🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
TX 8707L0823E12 Sales and/or Use Tax (State,Local,MTA) 1987-07-07

Could a contractor or subcontractor claim the 1987 prior-contract exemption without having its own written contract or bid with suppliers?

Short answer: Yes, if the owner-general-contractor contract or bid met the pre-January 1, 1987 timing and fixed-price requirements. The contractor did not need separate written supplier contracts.

Apply this to your situation

This page answers the general question as of 1987. Ezel answers yours, under current Texas tax law, with citations.

Currency note: this ruling is from 1987
Subsequent statutory amendments, regulation changes, court decisions, or later rulings may have changed the analysis. Treat this page as historical context, not current tax advice. Verify current law before relying on any specific rule, rate, or position mentioned here.
Disclaimer: This 1987 Texas Comptroller letter concerns a transition exemption tied to contracts or bids made before January 1, 1987. That historical cutoff and the letter's approved certificate should not be treated as current law. The conclusion also depends on a qualifying fixed-price owner-general-contractor agreement or bid. STAR documents may no longer represent current policy even when not marked superseded. Identities are redacted. This summary is informational only and is not legal or tax advice.
About this page: The plain-English summary, reader guidance, and Q&A below were written by Ezel based on the official state tax ruling. The original ruling (linked on this page) is the authoritative source for any reliance.

Plain-English summary

The Comptroller explained that the prior-contract exemption covered items purchased under either a written contract signed by both parties before January 1, 1987, or a seller's written bid issued before that date. The seller and purchaser also had to be bound to a fixed price or to a price based on criteria neither party controlled.

For this contractor or subcontractor, qualifying purchases could rely on the contract or bid between the general contractor and the owner. The contractor or subcontractor did not also need a written bid or contract with each supplier.

The Comptroller found that the submitted example prior-contract exemption certificate was completed properly and could be given to suppliers for qualifying items.

What this means for you

The historical exemption followed the qualifying project-level agreement rather than requiring a separate pre-cutoff contract at every link in the supply chain. The purchased items still had to be used to fulfill the qualifying contract.

Common questions

What timing qualified? A written contract signed by both parties before January 1, 1987, or a seller's written bid issued before that date.

Did the price have to be fixed? Yes, unless it was based on criteria outside the parties' control.

Did the contractor need written agreements with suppliers? No.

Could the submitted certificate be used? Yes, for qualifying items.

Citations and references

  • No statute or rule number is cited in the ruling text.

Source

Original ruling text

COMPTROLLER OF PUBLIC ACCOUNTS
STATE OF TEXAS
AUSTIN, 78774

BOB BULLOCK
Comptroller July 7, 1987




Dear ***:

Thank you for your recent letter regarding prior contract exemptions.

In order to qualify for a prior contract exemption, the items to be
purchased must be covered by either a written contract signed by both
parties prior to January 1, 1987 or a written bid issued by the seller
(general contractor in this case) before that date. In addition, both
the seller and the purchaser must be bound by a fixed price, or the
price must be based on criteria not controlled by parties to the
contract.

In your case, the items to be purchased to fulfill your contract with
the general contractor qualify for the prior contract exemption if the
contract/bid between the general contractor and owner meets the
requirements outlined above. It is not necessary for the contractor/
sub-contractor to have a written bid or contract with its supplier(s)
for the exemption to apply.

The example "Prior Contract Exemption Certificate" you submitted with
your letter is completed properly and should be submitted to your
supplier(s) for qualifying items.

This opinion is based on the facts presented. If there are additional or
different facts, the opinion may change.

If you have any questions or need more information, please call me at
1-800-252-5555 toll free from anywhere in Texas. The regular number is
512/463-4600. You may write me at the Tax Administration Division.

Sincerely,
Sandi Skaggs
Tax Policy Section
Tax Administration Division

Get today's answer for your situation

You just read a 1987 ruling on this question. Ezel checks current Texas tax law and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.