ALJ

Keystone Construction Corp.

Failure to assess deteriorated tank roof affirmed

Keystone Construction repaired and repainted concrete water tanks using a containment system supported on the tank roof. While employees removed deteriorated concrete and erected scaffolding, the Smithtown tank roof collapsed and three employees fell about 35 feet. Judge Covette Rooney found that…

December 24, 1998 ·Covette Rooney
Citations affirmed
ALJ

JHL Constructors, Inc.

Subcontractor fall-protection citation vacated

JHL Constructors was the general contractor for construction of a middle school. OSHA cited JHL after a masonry subcontractor employee worked near an unprotected edge about 14 feet above the ground without fall protection. The Secretary proved that the standard applied, its terms were not met, and…

December 21, 1998 ·Sidney J. Goldstein
Citations vacated
ALJ

AFO, Inc.

Settlement approved with $17,000 penalty

AFO contested citations alleging willful and serious violations at a Pennsylvania worksite. The parties reached a written settlement under the Commission's settlement rule. The agreement changed Citation 2 items from willful violations to violations under section 17 of the Act while leaving the…

December 21, 1998 ·Michael H. Schoenfeld
Settled
ALJ

Dover Elevator Company

Access and fall-protection citations vacated

Dover Elevator Company was installing elevators in an addition to a federal courthouse and post office in Victoria, Texas. OSHA cited floor holes, inadequate guardrails, improper elevated access, and portable ladders at the site. Because the citation and complaint alleged violations only on the…

November 30, 1998 ·James H. Barkley
Citations vacated
ALJ

Jensen Road Company

Crane boom-tip scaffold citation vacated

Jensen Road Company used a scaffold attached to a crawler crane boom to position employees beneath a bridge deck while they removed plywood forms. OSHA alleged that this use violated the crane manufacturer's specifications and limitations. The manufacturer's notices warned that the crane was not…

November 25, 1998 ·Ken S. Welsch
Citations vacated
ALJ

Mr. Fox Tire Company, Inc.

Late notice of contest dismissed

OSHA issued Mr. Fox Tire Company a serious citation after inspecting its business. The company received the citation on December 19, 1997, making January 14, 1998 the deadline for a written notice of contest, but it submitted only an abatement verification form during that period. Its owner later…

November 25, 1998 ·Irving Sommer
Procedural
ALJ

Michael J. Gresh Painting Co., Inc.

Bridge fall-protection violation affirmed

Michael J. Gresh Painting employees secured containment tarps on a bridge superstructure about 25 to 30 feet above the roadway without tying off. Six employees violated the company's fall-protection policy, including the foreman, who was not wearing a safety belt or harness. Judge Richard…

November 23, 1998 ·Richard DeBenedetto
Mixed result
COMM

Honey Creek Contracting Co.

Review vacated after employer failed to brief

Honey Creek Contracting petitioned for Commission review of two administrative law judge decisions concerning excavation work in Homer City, Pennsylvania. After directing the cases for review, the Commission ordered Honey Creek to file a brief or a letter in lieu of a brief within 40 days. Honey…

November 16, 1998
Procedural
COMM

United House of Prayer

Review vacated after Secretary missed briefing deadline

OSHA cited the United House of Prayer for exit and sprinkler conditions after a fire in a tenant's New York City store caused the deaths of seven store employees. The administrative law judge granted summary judgment to the Church because it had no employees at the renovation site, did not create…

November 16, 1998
Procedural
ALJ

Akzo Nobel Chemicals, Inc.

Emergency-action and lockout violations yield $12,000

OSHA inspected Akzo Nobel Chemicals' organic peroxide plant and initially proposed $240,000 for serious, willful, repeat, and other-than-serious violations. The Secretary withdrew most items, and Judge Robert A. Yetman vacated several remaining allegations for insufficient proof. Akzo intended…

November 13, 1998 ·Robert A. Yetman
Mixed result
ALJ

BCB Construction, Inc.

