Secretary of Labor v. Patton Mining LLC
Secretary of Labor v. Patton Mining LLC (FMSHRC LAKE 2025-0199): Misplaced assessment reopened
Apply this precedent to your situation
This is citable Commission precedent from 2026, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
A proposed assessment was placed on the safety manager's desk while he was away and apparently fell between the desk and wall. The manager found it four days after the contest deadline, and the company received a delinquency notice several days later. Patton investigated the handling failure, contacted counsel, and trained mine personnel to place future assessments in a designated tray. The Secretary did not oppose relief. The Commission treated the event as a simple administrative mistake, reopened and remanded the assessment, and noted one Commissioner's dissent on reopening authority.
Decision snapshot
- Cited authority: 30 U.S.C. § 815(a); 29 C.F.R. § 2700.28
- Outcome: The penalty assessment was reopened and remanded for further proceedings.
- Key point: A physically misplaced assessment may support reopening when the operator investigates promptly and establishes a clear mail-handling protocol to prevent recurrence.
Full text (FMSHRC public release)
FEDERAL
MINE SAFETY AND HEALTH REVIEW COMMISSION
1331
PENNSYLVANIA AVE., N.W., SUITE 520N
WASHINGTON,
DC 20004-1710
|
SECRETARY OF LABOR MINE SAFETY AND HEALTH ADMINISTRATION (MSHA)
v.
PATTON MINING LLC |
|
|
Docket No. LAKE 2025-0199 A.C. No. 11-03182-613736
|
BEFORE: Rajkovich, Chair; Jordan, Baker, and Marvit, Commissioners
ORDER
BY: Rajkovich, Chair; Jordan, and Baker, Commissioners
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2018) (“Mine Act”). On April 4, 2025, the Commission received from Patton Mining LLC (“Patton Mining”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
We
have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested
assessments that have become final Commission orders under section 105(a). Jim
Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In
evaluating requests to reopen final orders, the Commission has found guidance
in Rule 60(b) of the Federal Rules of Civil Procedure, under which the
Commission may relieve a party from a final order of the Commission on the
basis of mistake, inadvertence, excusable neglect, or other reason justifying
relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall
be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR,
15 FMSHRC at 787. We have also observed that default is a harsh remedy and
that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be
reopened and appropriate proceedings on the merits permitted. See Coal Prep.
Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) indicate that the proposed assessment was delivered on January 30, 2025, and became a final order of the Commission on March 3, 2025. A delinquency notification was received by the operator on March 12, 2025.
Patton Mining asserts that its failure to timely contest the proposed assessment was the result of an “administrative error” and a “simple mistake.” Specifically, the operator states that the safety manager’s supervisor inquired whether the safety manager had received any proposed assessments. The safety manager then searched his desk and discovered the missing proposed assessment. It was placed on his desk while he was not in the office and apparently had fallen between his desk and wall. By that time, it was March 7, 2025, and the deadline for contesting the assessment had passed.
The supervisor received a delinquency notice on March 12, 2025. After locating the proposed assessment and receiving the delinquency notice, the safety manager and his supervisor commenced an investigation to determine why the proposed assessment was not timely processed. The supervisor also contacted counsel and requested that a motion to reopen be filed. The operator filed its motion to reopen soon after it completed the investigation into the circumstances surrounding the delinquency.
The operator contends that it has historically paid close attention to MSHA’s Proposed Assessments and mistakes such as this are uncommon. In the future, when proposed assessments come in the mail, personnel at the mine are trained to put them in the tray on the safety manager’s desk specifically designed for this purpose.
The Secretary does not oppose the request to reopen, but urges the operator to take steps to ensure that future penalty contests are timely filed.
Having
reviewed Patton Mining’s request and the Secretary’s response, we find
that the operator’s failure to timely contest the proposed assessment resulted
from an “administrative error” and a “simple mistake.” We note that the
operator conducted an investigation to determine why the proposed assessment
was not timely processed, and has trained personnel at the mine on the proper
protocol to bring delivered assessments to the safety manager’s attention. Shelter
Creek Capital, LLC, 34 FMSHRC 3053, 3055 (Dec. 2012) (holding that operators
must explain in detail what steps they have taken to ensure errors will not recur).
In the interest of
justice, we hereby reopen this matter and remand it to the Chief Administrative
Law Judge for further proceedings pursuant to the Mine Act and the Commission’s
Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the
Secretary shall file a petition for assessment of penalty within 45 days of the
date of this order. See 29 C.F.R. § 2700.28.
/s/ Marco M. Rajkovich, Jr.
Marco M. Rajkovich, Jr., Chair
/s/ Mary Lu Jordan
Mary Lu Jordan, Commissioner
/s/ Timothy J.
Baker
Timothy J. Baker, Commissioner
Commissioner Marvit, dissenting:
I write to disagree with the Majority in this case for the reasons set forth below.
In Explosive
Contractors, 46 FMSHRC 965 (Dec. 2024), I dissented and explained that
Congress did not grant the Commission the authority to reopen final orders
under section 105(a) of the Mine Act. The Commission’s repeated invocation of
Federal Rule of Civil Procedure 60(b) cannot overcome the statutory language.
However, in Belt Tech, I explained in my concurrence that “the Act
clearly states that to become a final order of the Commission, the operator
must have received the notification from the Secretary.” 46 FMSHRC 975 (citing Hancock
Materials, Inc., 31 FMSHRC 537 (May 2009)). Taken together, these opinions
stand for the proposition that the Commission may not reopen final orders under
its statutory grant, but an operator may proceed if it has not properly
received a proposed order.
In the instant case, as the Majority
recounts, the Commission’s order became final under the language of section
105(a). The Majority, however, votes to reopen the case. The Mine Act has not
granted us authority to reconsider final orders of the Commission as I set out
more fully in Explosive Contractors. To the contrary, it has limited our
authority to do so. Therefore, I respectfully dissent and would deny reopening.
/s/ Moshe Z.
Marvit
Moshe Z. Marvit, Commissioner
Distribution:
Christopher D. Pence, Esq.
Pence Law Firm PLLC
10 Hale Street, 4th Floor
PO Box 2548
Charleston, WV 25329-2548
Thomas A. Paige, Esq.
Office of the Solicitor
U.S. Department of Labor
Division of Mine Safety and Health
200 Constitution Avenue NW, Suite N4428
Washington, DC 20210
Melanie
Garris
US
Department of Labor/MSHA
Office of Assessments, Room N3454
200 Constitution Ave NW
Washington, DC 20210
Chief Administrative Law Judge Glynn F. Voisin
Office
of the Chief Administrative Law Judge
Federal Mine
Safety Health Review Commission
1331
Pennsylvania Avenue, NW Suite 520N
Washington,
DC 20004-1710
Get today's answer for your situation
You just read Commission precedent from 2026. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.