FMSHRC ALJ decision Docket PENN 2022-0129 Decided April 25, 2023 Settled Judge William B. Moran

Secretary of Labor v. Consol Pennsylvania Coal Company, LLC

Secretary of Labor v. Consol Pennsylvania Coal Company, LLC (FMSHRC PENN 2022-0129): Communications and track settlement approved

Apply this to your situation

This order from 2023 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current MSHA standards and Commission precedent, with citations.

Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the Commission's own document.
Read the official release (fmshrc.gov)

Plain-English summary

The settlement covered an emergency-communications citation and two track or travelway safeguard citations at Consol Pennsylvania Coal's Bailey Mine. The communications system lacked redundant tracking and communication along a 2,420-foot alternate escapeway and at a refuge location; its high-negligence finding was reduced to moderate and the $6,898 penalty to $1,393. Two safeguard citations involving 39 loose track bolts, a misaligned rail, and a wet, obstructed belt walkway were changed to unlikely and non-S&S, reducing each $1,069 penalty to $252. Judge Moran concluded that the safeguard reductions lacked supporting facts, criticized repeated reliance on Mechanicsville Concrete as authority for unreviewable S&S withdrawal, and explained the factual-support requirements of the Commission's American Coal decisions. He nevertheless approved the $1,897 settlement, a 79% reduction.

Decision snapshot

  • Cited authorities: 30 U.S.C. § 876(b) and 30 C.F.R. § 75.1403
  • Outcome: All three citations were modified and settled for $1,897 instead of $9,036.
  • Key point: The Judge found the two safeguard reductions factually unsupported but approved them under the Commission's restricted settlement-review framework.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND
HEALTH REVIEW COMMISSION

Office of Administrative Law Judges

1331 Pennsylvania Avenue, N.W., Suite 520N

Washington, DC 20004

Office: (202) 434-9933 / Fax: (202) 434-9949

|
SECRETARY OF LABOR MINE SAFETY AND HEALTH ADMINISTRATION (MSHA), Petitioner
v.
CONSOL PENNSYLVANIA COAL COMPANY, LLC, Respondent |
|
|
CIVIL PENALTY PROCEEDING
Docket No. PENN 2022-0129 A.C. No. 36-07230-561904
Mine: Bailey Mine |

DECISION APPROVING SETTLEMENT WITH
SIGNIFICANT RESERVATIONS

Before: Judge William Moran

This case is before the
Court upon a petition for assessment of a civil penalty under Section 104(d) of
the Federal Mine Safety and Health Act of 1977. The Secretary has filed a
Motion to Approve Settlement. The Respondent has agreed to the proposed
settlement. The originally assessed total amount for the citations at issue was
$9,036.00 and the proposed total settlement amount is $1,897.00,
reflecting a 79% (seventy-nine percent)
overall reduction, as reflected in
the following table:

|
|
|
|
|
|
9205312 |
$6,898 |
$1,393 |
Citation
modified to moderate negligence; |
|
9204928 |
$1,069 |
$252 |
Citation modified to unlikely and
non-S&S; |
|
9205356 |
$1,069 |
$252 |
Citation modified to unlikely and
non-S&S; |
|
|
|
|
|


The
Citations in issue


**Citation
No. 9205312 **


This
citation invoked 30 U.S.C. §876(b), pertaining to “Communication facilities;
locations and emergency response plans
.” The section addresses telephone
service or equivalent two-way communication facilities, which are to be approved
by the Secretary or his authorized representative. Such communication
facilities shall be provided between the surface and each landing of main
shafts and slopes and between the surface and each working section of any coal
mine that is more than one hundred feet from a portal. The cited subsection
addresses the plan requirements.

The section 104(a) citation for this now-admitted violation stated:


The Mine Operator failed to comply
with their Approved Emergency Response Plan (Approved 9-11-2020), in that,
there were no leaky feeder line (communication) or tracking tags installed in
the 2-K Working Section (009-0 MMU) Alternate Escapeway (number 3 entry of 2-K)
from the loading point inby 8 crosscut outby to the 5 South Mains Right (K)
Track at the number 80 crosscut (2420 feet in length). Therefore there was no
redundant communication between the Primary or Alternate Escapeways
and no
communication or tracking at all in the alternate escapeway
or at the
Working Section refuge alternative/SCSR cache from the alternate escapeway
.
After issuance of this citation, the Operator removed the persons from the
working faces to outby the loading point until the condition can be corrected.