Faxed citation triggered contest deadline

OSHA cited BCB Construction after inspecting a multi-employer construction site where an accident caused one employee's death and another employee's serious injury. Certified-mail delivery to BCB's address of record failed after three attempts, but OSHA faxed the citation to a law firm that said it…

October 30, 1998 ·Irving Sommer
Procedural
ALJ

Christie Constructors, Inc.

Barge safety citations produce $2,750 penalty

Christie Constructors performed bridge construction from two connected barges on the Columbia River. Judge Stanley M. Schwartz held that federal OSHA retained jurisdiction over non-maritime construction on vessels in navigable waters despite Washington's state plan. He affirmed serious violations…

October 26, 1998 ·Stanley M. Schwartz
Mixed result
ALJ

The Boeing Company, d/b/a Boeing Commercial Airplane Group--Wichita Division

Cited electrical standards held inapplicable

Two Boeing electricians sustained second-degree burns when switchgear failed as they opened a cabinet at the company's Wichita aircraft plant. OSHA cited general-industry electrical standards addressing recognized equipment hazards and moisture in cabinets. Judge Nancy J. Spies found that Boeing's…

October 26, 1998 ·Nancy J. Spies
Citations vacated
ALJ

Turnbull Metal Products, Inc.

Press and facility violations produce $9,450 penalty

Turnbull Metal Products manufactured metal furniture and other products at a Mississippi facility using press brakes and mechanical power presses. OSHA cited missing platform and stair midrails, an inadequate lockout program, unguarded machine parts, deficient press inspections, and electrical…

October 26, 1998 ·Ken S. Welsch
Mixed result
ALJ

National Envelope Corporation d/b/a New York Envelope Co.

All remaining machine-safety citations vacated

OSHA issued National Envelope Corporation citations after two inspections of its envelope manufacturing plant. One case alleged inadequate training after a machine operator injured a finger while attempting to address a chip-collector problem. Judge Richard DeBenedetto found that the operator had…

October 26, 1998 ·Richard DeBenedetto
Citations vacated
ALJ

Peach Auto Painting and Collision of Montgomery, Inc.

Repeated eye-protection violation affirmed

Peach Auto's painter regularly spray painted vehicles without eye protection despite chemical-vapor hazards identified in product safety data sheets and the company's job-hazard assessment. The company had bought welding-style goggles after an earlier OSHA citation, but the painter found them hot…

October 19, 1998 ·Nancy J. Spies
Mixed result
ALJ

Crown Pacific

Rim-wheel training and trajectory violations affirmed

A Crown Pacific employee was killed when a repaired multi-piece wheel exploded while employees unloaded it from a pickup truck at the company's lumber-processing facility. A mechanic regularly transported, handled, and inflated multi-piece wheels but had not been trained in the required procedures…

October 19, 1998 ·Benjamin R. Loye
Mixed result
ALJ

West Winds Construction, Inc.

Scaffold planking and fall-protection violations affirmed

West Winds Construction employees repaired plaster from partially dismantled scaffold platforms that were not fully planked and had no guardrails. The workers faced falls of about 18 to 20 feet, and the site foreman directed and observed the work. Chief Judge Irving Sommer imputed the foreman's…

October 13, 1998 ·Irving Sommer
Citations affirmed
ALJ

High End Systems, Inc.

Consultant's missed deadline did not excuse late contest

High End Systems hired a safety consultant to represent it during an OSHA inspection. The consultant received the citation, advised High End to contest it, knew the June 3 deadline, and prepared a notice of contest, but neither party sent the notice. Judge James H. Barkley found that the consultant…

October 2, 1998 ·James H. Barkley
Procedural
ALJ

Metal Buildings of Wisconsin, Inc.

Willful fall-protection citation reduced to serious

Metal Buildings of Wisconsin employees installed steel decking about 37 feet above the ground without nets, safety lines, belts, or other fall protection, and one worker died after falling through a gap. The company used a safety monitor because it considered nets a fire hazard and other methods…

September 21, 1998 ·Sidney J. Goldstein
Modified
ALJ

Heinz Pet Products a/d/a Star-Kist Foods, Inc.

