Clean-energy bond spending period extended
Apply this to your situation
This page covers one taxpayer's ruling from 2021, which can't be cited as precedent. Ezel answers your situation under the current Code and IRS guidance, with citations.
Plain-English summary
A public authority issued new clean renewable energy bonds to finance solar equipment for a city's exclusive use. Significant equipment defects, contractor errors, resulting litigation, and pandemic delays prevented all bond proceeds from being spent within the original three-year period. Installation had reached substantial completion, the city and contractor agreed to mediation, and the authority expected to resolve the remaining issues and spend the funds by a specified later date. The IRS found reasonable cause for the delay and continued due diligence, and extended the expenditure period to that date. It expressed no opinion on whether the bonds otherwise qualified as tax credit bonds.
Ruling snapshot
- Question: Could the authority receive more time to spend the remaining clean-energy bond proceeds?
- Outcome: Approved.
- Key authorities: IRC §§ 54A(d)(2)(B) and 54C(a)
Full text (IRS public release)
Internal Revenue Service Department of the Treasury
Washington, DC 20224
Number: 202118007 Third Party Communication: None
Release Date: 5/7/2021 Date of Communication: Not Applicable
Index Number: 54A.00-00
Person To Contact:
------------------------------------------ ----------------, ID No. -----------
------------------------------------ Telephone Number:
------------------- --------------------
------------------------------ Refer Reply To:
------------------------- CC:FIP:B05
PLR-128873-20
Date:
February 11, 2021
LEGEND:
Authority = ------------------------------------------------------------
Bonds = ------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------
------------------------------------
City = --------------------------------------
Contractor = ------------------------------
State = ---------------
a = -------------
b = -----------------
Date 1 = --------------------------
Date 2 = --------------------------
Date 3 = -----------------------
Date 4 = -----------------------
PLR-128873-20 2
Dear ------------:
This is in response to your request under § 54A(d)(2)(B)(iii) of the Internal Revenue
Code1 (the Code) for an extension of the expenditure period for the available project
proceeds of the Bonds.
Facts and Representations
You make the following factual representations. Authority is a constituted authority
authorized to issue bonds on behalf of City. Authority issued the Bonds on Date 1 and
designated them as new clean renewable energy bonds within the meaning of § 54C(a).
The Bonds were issued for the purpose of financing solar equipment (the "Equipment")
to produce electricity for the exclusive use of City. Contractor was engaged to provide
and install the Equipment on several City sites (the “Project”).
The original three-year expenditure period for the Bonds under § 54A(d)(2)(B)(i) (the
“Original Expenditure Period”) expired on Date 2. As of the issue date of the Bonds,
Authority expected all available project proceeds of the Bonds to be spent not later than
Date 2.
Subsequent to the issuance of the Bonds, Contractor proceeded with due diligence to
provide and install the Equipment. Prior to submitting this request, the District had
expended Bond proceeds totaling at least $a.
Although work on the Project by Contractor and expenditure of Bond proceeds initially
proceeded with due diligence, unexpected events have resulted in unforeseeable
delays in the expenditure of the remaining $b of available project proceeds. Authority
represents that significant defects in the Equipment and errors by Contractor caused
delays in expenditures of Bond proceeds. City and the Contractor have been engaged
in litigation regarding these matters. In civil court proceedings, City raised various
issues, including Contractor's failure to provide bonding as required by State statute,
Contractor's failure to substantiate costs under the contract with the City, defects in a
certain subcontractor's construction resulting in Equipment damage, and Contractor's
failure to timely complete construction. Lastly, the Coronavirus Disease 2019 pandemic
has significantly delayed the civil court proceedings and thus, resolution of the dispute
and expenditure of the remaining unspent Bond proceeds.
As of Date 3, Equipment installation has continued and has reached substantial
completion. In addition, City and Contractor have agreed to resolve their dispute
through mediation.
1References to §§ 54A and 54C are to those sections of the Code as in effect prior to repeal by the Tax
Cuts and Jobs Act, Pub. L. No 115-97, § 13404, 131 Stat. 2138 (2017). The repeal is effective for bonds
issued after December 31, 2017, and thus, §§ 54A and 54C still apply to the Bonds.
