OSHRC ALJ decision Docket 96-1424 Decided May 7, 1998 Mixed result Judge Ken S. Welsch

Geo. Gradel Company

Training violation affirmed after a backhoe punctured a gas line

Apply this to your situation

This order from 1998 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1998
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Geo. Gradel Company was an excavation contractor replacing a sewer line during a road-widening project in Ohio. A backhoe operator punctured an eight-inch high-pressure gas line where the sewer crossed it. The judge affirmed a serious training violation because Gradel had only told workers to be careful and had not instructed them how to recognize and avoid the underground utility hazard. The judge also credited testimony that workers were asked after the incident to sign safety sheets that were later backdated. The alleged willful violation for failing to determine the gas line's exact location was vacated because the company had requested utility markings, exposed part of the line by hand, and planned further hand digging before the operator acted without supervisory knowledge. A separate excavation-inspection item was withdrawn, and the judge assessed a $3,000 penalty for the training violation.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.21(b)(2); 29 C.F.R. § 1926.651(k)(1); 29 C.F.R. § 1926.651(b)(3)
  • Outcome: One serious item affirmed with a $3,000 penalty, one item withdrawn, and one alleged willful item vacated.
  • Key point: General warnings to be careful did not satisfy the duty to train employees about the specific hazards of excavating near a known gas line.

Full text (OSHRC public release)

))))))))))))))))))))))))))))))))))))))))))))),
Secretary of Labor, *
Complainant, *
*
v. * OSHRC Docket No. 96-1424
*
Geo. Gradel Company, *
Respondent. *
)))))))))))))))))))))))))))))))))))))))))))))-

Appearances:

                 Kenneth Walton, Esquire                                Frank A. Justen, Esquire
                         U. S. Department of Labor                              Sylvania, Ohio
                         Office of the Solicitor                                         For Respondent
                         Cleveland, Ohio
                                  For Complainant

Before: Administrative Law Judge Ken S. Welsch

                                                          DECISION AND ORDER
                 Geo. Gradel Company (Gradel) is an excavation contractor whose office is located in

Toledo, Ohio. On August 27, 1996, a backhoe operator working for Gradel punctured a gas
utility line while removing a sewer line in Perrysburg, Ohio. Occupational Safety and Health
Administration (OSHA) compliance officer Robert Koedam investigated the incident. As a result
of Koedam’s investigation, the Secretary issued two citations to Gradel on September 17, 1996.
Citation No. 1 alleges a serious violation of § 1926.21(b)(2) for failure to instruct each
employee in the recognition and avoidance of unsafe conditions. Item 2 of the citation, alleging a
serious violation of § 1926.651(k)(1), was withdrawn by the Secretary at the hearing (Tr. 6).
Citation No. 2 contains one item that alleges a willful violation of § 1926.651(b)(3) for
failure to determine the exact location of underground installations by safe and acceptable means
when approaching the estimated location.
Gradel contests the two remaining alleged violations, their classifications, and proposed
penalties, and asserts the affirmative defense of unpreventable employee misconduct with regard
to the willful allegation.
Background
Gradel began work in May 1996 on a project to widen South Boundry, a two-lane road in
Perrysburg, Ohio. Gradel’s responsibilities on the project included installing a new main sewer
line; widening the road by 8 to 10 feet on each side; installing new curbs, gutters, drainage, and
crossovers; and re-stoning and blacktopping the widened areas (Tr. 139-140).
In order to install the new sewer line, Gradel had to remove an existing line. On the
morning of August 27, 1996, one of Gradel’s crews met with Gradel foreman James Zibbel. The
crew consisted of an operating engineer, Ronald Amos, and two laborers, Gerald Whalen and
Jami Aravantis (Tr. 16-17, 162-163). Zibbel told Amos and the others “to get the flow line of the
ditch started, expose the gas main and dig down to the flow line of the catch basin” (Tr. 27). This
involved removing the existing sewer pipe where it crossed an 8-inch gas main. Zibbel planned to
expose the gas main by hand and then to remove the existing sewer pipe (Tr. 26-27).
Zibbel told Amos that he would be using the backhoe Amos designated as “the 566.”
Amos objected that the 566 “was entirely the wrong machine to put in that position for that job . .
. . It’s too big” (Tr. 20). Zibbel told Amos that the 566 backhoe was the only machine available
and that he would have to use it (Tr. 29, 180-181).
Part of the sewer line that was to be replaced crossed over the gas line. As the gas line
approached the sewer line, it dipped at a 45º angle. On August 27, Gradel had uncovered only
one side of the gas line at the 45º angle. The exposed portion consisted of 2 feet of the straight
gas line and another 2 feet of the angled line. No one from Gradel knew exactly how or where
the gas line was configured underneath the sewer line (Exhs. C-1, C-3, R-2; Tr. 20, 24, 89, 148,
168).
At approximately 8:30 on the morning of August 27, Amos was operating the 566
backhoe to remove the old sewer pipe. The teeth of the backhoe’s bucket punctured the gas line
(Tr. 52). Gradel alerted the fire department and the gas company, and blocked off the road. A
high school located 300 to 400 yards west of the gas line rupture was evacuated (Tr. 29). Gradel
fired Amos the next day as a result of the incident (Tr. 19).

