FMSHRC Commission decision Docket SE 2024-0109 Decided December 13, 2024 Procedural

Secretary of Labor v. JDI Industrial

Secretary of Labor v. JDI Industrial (FMSHRC SE 2024-0109): Refused assessment and legal mistake defeated reopening

Apply this precedent to your situation

This is citable Commission precedent from 2024, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the Commission's own document.
Read the official release (fmshrc.gov)

Plain-English summary

JDI Industrial sought to reopen five recordkeeping penalties after delivery of the proposed assessment was refused and the contest deadline passed. Its safety director had worked with MSHA to correct the violations and mistakenly believed that abatement meant no penalties would be issued. The Secretary did not oppose reopening and noted JDI's clean history, but JDI could not explain why its employees refused the assessment. The Commission held that an unexplained refusal of service and an intentional choice not to contest based on a legal misunderstanding did not establish good cause, so it denied reopening. Commissioner Marvit concurred in the denial while maintaining that the Commission lacks statutory authority to reopen final orders.

Decision snapshot

  • Cited authority: 30 U.S.C. § 815(a)
  • Outcome: The motion to reopen the final penalty assessment was denied.
  • Key point: Refusing delivery without explanation and misunderstanding the legal effect of abatement did not establish good cause to reopen.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVE., N.W., SUITE 520N

WASHINGTON, DC 20004-1710

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

JDI INDUSTRIAL[1]

:

:

:

:

:

:

:

Docket No. SE 2024-0109

A.C. No. 09-00241-588160

BEFORE: Jordan, Chair; Baker and Marvit, Commissioners

ORDER

BY: Chair Jordan and Commissioner Baker

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2018) (“Mine Act”). On February 21, 2024, the Commission received from JDI Industrial (“JDI”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure, under which the Commission may relieve a party from a final order of the Commission on the basis of mistake, inadvertence, excusable neglect, or other reason justifying relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) and the U.S. Postal Service indicate that delivery of the proposed assessment was attempted and rescheduled on November 3, 2023, then reattempted and refused on November 6. The assessment became a final order of the Commission on December 6, 2023.[2] A delinquency was mailed to the contractor on January 22, 2024.

JDI asserts that, prior to receipt of the delinquency notice, it mistakenly believed no assessment would be issued. The Safety Director explains that he had cooperated with MSHA to remedy the underlying recordkeeping citations and implement procedures to ensure future reports were timely filed, and therefore believed the citations had been “closed.” He concedes that he was still learning about the mine’s operations at the time, and did not ask whether the penalties associated with the citations had been dropped. After receiving the delinquency notice, the Director of Safety contacted MSHA and learned that delivery of the assessment package had been refused. JDI is unable to explain why any if its employees would refuse to sign for mail coming from MSHA.

The Secretary does not oppose the motion to reopen. The Secretary notes the Safety Director’s diligent efforts in working with MSHA to correct the recordkeeping errors and to implement procedures to prevent future errors. The Secretary further notes that JDI has no history of untimely contests or delinquent penalties, as the five recordkeeping citations at issue are the only citations the contractor has ever received.

According to the parties’ representations, the assessment was not timely contested for two reasons: delivery of the assessment was refused, and the Safety Director did not believe an assessment would be issued because he misunderstood the legal ramifications of abatement.

Neither of these justifications establish good cause to reopen the final assessment.

We have looked disfavorably on motions to reopen where the operator has actively refused service of the proposed assessment, finding that a “party which refuses to accept certified mail from MSHA will most likely be unable to establish good cause [to reopen].” Munn Road Sand & Gravel, 26 FMSHRC 383, 384 (May 2004). Moreover, a party seeking to reopen a final penalty must provide a detailed explanation that accounts, to the best of the party’s knowledge, for the failure to submit a timely contest. Higgins Stone Co., 32 FMSHRC 33, 34 (Jan. 2010). General assertions or conclusory statements are insufficient. Southwest Rock Prod., Inc., 45 FMSHRC 747, 748 (Aug. 30, 2023). Here, JDI refused delivery of the assessment, and is unable to offer any explanation beyond a general assertion that it “does not know why anyone from [JDI] would refuse to sign for the mail coming from MSHA.” This statement is not sufficient to establish good cause to reopen this case.