The Following statements are from the Approved Mine Emergency Response Plan and have not been complied with:

  1. Page 1, Communication, 2. Coverage Area, line b.,- The system will also generally provide continuous coverage along escapeways and a coverage zone approximately 200' feet inby and outby strategic areas of the mine. Strategic Areas are fixed work locations where miners are normally required to work, section SCSR caches, working section power centers and manned belt transfers.

  2. Page 2., 6.,- Survivability, a. The post accident communication system will generally provide redundant signal pathways to the surface component. b.- Redundancy will be achieved by two or more systems installed in two or more entries, or one system with two or more pathways to the surface; provided that a failure in one system or pathway does not affect the other system or pathway. c.,- Redundancy means that the system can maintain communication with the surface when a single pathway is disrupted. Disruptions can include major events in an entry or component failure.

  3. Page 3, Tracking System, 1. Performance, aiii.,- Locate Miners in escape-way at intervals not to exceed 2000 feet. iv.,- Locate miners within 200 feet of strategic areas. Strategic Areas are fixed work locations where miners are normally required to work, section mass SCSR caches, working section power centers and manned belt transfers. vii.,- Locate miners at the key junction in the escape-ways. viii.,- Locate miners within 200 feet of refuge alternatives. d.- The electronic tracking system will be installed in active daily traveled areas of the mine Primary and Secondary escapeways.

  4. Page 5, 8. Maintenance, d. In the event of system or component failures, the miners will be notified of the problem. The affected miners will begin manual zone tracking and continue to advise the surface communication facility of their travel until the system is repaired. Repairs will start immediately if there is a loss in tracking capabilities. e.- The system will be examined weekly to verify that it is maintained in proper operating condition and the results of the examination will be entered in a record book.

  5. Page 5, 9. Purchase and Installation,- b. If there is system failure the mine will revert to manual tracking system that was previously used.

Petition for Civil Penalty at 11-13.

The citation was terminated the following day, with the inspector noting:

Through a visual observation after traveling the 2K MMU 009-0 #3 entry (return) (Alternate Escapeway) in its entirety and having communication throughout and verifying through the tracking software on the Mine's surface of this inspectors locations, this citation is hereby terminated. The system is working in the previously mentioned entry/area. Secondly, the Mine Operator is carrying a record/ledger (weekly exam) to show the systems functioning properly.

Id. at 13.

The
issuing inspector, who diligently recorded the aspects of the Approved Mine
Emergency Response Plan provisions which were not complied with, listed the
“Gravity” of the injury or illness as ‘Unlikely,’ but listed such injury or
illness as “Fatal” if it were to occur. Marked as non-significant and
substantial, nine miners would be affected. Given the multiple subjects of
non-compliance, the inspector listed the negligence as “High.” Id.

Analysis
for Citation No. 9205312
** **

The penalty, which
was regularly assessed at $6,898.00, is now proposed to be settled at $1,393.00, representing an 80% reduction. This
figure is apparently derived by designating the negligence from ‘High’ to
“Moderate.’ Motion at 3. The justification for this is short, the Motion
relating that the “Respondent has represented to the Secretary that it had
assigned miners to install the missing equipment that is the subject of the
citation, but that the work was not timely completed because of supply problems.”
Undercutting this claim is that the inspector found five instances of
non-compliance, yet all five violative conditions were somehow corrected the
next day, the supply problems apparently having vanished rapidly. This is the
sole basis presented in the motion for listing the negligence as moderate.