                                         Discussion
    The Secretary has the burden of proving the violation.
           In order to establish a violation of an occupational safety or health
           standard, the Secretary has the burden of proving: (a) the
           applicability of the cited standard, (b) the employer’s
           noncompliance with the standard’s terms, (c) employee access to
           the violative conditions, and (d) the employer’s actual or

constructive knowledge of the violation (i.e., the employer either
knew or, with the exercise of reasonable diligence could have
known, of the violative conditions).

Atlantic Battery Co., 16 BNA OSHA 2131, 2138 (No. 90-1747, 1994).
Citation No. 1
Item 1: Alleged Serious Violation of § 1926.21(b)(2)
The Secretary alleges that Gradel committed a serious violation of § 1926.21(b)(2), which
provides:
The employer shall instruct each employee in the recognition and
avoidance of unsafe conditions and the regulations applicable to his
work environment to control or eliminate any hazards or other
exposure to illness or injury.

   The citation specifically alleges that:

           This employer did not instruct each employee in the recognition and
           avoidance of unsafe conditions and the regulations applicable to
           their work in that on or about August 27, 1996, employees were
           exposed to explosion hazard when the 8" high pressure gas main
           was damaged when the model #566 Koehring Excavator punctured
           or caused a 12" storm sewer to puncture it. Neither employee was
           trained by this company on the avoidance of this unsafe condition
           through manual removal of the soil to find the exact location of the
           gas main in a safe and acceptable manner.


   It is undisputed that § 1926.21(b)(2) applies to the cited conditions in the present case,

and that Gradel’s employees were exposed to the hazard of a gas explosion. Item 1 alleges a
training violation; therefore, the employer must necessarily have knowledge if a violation exists.
The only element of the violation at issue is whether Gradel failed to instruct its employees in the
recognition and avoidance of the hazards of excavating in areas known to contain gas lines.
Amos testified that he never received training from Gradel relating to the location of
underground installations or gas lines (Tr. 32). Gradel contends that it did provide the required
training, but its evidence is scant. Whalen, a lead laborer with Gradel, gave this account of his
training of other Gradel employees (Tr. 189):
Q.: Are you more or less like a crew leader?
Whalen: I do what the boss tells me. I mean, we get new people on
the job, and a lot of times they -- you can’t put five new
people there. And you put a couple of new ones with me to
help them out and stuff like that.

           Q.:            You provide some training for these newer people?

           Whalen:        Oh, I try to help them out.

   When asked how many times he and his crew had been told about the danger of working

near the gas line, Whalen responded, “Quite a bit. We knew it was there . . . [W]e always
remembered the gas line next to us” (Tr. 195).
Zibbel, the foreman in charge of the crew, gave similar vague testimony regarding safety
training (Tr. 156):
From the day we started on that main line sewer, which was our
first project and especially encountering [a gas line] that wasn’t
marked, they were all told to be careful.
And at that point there was one crew working and I was
working along with them on a daily basis. Any time I would see the
side of that became exposed in any way, shape or form, I would tell
them, you know, “Move things over a little. Let’s be careful and
watch what we’re doing.”
And, I think it was pretty much on a daily basis that a lot of
these -- the guys that worked around it were made aware of it.