Union objections did not prevent settlement approval

Heinz Pet Products and the Secretary reached a settlement after Heinz contested citations alleging several violations. The employees' union objected because it had not participated in the negotiations, questioned whether hazards were abated, and disputed the penalty reductions and…

September 18, 1998 ·Irving Sommer
Settled
ALJ

Nelson Tree Service, Inc.

Aerial-lift tie-off citation vacated for lack of knowledge

A Nelson Tree Service apprentice briefly operated an aerial lift without wearing the required safety belt after returning from a break. His crew leader had watched him tie off earlier, was completing paperwork in the truck when the lift rose, and could not see from the ground whether the belt was…

September 14, 1998 ·Nancy J. Spies
Citations vacated
ALJ

Foss Maritime

Eyewash and walkway citations vacated

At Foss Maritime's repair facility, OSHA found a clogged eyewash near a caustic-soda parts tank and a yacht-access walkway without midrails. A working water hose was immediately beside the caustic tank, and Judge Stanley M. Schwartz found that the Secretary did not prove the hose was unsuitable for…

September 14, 1998 ·Stanley M. Schwartz
Citations vacated
ALJ

Bovis Construction Corporation

Excavation citations vacated for lack of knowledge

A Bovis Construction subcontractor allowed employees into a deep excavation without a nearby safe exit, adequate water precautions, or cave-in protection. As general contractor, Bovis had enough supervisory authority to require subcontractor compliance, but its liability still depended on actual or…

September 11, 1998 ·Stephen J. Simko, Jr.
Citations vacated
ALJ

Scafar Contracting, Inc.

Two trench violations affirmed and three vacated

Scafar Contracting replaced an underground sewer line through a series of excavations in Newark, New Jersey. Judge Michael H. Schoenfeld found that employees building a manhole worked beside an inadequately protected excavation wall and that another trench used timber shoring that did not meet the…

September 4, 1998 ·Michael H. Schoenfeld
Mixed result
ALJ

Bilran Excavating Company

Inadequately sloped trench violation affirmed

Bilran Excavating installed a water line in a trench about 8.5 feet deep with no shoring and walls sloped at 58 degrees. Its competent persons had not performed the required visual and manual soil analysis before the foreman entered the trench. Judge Covette Rooney held that without a valid soil…

August 31, 1998 ·Covette Rooney
Citations affirmed
ALJ

The Fishel Company

Willful trench citations vacated for employee misconduct

A Fishel Company crew leader entered an unshored Type C trench more than five feet deep while a spoil pile and backhoe were close to the edge. As crew leader and competent person, his knowledge of the conditions was imputable to Fishel. Judge Ken S. Welsch nevertheless found unpreventable employee…

August 28, 1998 ·Ken S. Welsch
Citations vacated
ALJ

Richards Roofing, Inc., and Construction

Inexperience did not excuse late contest

Richards Roofing received an OSHA citation on October 6, 1997, making October 28 the deadline for a notice of contest. It filed on October 31 and explained that it was unfamiliar with OSHA procedures. Chief Judge Irving Sommer found that the citation cover letter and accompanying OSHA booklet…

August 26, 1998 ·Irving Sommer
Procedural
ALJ

Megan Construction Company

Subcontractor scaffold violation affirmed

A masonry subcontractor employee worked on a third-level scaffold without guardrails at a project controlled by Megan Construction. Judge Covette Rooney vacated an allegation that Megan lacked a program of frequent and regular inspections because its daily and weekly inspection evidence showed…

August 21, 1998 ·Covette Rooney
Mixed result
ALJ

Scarff's Nursery, Inc.

Trench cave-in violation affirmed under general duty clause

Scarff's Nursery employees installed irrigation pipe in a narrow trench about 6.5 feet deep when a cave-in injured two workers. The agriculture standards contained no trench-safety provision, so OSHA proceeded under the general duty clause. Judge Ken S. Welsch found no proof that the nursery…

August 19, 1998 ·Ken S. Welsch
Mixed result
ALJ

Evergreen Technologies, Inc.

Machine-guarding citation vacated for unforeseeable access

An Evergreen Technologies lab technician sustained severe injuries when her hair became entangled in an exposed drive screw on a material-testing machine. An accordion guard had been detached for at least three weeks, and Judge Nancy J. Spies found that reasonable diligence would have revealed the…

August 17, 1998 ·Nancy J. Spies
Citations vacated
ALJ

O'Connor & Taylor, Inc.

