7 decisions 29 C.F.R. § 1926.703(a)(2)

No decisions match these filters

Try a different search term or clear the filters.

ALJ

Southern Pan Services Company

Two willful formwork violations affirmed for $125,000

Southern Pan Services Company was the concrete formwork contractor on a six-story parking structure that partially collapsed during a concrete pour. One Southern Pan employee died, another was seriously injured, and more than twenty other workers were injured. After the Commission remanded the…

May 19, 2016 ·Heather A. Joys
Citations affirmed
COMM

Southern Pan Services Co.

Parking-garage collapse items remanded under exposing-employer and supervisor-knowledge rules

A parking garage partially collapsed during a concrete pour, killing one Southern Pan employee and injuring another along with more than twenty workers. The Commission held that the construction-load standard applied to the conditions and that Southern Pan, as an exposing employer, could have a…

December 18, 2014
Remanded
COMM

Altor, Inc., and/or Avcon, Inc.

Eight willful items affirmed with $412,000 penalty

OSHA cited extensive hard-hat, open-edge, and floor-hole hazards during construction of a sixteen-story concrete building. The Commission held that Altor and Avcon operated as a single employer because they shared a worksite, management, ownership, office support, and integrated operations. The…

April 26, 2011
Modified
ALJ

Fabi Construction, Inc., and Pro Management Group

Parking-garage collapse decision assesses $21,000

Four parking-garage levels collapsed during concrete placement at an Atlantic City project, killing four employees and injuring 21. The judge found serious general duty violations because reinforcing mesh did not follow the approved shop drawings and longitudinal steel was installed contrary to…

May 1, 2006 ·Covette Rooney
Mixed result
COMM

Major Construction Corp., Inc. and Michael J. Polites

Fall citations largely affirmed with $223,200 penalty

Major Construction was the concrete subcontractor on a 32-story structure where OSHA documented extensive fall-protection and related violations, including violations after an imminent-danger notice was posted. The Commission largely upheld the judge's findings on feasibility, employer…

January 26, 2005
Mixed result
ALJ

Concrete Metal Forms, Inc.

Formwork violations affirmed after deck collapse

Concrete Metal Forms, Inc. designed and erected formwork for a new county jail in Alabama. During the third-level concrete pour, the deck collapsed and 22 employees were injured. CMF argued that the general contractor caused the collapse by directing an uneven pour despite CMF's warning. The judge…

January 15, 1998 ·Ken S. Welsch
Mixed result
COMM

Simpson, Gumpertz & Heger, Inc.

Concrete-formwork citations against engineer vacated

Simpson, Gumpertz & Heger provided structural-design and consulting services for a laboratory-building project where metal decking collapsed during a two-layer concrete pour. OSHA cited SGH for allegedly inadequate formwork support and missing shoring plans. The Commission held that design and…

August 28, 1992
Citations vacated

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.