Wayne J. Griffin Electric, Inc.

Electrical contact violations affirmed

Wayne J. Griffin Electric installed replacement substations during a large electrical upgrade at a New Hampshire office complex. An electrician was seriously injured when his face contacted an energized bus bar while he worked inside a switchgear compartment believed to be de-energized. The judge…

June 15, 2017 ·Carol A. Baumerich
Citations affirmed
COMM

Monroe Drywall Construction, Inc.

Serious-item penalties increased to $6,300

Monroe Drywall employees worked near exposed energized wires at a Florida construction site where a worker died after contacting the electrical hazard. The affirmed violations involved failure to train employees to recognize and avoid unsafe conditions and failure to determine the status of exposed…

September 30, 2013
Modified
COMM

Monroe Drywall Construction, Inc.

Employer finding reversed and citations remanded

A drywall worker was electrocuted after contacting exposed wiring at a retail-store renovation. The judge vacated the citations because he found OSHA had not proved that Monroe Drywall employed the workers performing the drywall work. The Commission held that the judge improperly discounted worker…

April 19, 2013
Remanded
ALJ

Florida Power and Light Company

Arc-flash citations affirmed

An electrical contractor at Miami International Airport needed Florida Power and Light to open a meter can and remove a protective plate so it could replace wiring and a breaker. The FPL employee raised an energized bypass handle without first asking what work had been done or inspecting the…

October 24, 2011 ·Dennis L. Phillips
Citations affirmed
ALJ

Shaw Environmental & Infrastructure, Inc.

Electrical citation items vacated

A Shaw electrician was severely burned by an electrical arc after opening an energized panel box at a Maryland waste-removal project. OSHA concluded that he was loosening a live lug bolt with an Allen wrench, while Shaw's investigation concluded that a wrench left on top of the box fell when the…

June 20, 2005 ·Covette Rooney
Citations vacated
ALJ

Miller Electric Company

Electrical violations affirmed before Commission remand

A Miller Electric journeyman was electrocuted while connecting a light fixture to an energized 277-volt circuit at a medical-center construction project. The judge found that Miller permitted work near the energized circuit and failed to ascertain and warn employees that the circuit was live. She…

September 4, 2001 ·Nancy J. Spies
Mixed result
COMM

Miller Electric Company, Inc.

Electrical case remanded after testimony was misunderstood

Miller Electric received three serious electrical citations after a journeyman electrician was electrocuted while connecting a light fixture to an energized circuit. The administrative law judge affirmed two items and rejected the company's employee-misconduct defense. The Commission found that the…

June 8, 2001
Remanded
COMM

CMC Electric, Inc.

Electrical-hazard and worksite-safety items affirmed

CMC Electric sent three journeyman wiremen to install electrical service at a cellular-telephone construction site near Andover, Ohio. An employee died after climbing a utility pole and contacting an energized 7,200-volt line that was not shown on the work schematic. CMC had not inspected for…

April 26, 1999
Citations affirmed
ALJ

National Acoustics, Inc.

Housekeeping citation tossed, but electrical-hazard citations upheld against a demolition subcontractor

National Acoustics was a demolition and cleanup subcontractor on a hotel renovation in Chicago. OSHA inspected in August 1996 and issued a serious citation with three items: one for scrap lumber with protruding nails and other debris on the floor, and two for letting employees work close to live…

August 1, 1997 ·Irving Sommer
Mixed result
ALJ

Stein, Inc.

Crane inspection and power-line clearance items affirmed

Stein provided a crane and crane operator for installation of a truck scale at an Ohio steel-mill site. A ground worker employed by the scale contractor was electrocuted when the crane boom contacted a 13,000-volt power line. The judge found that Stein remained an employer responsible for its…

May 8, 1995 ·Nancy J. Spies
Mixed result
ALJ

Hirsch Electric Company

Energized-wiring item affirmed, penalty reduced to $1,000

Hirsch Electric installed energized wiring for operating rooms under construction at Hillcrest Hospital in Ohio. A flexible conduit containing 270-volt lines hung into the area where another contractor's employees were installing metal duct diffusers, and one worker received an electrical shock…

December 19, 1994 ·Robert A. Yetman
Modified

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.
  • Where they come from: Every page links the official OSHRC public release, and the full text on the page is that release. The plain-English summaries are written by Ezel.