Clerical date error did not excuse late contest

O'Connor & Taylor received an OSHA citation on April 20, 1998, making May 11 the deadline for a notice of contest. A clerical error caused the company to record April 22 as the receipt date and file after the 15-working-day period. Chief Judge Irving Sommer found no improper conduct by the…

August 14, 1998 ·Irving Sommer
Procedural
ALJ

Korte & Luitjohan, Inc.

Leading-edge fall citation vacated under steel-erection exception

Korte & Luitjohan was installing metal roof decking on a commercial building with steel framing and wood trusses. Ten employees worked 16 to 22 feet above a concrete floor without guardrails, safety nets, or personal fall arrest systems. OSHA cited the company under the general construction…

August 10, 1998 ·Stephen J. Simko, Jr.
Citations vacated
ALJ

Cumbie Concrete Company, Inc.

Carbon-monoxide and respirator violations yield $7,800

Cumbie Concrete employees cut holes in a library floor with a propane-powered saw inside a room sealed with plastic sheeting. Three employees developed carbon-monoxide poisoning and received hospital treatment. Judge Ken S. Welsch affirmed violations for lacking a propane safety data sheet and…

August 10, 1998 ·Ken S. Welsch
Mixed result
ALJ

CMH Material Handling, LLC

Elevated-platform fall violations affirmed

A CMH Material Handling employee died after falling from a 40-foot platform while replacing bolts on an overhead crane system at an aircraft manufacturing facility. The platform lacked standard guardrails in work areas, and employees did not consistently use the body harnesses CMH supplied. Judge…

August 10, 1998 ·Nancy J. Spies
Citations affirmed
ALJ

Island Lathing & Plastering, Inc.

Scaffold and ladder violations affirmed with $55,000 in penalties

Island Lathing & Plastering was performing interior plastering work at a multistory theater project. OSHA found an employee working from an unlocked mobile scaffold beside a balcony edge without fall protection, then descending a ladder while facing away from it. The judge found that the foreman…

July 31, 1998 ·Irving Sommer
Citations affirmed
ALJ

Equity Residential Development Corporation

Roofing safety citations affirmed by default

OSHA cited Equity Residential Development Corporation after workers were observed performing roofing work without fall protection at a height of 10.3 feet. The citation alleged that the company failed to have a competent person conduct adequate jobsite inspections and failed to retrain employees on…

July 30, 1998 ·Stephen J. Simko, Jr.
Citations affirmed
ALJ

King Concrete Construction Company, Inc.

Willful fall violations and settlement yield $18,200

King Concrete performed concrete work on a barracks project at Fort Jackson, South Carolina. The company admitted that employees working on and near leading edges lacked required fall protection, but disputed OSHA's willful classification and proposed $49,000 penalty. The judge found the violations…

July 30, 1998 ·Stephen J. Simko, Jr.
Mixed result
ALJ

Kenko, Inc.

Two trench hazards affirmed and egress item vacated

Kenko employees were laying and connecting pipe in a trench more than 11 feet deep. OSHA cited the company for inadequate egress, loose rock or soil on the excavation face, and insufficient cave-in protection. The judge vacated the egress item because the backfill provided a safe way out and the…

July 30, 1998 ·Sidney J. Goldstein
Mixed result
COMM

East Texas Coatings, Inc.

Commission approves $4,170 confined-space settlement

East Texas Coatings removed and replaced linings inside railroad tank and hopper cars. After review was directed, the parties settled citations involving respiratory protection and permit-required confined spaces. The Secretary withdrew many items, reduced penalties on several others, and…

July 30, 1998
Settled
ALJ

Harpis Exteriors

Late notice of contest dismissed

OSHA issued Harpis Exteriors a citation and proposed penalties in October 1997. The company received the citation on October 8 but did not send a notice of contest before the October 30 deadline. Its owner said he misread the citation, promptly corrected the cited conditions, and contacted OSHA and…

July 27, 1998 ·Irving Sommer
Procedural
ALJ

J & B Masonry and Construction, Inc.

