Citations vacated
ALJ

Malu Construction Co., and its successors

Jury-rigged scaffold items affirmed for $8,000

Malu called its framing workers independent subcontractors, but it supplied their scaffold and safety equipment, assigned their work, provided training, and retained authority to stop work. Judge Stanley M. Schwartz therefore treated them as Malu employees under the common-law control test. OSHA…

September 17, 1999 ·Stanley M. Schwartz
Mixed result
ALJ

North Pacific Enterprises

Unprotected 25-foot scaffold work affirmed for $525

Two North Pacific employees worked from a narrow board on a wooden scaffold more than 25 feet above a concrete parking lot without guardrails or personal fall protection. The company president had seen the same conduct the previous day but did not stop or discipline the workers, and the foreman…

September 15, 1999 ·Nancy J. Spies
Citations affirmed
ALJ

Groesbeck Masonry, Inc.

Scaffold decking, guardrail, and training items affirmed

Two Groesbeck Masonry employees washed an acid-cleaned brick wall from a scaffold 10 to 12 feet high while straddling two planks, without full decking or guardrails. A third employee dismantled the level above, but the workers had not been specifically trained to wait until the lower level was…

September 7, 1999 ·Benjamin R. Loye
Modified
ALJ

The Pike Company, Inc.

Edge, scaffold, and ground-fault items affirmed

At a prison construction project, Pike employees worked near a 13-foot unguarded edge, and another employee poured concrete from an unguarded outrigger scaffold about 20 feet high without a proper access ladder. Judge Ann Z. Cook rejected infeasibility because the edge work did not require removal…

June 21, 1999 ·Ann Z. Cook
Modified
ALJ

Bast Hatfield, Inc.

Scaffold and ladder items affirmed

Bast Hatfield employees performed masonry work from scaffolds at a church construction project in New York. Judge Robert A. Yetman denied Bast's Fourth Amendment challenge because the OSHA inspector observed the work from a parking area that remained open to church visitors and the public. He…

May 26, 1999 ·Robert A. Yetman
Mixed result
ALJ

New England Synthetic Systems, Inc.

Scaffold and electrical violations affirmed for $30,000

New England Synthetic Systems replaced exterior walls at an apartment complex in Weymouth, Massachusetts. Judge Robert A. Yetman affirmed violations involving unprotected temporary electrical wiring, lifelines tied to vent curbing and exposed to sharp edges, incomplete scaffold planking, unsafe…

April 22, 1999 ·Robert A. Yetman
Mixed result
COMM

New Age, Inc.

Mandatory $500 penalty assessed for scaffold fall hazard

New Age performed masonry work from a four-tier scaffold at a construction site in New Braunfels, Texas. Five to seven employees were finishing masonry work or preparing to dismantle the scaffold while required guardrails were missing or replaced by loose, incomplete cables. The administrative law…

April 20, 1999
Citations affirmed
COMM

Easthaven Masonry, Inc.

Denial of E-Z Trial procedure reversed

Easthaven Masonry requested the Commission's simplified E-Z Trial procedure for a scaffold case. The Secretary objected only that some discovery might be needed, and the Chief Administrative Law Judge denied the request. The Commission held that the stated need for discovery was not enough on the…

February 3, 1999
Remanded
ALJ

West Winds Construction, Inc.

Scaffold planking and fall-protection violations affirmed

West Winds Construction employees repaired plaster from partially dismantled scaffold platforms that were not fully planked and had no guardrails. The workers faced falls of about 18 to 20 feet, and the site foreman directed and observed the work. Chief Judge Irving Sommer imputed the foreman's…

October 13, 1998 ·Irving Sommer
Citations affirmed
ALJ

Island Lathing & Plastering, Inc.

Scaffold and ladder violations affirmed with $55,000 in penalties

Island Lathing & Plastering was performing interior plastering work at a multistory theater project. OSHA found an employee working from an unlocked mobile scaffold beside a balcony edge without fall protection, then descending a ladder while facing away from it. The judge found that the foreman…

July 31, 1998 ·Irving Sommer
Citations affirmed
COMM

Western Waterproofing Co., Inc.

Five suspension-scaffold items affirmed

Western Waterproofing employees sprayed a building from a two-point suspension scaffold supported by outrigger beams at heights up to 22 feet. The judge found that the outrigger supports lacked required bearing, anchorage, and bracing, and that the scaffold lacked a secondary tieback, safety belts…

March 17, 1977
Mixed result
COMM

Elmer Vath, Painting Contractor

Lifeline and fatality-reporting violations affirmed

Elmer Vath hired two painters to paint a building cornice from a two-point suspended scaffold and supplied the scaffold materials. One painter fell about 60 feet and died after a supporting beam slipped; he had removed his safety belt shortly before the incident. The judge found that the painter…

July 2, 1974
Mixed result
COMM

The Austin Co., Inc.

Scaffold and ladder violations affirmed

The Austin Company was constructing a hospital addition where two employees worked from a suspension scaffold without safety belts or lifelines. Two other employees worked on a 12-foot scaffold without guardrails. The judge treated those conditions as a serious violation and assessed $550. He…

July 1, 1974
Mixed result

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.
  • Where they come from: Every page links the official OSHRC public release, and the full text on the page is that release. The plain-English summaries are written by Ezel.