Furthermore, we have held that an operator’s intentional failure to contest based on ignorance of the law does not provide grounds for relief under Rule 60(b)(1). Active Res., Inc., 47 FMSHRC 848, 850 (Oct. 2024) (denying operator’s motion to reopen where the operator elected not to contest an assessment because it mistakenly believed that the citation was considered abated with the assessment of the penalty). Here, JDI made no effort to contest the assessment because it mistakenly believed no assessment would be issued for an abated citation.[3] In other words, JDI intentionally did not file a contest based on an erroneous understanding of the law.

Having reviewed JDI’s request and the Secretary’s response, we find that the provided justifications do not establish good cause for reopening the captioned proceeding. Accordingly, we deny JDI’s motion.

/s/ Mary Lu Jordan

Mary Lu Jordan, Chair

/s/ Timothy J. Baker

Timothy J. Baker, Commissioner

Commissioner Marvit, concurring:

I write to agree with the Majority in this case for the reasons set forth below.

In Explosive Contractors, 46 FMSHRC , No. CENT 2024-0122 (Dec. 4, 2024), I dissented and explained that Congress did not grant the Commission the authority to reopen final orders under section 105(a) of the Mine Act. The Commission’s repeated invocation of Federal Rule of Civil Procedure 60(b) cannot overcome the statutory language. However, in Belt Tech, I explained in my concurrence that “the Act clearly states that to become a final order of the Commission, the operator must have received the notification from the Secretary.” 46 FMSHRC , slip op. at 3, No. WEVA 2024-0036 (Dec. 5, 2024) (citing Hancock Materials, Inc., 31 FMSHRC 537 (May 2009)). Taken together, these opinions stand for the proposition that the Commission may not reopen final orders under its statutory grant, but an operator may proceed if it has not properly received a proposed order.

In the instant case, as the Majority recounts, the operator received the final order. The Majority denies reopening in its opinion because the operator has not alleged good cause or provided a factual accounting for its failure to timely contest the penalties. Though I believe the Commission lacks the authority to consider motions to reopen, I concur with the Majority in denying reopening in this matter.

/s/ Moshe Z. Marvit

Moshe Z. Marvit, Commissioner

Distribution:

David J. De Vita

Director of Safety

J. Davis Inc.

12245 South Hwy 11

Westminster, SC 29693

[email protected]

April Nelson, Esq.

Associate Solicitor

Office of the Solicitor

U.S. Department of Labor

Division of Mine Safety and Health

201 12th Street South, Suite 401

Arlington, VA 22202

[email protected]

Emily Toler Scott, Esq.

Counsel for Appellate Litigation

Office of the Solicitor

U.S. Department of Labor

Division of Mine Safety and Health

201 12th Street South, Suite 401

Arlington, VA 22202

[email protected]

Melanie Garris USDOL/MSHA, OAASEI/CPCO 201 12th Street South, Suite 401 Arlington, VA 22202 [email protected]

Chief Administrative Law Judge Glynn F. Voisin Federal Mine Safety Health Review Commission

Office of the Chief Administrative Law Judge 1331 Pennsylvania Avenue, NW Suite 520N Washington, DC 20004-1710 [email protected]

[1] The caption in this matter previously identified the contractor to whom the relevant assessment was issued as J. Davis, Inc. The caption has been amended to reflect that the contractor’s identification on record with the Department of Labor’s Mine Safety and Health Administration is JDI Industrial.

[2] Service has occurred where delivery to the correct address was attempted but refused. See, e.g., Dyno Nobel, 46 FMSHRC 397 (June 2024) (assessment became final 30 days after attempted delivery to operator’s address of record); cf. Beelman Truck Co., 40 FMSHRC 1104 (Aug. 2018) (finding the motion to reopen moot where attempted delivery was unclaimed, the operator asserted it never received the assessment, and the Secretary did not argue that the operator refused to accept delivery).

[3] The Commission may reopen a final order where an operator intended to contest the assessment, but failed to timely do so because it was unfamiliar with some aspect of the contest process. E.g., Highway Materials, Inc., 45 FMSHRC 593 (July 2023) (reopening where the operator intended to contest citations but failed to timely file because it mistakenly believed that the conference with MSHA tolled the filing deadline). That is distinguishable from the situation here, in which the operator made no attempt to contest the assessment due to ignorance of the legal ramifications of abatement.

Get today's answer for your situation

You just read Commission precedent from 2024. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.