Oral discussion did not preserve late contest

OSHA issued J & B Masonry and Construction a citation and proposed penalty in September 1997. The company's president said he spoke with the compliance officer after receiving the citation and believed that conversation was enough to make an appeal. He also said he did not carefully read the…

July 27, 1998 ·Irving Sommer
Procedural
ALJ

Reliance Environmental Management, Inc.

Asbestos violations affirmed but willful classification rejected

Reliance Environmental Management removed asbestos during renovation of an abandoned department store in Toledo, Ohio. OSHA cited monitoring, training, wet-method, work-practice, decontamination, and shower violations. The judge rejected the company's challenges to the inspection and its…

July 27, 1998 ·Ken S. Welsch
Mixed result
ALJ

CH2M Hill, Inc., f/k/a CH2M Hill Central, Inc.

Forty willful tunnel electrical violations yield $200,000

CH2M Hill provided engineering and program-management services for a Milwaukee wastewater tunnel project. After methane ignited in a tunnel explosion that killed three employees of the tunneling contractor, OSHA cited CH2M for unapproved electrical equipment and nonreversible ventilation. The…

July 22, 1998 ·Nancy J. Spies
Mixed result
ALJ

Southwest Marine, Inc.

General-duty citation dismissed because a shore-based crane fell under California's state plan

Southwest Marine repairs and refurbishes ships at a San Diego facility. In October 1996, the boom of a shore-based portal crane collapsed onto the USS Benfold moored at the pier. California's state OSHA program (CalOSHA) cited the company over crane operation and maintenance, and federal OSHA…

July 16, 1998 ·Benjamin R. Loye
Procedural
ALJ

Black Construction Corp.

Eye-protection citation vacated, scaffold citation downgraded to de minimis

Black Construction Corporation was a contractor working on a Naval Hospital renovation project in Agana Heights, Guam. After a November 1996 inspection, OSHA cited the company for two serious violations: an employee drilling metal frames without eye protection, and a wood pole scaffold about 18…

July 16, 1998 ·Benjamin R. Loye
Mixed result
ALJ

Dawson Production Services

Rig-guying citation affirmed, anchor-capacity citation vacated after a fatal rig collapse

Dawson Production Services operated a well-servicing rig at a site in Chambers County, Texas. OSHA inspected after a fatality caused by a drill rig collapse and issued two general duty clause citations tied to how the rig was guyed and anchored. On the first item, the evidence showed the company…

July 13, 1998 ·James H. Barkley
Mixed result
ALJ

Rausch Construction Company

Both excavation citations affirmed for a $5,100 penalty

Rausch Construction Company was doing sewer line connection work at an excavation site in Chicago. An OSHA compliance officer driving by in May 1997 stopped and measured the trench, finding it about 6.5 feet deep in Type C soil with vertical walls that should have been sloped to 34 degrees, and a…

July 10, 1998 ·Irving Sommer
Citations affirmed
ALJ

R.K. Construction & Development Co.

All five demolition-site citations affirmed with penalties reduced to $4,250

R.K. Construction & Development Co. is a small family-owned demolition and building restoration contractor in Savannah, Georgia. While the company was tearing down a three-story building, an OSHA compliance officer driving by saw employees on a scaffold about 25 feet up and stopped to inspect. OSHA…

July 6, 1998 ·Ken S. Welsch
Citations affirmed
ALJ

Exterior Erecting Systems, Inc.

Secretary's illness did not excuse late contest

Exterior Erecting Systems received an OSHA citation on September 2, 1997, but did not contest it before the September 23 deadline. The company explained that its secretary signed for the citation and then left work for two months because of a serious illness. Other office staff handled her duties…

June 29, 1998 ·Irving Sommer
Procedural
ALJ

Auto Shred Recycling, L.L.C.

Conveyor machine-guarding citation vacated

Auto Shred Recycling operated a metal-scrap shredding facility in Pensacola, Florida. After an employee was caught in a conveyor tail pulley and later died from his injuries, OSHA cited the company for inadequate machine guarding. The judge found that a guardrail protected employees during normal…

June 29, 1998 ·Stephen J. Simko, Jr.
Citations vacated
ALJ

M & M Road Recycle, Inc.