In support of the Secretary’s contention, the Solicitor’s attorney
looks to Vindex Energy Corporation, 34 FMSHRC 223, 224 (Jan. 2012) (ALJ)
(“Vindex”), asserting that “[i]t is ‘appropriate to defer to the
judgment of the parties’ in arriving at a modified penalty based on the §100.3
tables.” Motion at 3. The Solicitor’s attorney is apparently unaware that an
administrative law judge’s decision is not precedential. Commission Procedural
Rule 69(d) provides that a Judge's decision does not constitute binding
precedent. 29 C.F.R. § 2700.69(d). Rain for Rent, 40 FMSHRC 976, 980
(July 2018), Tilden Mining, 36 FMSHRC 1965 (Aug. 2014). The Secretary
also errs in asserting that there is an evidentiary dispute regarding the
appropriate level of negligence but offers nothing to support the notion that
the negligence should be deemed “Moderate,” other than the vague remark about
the short-lived claim of ‘supply problems.’ Merely asserting ‘supply problems’
is apparently sufficient to carry the day.

Citation
No. 9204928

This section 104(a) citation, invokes 30 C.F.R. § 75.1403, well known as the ‘safeguard standard.’ It is also a statutory provision which requires that “[o]ther safeguards adequate, in the judgment of an authorized representative of the Secretary, to minimize hazards with respect to transportation of men and materials shall be provided.”

For
this now-admitted violation, on July 8, 2022 the inspector identified multiple
violations of the provision, noting that “[t]he 2K section (MMU 009-0) #2 entry
track from 0xc - 9.5xc has failed to be properly maintained as identified by
the safeguards for the Bailey Mine in the aspect: 39 loose track bolts,
a loose fish plate and a missing bolt are allowed to exist on this
track. Also, at the #8 crosscut the rail is out of alignment by 1/4 inch
at the time of the exam.

Petition for Civil Penalty at 15 (emphasis added).

The
citation noted that the safeguard standard had been cited 59 times in two
years
at the mine. Id.

The
citation was terminated four days later, on July 12, 2022, after the identified
violations were corrected with the inspector stating that the “operator was
able to tighten the loose bolts with approved means, and properly adjust the
rail at #8 crosscut, however will need to burn a hole in the rail to install
the missing bolt on the right side of the track at #8 crosscut. Because the
mine is currently operating on shutdown and minimal people are working,
additional time is granted to get specialized manpower to this location to cut
the rail to install the bolt. Id. at 16.

Analysis
for Citation No. 9204928


The
Secretary’s attorney cites an administrative law judge decision as precedent,
misconstrues the Commission’s decision in
Mechanicsville Concrete, Inc., 18 FMSHRC 877, (June 1996), and
does not provide ‘facts’ to support the requirements for settlement, per the
Commission’s AmCoal decisions: 38 FMSHRC 1972, (Aug. 2016) (“
AmCoal I
”),
American Coal Co., 40 FMSHRC 983 (Aug. 2018) (“AmCoal II”) **


** If the basis for the 80% penalty
reduction regarding the previously discussed Citation, No. 9205312, is arguably
justified, the same cannot be said for Citation No. 9204928.
This is so because
the offering by the Secretary does not even meet the Commission’s requirements
for settlement motions. The justification,
in its entirety
, provides
only that:

[t]he
Secretary has elected to withdraw the S&S designation for this violation
and resolve it as “unlikely.” The proposed penalty reduction in this settlement
is based on the point values in 30 C.F.R. §100.3 based on the Secretary’s
modification to the citation. The Secretary’s use of the Part 100 regular
assessment tables in settlement is a prima facie indication that the penalty
reduction is fair, reasonable, and adequate under the facts, and protects the
public interest.

Motion at 3-4.

The
Secretary’s attorney cites once again to the ALJ decision in Vindex,
asserting that “[i]t is ‘appropriate to defer to the judgment of the parties’
in arriving at a modified penalty based on the §100.3 tables.” Id. The
inapplicability of ALJ decisions as precedent has been discussed above.

The
Secretary then adds that she “possesses unreviewable discretion to withdraw an
S&S designation,” citing Mechanicsville
Concrete, Inc
., 18 FMSHRC 877, 879 (June 1996) (“Mechanicsville”)
(finding “no material difference between the Secretary’s discretion on the one
hand to vacate a citation [pursuant to RBK Construction, Inc., 15 FMSHRC
2099, 2101 (Oct. 1993)] and his discretion on the other hand not to issue a
citation in the first instance or not to designate a citation as S&S.”[1]
Motion at 4 (“RBK”).