PLR-128873-20 3
Authority expects that any remaining issues relating to the Equipment and installation
and the dispute with the Contractor will be resolved, and that the remaining available
project proceeds of the Bonds will be expended not later than Date 4.
Authority submitted its request for this ruling prior to the expiration of the Original
Expenditure Period.
Law and Analysis
Section 54A(d)(1) provides in part that a new clean renewable energy bond is a
qualified tax credit bond for purposes of § 54A if it is part of an issue that meets the
requirements of §§ 54A(d)(2) through (5).
Section 54A(d)(2)(B)(i) provides in part that to the extent that less than 100 percent of
the available project proceeds of the issue are expended by the close of the expenditure
period for 1 or more qualified purposes, the issuer shall redeem all of the nonqualified
bonds within 90 days after the end of such period.
Section 54A(d)(2)(B)(ii) provides that for purposes of subpart I (that is, §§ 54A through
54F), the term “expenditure period” means, with respect to any issue, the 3-year period
beginning on the date of issuance. Such term shall include any extension of such
period under § 54A(d)(2)(B)(iii).
Section 54A(d)(2)(B)(iii) provides that upon submission of a request prior to the
expiration of the expenditure period (determined without regard to any extension under
this clause), the Secretary may extend such period if the issuer establishes that the
failure to expend the proceeds within the original expenditure period is due to
reasonable cause and the expenditures for qualified purposes will continue to proceed
with due diligence.
Section 54A(d)(2)(C)(ii) provides that for purposes of § 54A(d)(2), in the case of a new
clean renewable energy bond, a “qualified purpose” means a purpose specified in
§ 54C(a)(1).
Section 54A(e)(4) defines “available project proceeds” to mean (A) the excess of (i) the
proceeds from the sale of an issue, over (ii) the issuance costs financed by the issue (to
the extent that such costs do not exceed 2 percent of such proceeds), and (B) the
proceeds from any investment of the excess described in § 54A(e)(4)(A).
As of the issue date of the Bonds, Authority reasonably expected that all the available
project proceeds of the Bonds would be spent within the Original Expenditure Period.
The failure to spend all the available project proceeds by the expiration of the Original
Expenditure Period on Date 2 has been caused by events that were not reasonably
expected at the time the Bonds were issued and were outside of the control of Authority
or City. These events caused a significant delay in spending the Bond proceeds.
PLR-128873-20 4
Authority will exercise due diligence in spending the remaining available project
proceeds on the Project. Authority expects that all available project proceeds of the
Bonds will be spent not later than Date 4.
Conclusion
Under the facts and circumstances of this case, we conclude that Authority’s failure to
expend all the available project proceeds of the Bonds by Date 2 is due to reasonable
cause and that the continued expenditure of the proceeds for qualified purposes will
proceed with due diligence. Therefore, Authority is granted an extension of the Original
Expenditure Period with respect to the Bonds until Date 4.
Except as expressly provided herein, no opinion is expressed or implied concerning the
tax consequences of any transaction or item discussed or referenced in this letter,
including whether the Bonds are qualified tax credit bonds under § 54A. This ruling is
directed only to the taxpayer requesting it. Section 6110(k)(3) provides that it may not
be used or cited as precedent.
In accordance with a Power of Attorney on file with this office, a copy of this letter is
being sent to your authorized representative.
The ruling contained in this letter is based upon information and representations
submitted by Authority and accompanied by penalty of perjury statements executed by
PLR-128873-20 5
the appropriate parties. While this office has not verified any of the materials submitted
in support of the request for a ruling, it is subject to verification upon examination.
Sincerely,
Associate Chief Counsel
(Financial Institutions and Products)
By: ________________________
Zoran Stojanovic
Assistant to the Branch Chief
Branch 5
cc:
Get today's answer for your situation
You just read what the IRS ruled for one taxpayer in 2021, and it can't be cited as precedent. Ezel checks the current Internal Revenue Code and IRS guidance and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.