$5,000 in attorney fees awarded for one duplicative citation under the EAJA

After largely defeating OSHA's citations in an earlier case, M & M Road Recycle, Inc. asked for its attorney fees under the Equal Access to Justice Act, which lets small employers recover costs when the government's position was not substantially justified. In the underlying case, the judge had…

June 25, 1998 ·Stanley M. Schwartz
Procedural
ALJ

S. E. Johnson Companies

Bridge-demolition protective-equipment and monitoring citations vacated

S. E. Johnson Companies cut painted steel beams during an Ohio Turnpike bridge-demolition project. OSHA alleged that disposable suits were unsafe for torch cutting, that helpers had not received representative lead monitoring, and that the company had not made the required cadmium determination…

June 22, 1998 ·Covette Rooney
Citations vacated
ALJ

New England Masonry Co.

Most roofing-site citations affirmed, safety-monitor and ladder-inspection items vacated

New England Masonry Co. was replacing the flat roof on a convalescent home in Glastonbury, Connecticut, when OSHA inspected and issued a five-item serious citation. The judge affirmed most of it: a ground worker in the hoist area without a hard hat, a discharged and an overcharged fire extinguisher…

June 17, 1998 ·John H. Frye, III
Mixed result
COMM

Wayne J. Griffin Electric, Inc.

Commission approves no-penalty electrical settlement

Wayne J. Griffin Electric and the Secretary settled two electrical citation items after Commission review was directed. The Secretary amended the first item, under the wiring-methods standard, from serious to other-than-serious with no penalty, consistent with the administrative law judge's earlier…

June 15, 1998
Settled
ALJ

Yates Grading & Heavy Equipment, Inc.

Trench safety violations yield $4,050

Yates Grading & Heavy Equipment installed sewer pipe in an excavation at a Georgia subdivision. OSHA cited the company for an inadequate safety program, insufficient excavation training, lack of cave-in protection, and a spoil pile placed at the trench edge. The judge found that general reminders…

June 15, 1998 ·Nancy J. Spies
Citations affirmed
ALJ

Condor Construction Company

Willful/repeat trenching citation and hard-hat citation affirmed for $23,000

Condor Construction was building a church and day-care facility in New Rochelle, New York. OSHA had already cited and settled with the company twice at the same site for leaving employees in an unprotected excavation. On a third inspection in June 1996, the compliance officer found employees again…

June 5, 1998 ·Irving Sommer
Citations affirmed
ALJ

Wye Electric, Inc.

Four excavation citations affirmed after employee-misconduct defense fails, $4,350

Wye Electric installs underground power and communication systems. On a construction project in Jackson, Mississippi, its crew dug a roughly 7-foot pit in unstable Type C soil at a former gas station site to set a precast manhole. OSHA cited four excavation violations: no fall barriers at the pit…

May 26, 1998 ·Nancy J. Spies
Citations affirmed
ALJ

Royal Gorge Publishing d/b/a Daily Record

Forklift citation vacated where a maintenance expert outweighed the inspector

Royal Gorge Publishing, which runs the Daily Record newspaper in Canon City, Colorado, was cited after an OSHA compliance officer inspected a forklift used to move pallets of newspaper inserts. The officer found damaged insulation on electrical and hydraulic cables, exposed copper wire, cuts…

May 26, 1998 ·Sidney J. Goldstein
Citations vacated
ALJ

Victory Memorial Hospital & Skilled Nursing Center

Ethylene-oxide safety violations yield $12,150

Victory Memorial Hospital used ethylene oxide to sterilize instruments in its central sterile supply area. OSHA cited the hospital after finding that the area monitor was not operating, the written emergency plan was incomplete, and several recordkeeping and employee-notification duties were not…

May 22, 1998 ·Irving Sommer
Mixed result

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.
  • Where they come from: Every page links the official OSHRC public release, and the full text on the page is that release. The plain-English summaries are written by Ezel.