The
Secretary continues to inappropriately cite Mechanicsville as authority.
This Court and other judges have noted that Mechanicsville does not
support the Secretary’s claim that she possesses unreviewable discretion to
withdraw an S&S designation. Yet, the Secretary continues to assert
otherwise. It’s time to be clear about the Commission’s holding in Mechanicsville.

  • *

At
the outset of its decision in Mechanicsville, the Commission very
plainly set forth the issue before it, stating that it “raises the issues of whether
a judge on his own initiative
can designate a violation of a mandatory
safety standard to be significant and substantial.” 18 FMSHRC 877. The
Commission’s answer to the issue was equally plain, stating that it “agree[d]
with the Secretary that the judge erred in determining on his own initiative
that the violation was S&S.” Id. at 879 (emphasis added). Thus, the
decision was expressly limited to the Commission’s holding that the judge
erred
by adding a new finding and conclusion, i.e., that the
violation posed a hazard to employees that was reasonably likely to result in a
reasonably serious injury and was therefore S&S.” Id. at 880
(emphasis added). The Commission’s decision added nothing more to that
holding.

That
the Commission’s decision in Mechanicsville did not go beyond the very
words it employed in that decision was made additionally clear in Spartan
Mining
, 30 FMSHRC 699 (August 2008). There, Spartan tried to expand [Mechanicsville] but
the Commission would have nothing of it, informing that it “reject[ed] Spartan’s
contention that the judge was bound by the Secretary’s assessment of the degree
of negligence of “moderate” contained in the citation. … Spartan unpersuasively
relies on Mechanicsville Concrete, Inc., 18 FMSHRC 877, 879-80 (June
1996) (finding that judge may not designate a violation as S&S on his own
initiative), to assert that the judge’s alteration of the citation was
impermissible. However, Mechanicsville is distinguishable because modifying
a negligence determination, as the judge did here, is authorized by the Mine
Act, whereas inserting an S&S designation is not.
Spartan at
*22 (emphasis added).

Accordingly,
there is no basis for the Secretary’s habitual citation to Mechanicsville as authority for the
claim that she possesses unreviewable discretion to withdraw an S&S
designation. It is one thing for the Secretary to argue that the
Commission’s holding in Mechanicsville should be expanded beyond
that holding, but to assert that the decision affords the Secretary with
unreviewable discretion to withdraw such a finding is beyond the pale. Here,
the Secretary does not present its contention as an argument. Instead, the
Secretary’s attorney presents his position as the state of the law. It is not.

Attorneys
have an obligation not to misstate case law. Teamsters Local No. 579 v. B
& M Transit, Inc.
, 882 F.2d 274, 280 (7th Cir.1989)#co_pp_sp_350_280). Rule 11 of the Federal Rules of
Civil Procedure requires attorneys to inquire about the … law before filing
pleadings. … an attorney who submits a pleading must certify that: ‘to the best
of the [attorney's] knowledge, information, and belief formed after reasonable
inquiry [the pleading] is … warranted by existing law or a good faith argument
for the extension, modification, or reversal of existing law.” Dzwonkoski, 2008
WL 2163916 (May 16, 2008) (S.D. Ala. 2008) citing Howard v. Liberty Memorial
Hosp
., 752 F.Supp. 1074, 1080 (S.D.Ga.1990).

Therefore,
unless and until the Commission revises its holding in Mechanicsville, the Secretary, both her attorneys
and her non-attorney representatives, (Conference and litigation
representative, “CLRs,”) should cease invoking that decision for propositions
not supported by it.


REVISITING
PRESENT COMMISSION LAW FOR SETTLEMENT MOTIONS AS APPLIED TO THIS MATTER.


Fundamentally,
the Secretary’s Motion in this matter does not meet the Commission’s test for
settlement approvals, as set forth in American Coal Co., 38
FMSHRC 1972, (Aug. 2016) (“AmCoal I”), and American Coal Co., 40
FMSHRC 983 (Aug. 2018) (“AmCoal II”)


** Once past the obvious preliminaries
– that a motion for settlement must state the penalty amount originally
proposed by the Secretary and the new amount the parties have agreed to pay, the
Commission’s decision in
AmCoal II
sets forth the present requirements deemed
sufficient for its judges in carrying out their “front line oversight of the
settlement process” in order “to fulfill their duty of determining if a
settlement of a penalty is fair, reasonable, appropriate under the facts, and
protects the public interest.” Id. at 985, 987.

The
Commission repeatedly spoke of the need for ‘factual support’ for penalty
reduction. Id. at 989, 990. Though the Commission advised that such
‘facts’ “are not limited to facts related to the section 110(i) penalty
criteria or to the alleged violations,” the Commission still required that
facts be presented. Id. at 986. Accordingly, it has “required parties to
submit facts
supporting a penalty amount agreed to in settlement.” Id. at

  1. It noted, “[i]n particular, Commission Procedural Rule 31 requires that a motion
    to approve penalty settlement must include for each violation “the penalty
    proposed by the Secretary, the amount of the penalty agreed to in settlement, and
    facts
    in support of the penalty agreed to by the parties.” Id.

The
Commission rejected the need for a respondent to present legitimate questions
of fact which can only be resolved through the hearing process and also
rejected that there is a need to show any legitimate factual
disagreement. Id. at 991. As such, the Commission stated that “[f]acts
alleged in a proposed settlement need not demonstrate a ‘legitimate’
disagreement that can only be resolved by a hearing. The Commission’s
Procedural Rules and standing precedent do not contain such a requirement.
Rather, the Commission has recognized that parties may submit facts that
reflect a mutual position that the parties have agreed is acceptable to them in
lieu of the hearing process.” Id.

Despite
the above, the Commission’s AmCoal II decision still requires the
submission of ‘facts.’ Such facts must be “mutually acceptable facts that
demonstrate the proposed penalty reduction is fair, reasonable, appropriate
under the facts, and protects the public interest.” Id. at 991. Here, no
facts have been presented.

It
is not an exaggeration to describe the basis for the Secretary’s justification
as essentially ‘because we can.’ Though set forth above, it is worth repeating
what the Secretary presented here, to wit:

[t]he
Secretary has elected to withdraw the S&S designation for this violation
and resolve it as “unlikely.” The proposed penalty reduction in this settlement
is based on the point values in 30 C.F.R. §100.3 based on the Secretary’s
modification to the citation. The Secretary’s use of the Part 100 regular
assessment tables in settlement is a prima facie indication that the penalty
reduction is fair, reasonable, and adequate under the facts, and protects the
public interest.

Motion at 3-4.

None
of this amounts to mutually acceptable facts that demonstrate the proposed
penalty reduction is fair, reasonable, appropriate under the facts, and
protects the public interest.

Citation
No. 9205356

This citation also invokes 30 C.F.R. § 75.1403. Issued on July 20, 2022, the inspector’s Condition or Practice section of the citation states:

The Mine Operator failed to
maintain an unobstructed travelway of at least 24 inches in width on walk side
of the 11-L Conveyor Belt between the outby end of the storage unit andthe
bottom step of the 6 south Mains Left Track overcast stairs for a distance of
30 feet in length. Old pieces of conveyor belt were humped up in the air, there
were 2 small rolls of conveyor belt, splicing nail buckets, splices, a conveyor
belt cutter and splicing template filling most of the required walkway in the
cited area. The walkways in this area was wet, muddy and very slippery without
having to traverse this extraneous materials. The Operator immediately started
to clear the extraneous materials after the issuance of this citation. Standard
75.1403 was cited 61 times
in two years at mine 3607230 (60 to the
operator, 1 to a contractor).

Petition for Civil Penalty at 18 (emphasis added).

The
citation was terminated on July 21, 2022, with the inspectors remarking that
“[a]ll of the extraneous materials have been cleaned out of the cited
travelway/walkway. There is now at least 24 inches of clear, unobstructed
travelway, therefore this citation is terminated. Id. at 19.

Analysis
for Citation No. 9205356


** **As the Secretary’s attorney seeks
the same modifications to this citation as he did for Citation No. 9204928 and
offers the same justification, the Court’s previous analysis applies.

Summary:

As
discussed above, the Secretary has cited to inapplicable precedent, by relying
upon an administrative law judge decision, inappropriately cited to Mechanicsville Concrete, Inc., 18 FMSHRC 877, (June 1996), for
a proposition that case does not support, and failed to meet the Commission’s
standards for an acceptable motion to approve settlement, per its decisions in AmCoal I and AmCoal II.

That
said, because the Commission has, to the best of this Court’s understanding, a
100% approval rate for settlement motions, it has decided to approve the
settlement in this instance because the Commission examines all settlement
determinations made by its judges, and has the authority, per 29 C.F.R.
§2700.71, to review a judge’s decision on its own motion.[2]

The
Court has considered the Secretary’s Motion and approves it solely on the basis
of the Commission’s decisions in The American Coal Co., 40 FMSHRC 983
(Aug. 2018) and Rockwell Mining, LLC, 40 FMSHRC 994 (Aug. 2018) for the
standard to be applied by administrative law judges when reviewing such
settlement motions under the Commission’s interpretation of section 110(k) of
the Mine Act. As noted, under those decisions, reasonable inquiry by the Court
is not permitted.

Accordingly, per the Commission’s decisions on the scope of a judge’s review authority of settlements, the “information” presented in this settlement motion is sufficient for approval.

WHEREFORE,
the motion for approval of settlement is GRANTED. [Citation
No]. 9205312 is modified to moderate negligence, Citation No. 9204928 is
modified to unlikely and non-S&S, Citation No. 9205356 is modified to
unlikely and non-S&S.

It
is ORDERED that the Respondent pay the agreed-upon civil penalty of $1,897.00
within 30 days of this order.[3]
Upon receipt of payment, this case is DISMISSED.

/s/
William B. Moran

William B. Moran

Administrative Law Judge

Distribution:

Attorney Kyle D. Stelmack, U.S. Department of Labor, Office of the Regional Solicitor

1835 Market Street, Mailstop SOL/22, Philadelphia, PA 19104

Craig S. Aaron, CONSOL Energy, Inc., 275 Technology Drive, Suite 101

Canonsburg, PA 15317 [email protected]

[1] RBK holds
only that the Secretary has the authority to vacate the citations. 15 FMSHRC at 2101

[2] 29 C.F.R. § 2700.71,
titled, “Review by the Commission on its own motion,” provides “[a]t any time
within 30 days after the issuance of a Judge's decision, the Commission may, by
the affirmative vote of at least two of the Commissioners present and voting,
direct the case for review on its own motion. Review shall be directed only
upon the ground that the decision may be contrary to law or Commission policy
or that a novel question of policy has been presented. The Commission shall
state in such direction for review the specific issue of law, Commission
policy, or novel question of policy to be reviewed. Review shall be limited to
the issues specified in such direction for review.

[3] Penalties may be
paid electronically at Pay.Gov, a service of the U.S. Department of the
Treasury, at https://www.pay.gov/public/form/start/67564508. Alternatively,
send payment (check or money order) to: U.S. Department of Treasury, Mine
Safety and Health Administration, P.O. Box 790390, St. Louis, MO 63179-0390.

It is vital to include Docket and A.C. Numbers when remitting payments.

Citation/Order MSHA’s Proposed Penalty Settlement Amount Other modifications to citation/order
9205312 $6,898 $1,393 Citation modified to moderate negligence; 80% reduction in penalty
9204928 $1,069 $252 Citation modified to unlikely and non-S&S; 76% reduction in penalty
9205356 $1,069 $252 Citation modified to unlikely and non-S&S; 76% reduction in penalty
TOTAL REVISED PENALTY Original total: $9,036.00 Revised total: $1,897.00 79% overall reduction in penalty