   When Zibbel was asked if he ever gave the crew any safety training other than telling them

to be careful, he replied, “No” (Tr. 157-158).
No one who testified for Gradel mentioned holding weekly safety meetings. Gradel
contends both in its brief and its reply brief that Gradel held weekly safety meetings that Amos
attended and signed attendance sheets showing his presence. This assertion is curious both
because Gradel adduced no such evidence, and because the only evidence relating to safety
meetings is detrimental to Gradel’s case.
Amos testified that, after he punctured the gas line on August 27, he and the crew
gathered in a nearby parking lot and ate while the various emergency vehicles arrived at the site.
Amos stated that Zibbel “showed up with a bunch of safety sheets and said we had to sign them
that day” (Tr. 30). Amos testified that he and his crew “were given several of them there at noon,
and we were told to read and sign them. So we read them and signed them that day” (Tr. 31).
Amos identified Exh. C-2 as a safety sheet he signed on August 27 (the only safety sheet
introduced and admitted into evidence) (Exh. C-1; Tr. 31). Amos noted that the safety sheet,
which he signed on August 27, was not dated at that time. The date “7-8-96" appeared on Exh.
C-2 after Amos and the crew signed it (Tr. 32). Compliance officer Koedam testified that he
warned Gradel not to provide him with false information (Tr. 91). When he asked if Gradel had
any training documentation, Gradel did not provide any (Tr. 103).
Amos’s testimony is uncontradicted. Neither Zibbel, Whalen, nor Daniel Murry, Gradel’s
project manager, disputed Amos’s assertion that he and the crew were directed to sign several
safety sheets on August 27, which were then back-dated. Neither Zibbel, Whalen, or Murry
asserted that Gradel held the weekly safety meetings claimed by Gradel in its post-hearing briefs.
Amos’s testimony regarding Gradel’s lack of safety training and its attempted post hoc creation of
a fraudulent record of safety meetings is accepted as unrefuted.
Instruction in the recognition and avoidance of unsafe conditions requires more than weak
admonitions to “be careful” and reminders that a potential hazard is nearby. See Anderson
Excavating and Wrecking Co., 17 BNA OSHC 1890, 1892 (No. 92-3684, 1997). Gradel failed
to provide its employees with safety training related specifically to its work in proximity to the gas
line. Reminders to “be careful” are inadequate to meet the requirements of § 1926.21(b)(2). The
Secretary has established a violation of § 1926.21(b)(2).
The hazard created by Gradel’s violation of § 1926.21(b)(2) was that of a gas explosion.
Such an explosion could result in death or serious injury. The violation is serious.
Citation No. 2
Item 1: Alleged Willful Violation of § 1926.651(b)(3)
The Secretary alleges that Gradel committed a willful violation of § 1926.651(b)(3), which
provides:
When excavation operations approach the estimated location of
underground installations, the exact location of the installations
shall be determined by safe and acceptable means.

   On the morning of August 27, 1996, Zibbel met with a crew consisting of Amos, Whalen,

and Aravantis. Zibbel told the crew their assignment that day was to remove the old sewer line
and install a new one at a location where the sewer line crossed over the gas line (Tr. 19).
Previously, Zibbel had contacted the Underground Protective Service (UPS) of Ohio, which
notified the utilities in the area that excavation work was going to be done. Each utility sent out a
crew to mark where the various utility lines were located. Most of the utilities spray paint the
location of the utility line, Zibbel testified, “or if the gas company is concerned, run flags along it
and tell you where it’s at” (Tr. 145). In the area where Gradel’s crew was working on August 27,
the gas company had marked the 8-inch high-pressure gas line with flags for a distance of about
1,500 feet (Tr. 146).
The gas company had previously exposed part of the gas line at that area to show where
the gas line stopped (Tr. 146). Gradel’s crew spent approximately an hour and a half exposing
the top 45º bend of the gas line by hand (Tr. 163-165). After exposing the east side of the bend in
the gas line, Zibbel realized that he needed to order more sewer pipe (Tr. 147). Zibbel halted the
work and either Whalen or Aravantis stuck a shovel in the ground next to the gas line (Tr. 40,
149). Zibbel explained that, “It’s normal practice that once you located a utility, you put a shovel
in next to it if any additional work is going to take place any time during that day” (Tr. 148).
Zibbel sent Whalen to pick up the additional sewer pipe. According to Zibbel and Whalen,
Zibbel told the crew to “just hold tight” until Whalen got back (Tr. 151, 164, 166, 174, 197-198).
Both Zibbel and Whalen recalled specifically that Zibbel used the expression “hold tight.” Zibbel
testified that he intended “hold tight” to mean that no more work was to be done around the gas
line until Whalen returned (Tr. 151-152). Whalen testified that he understood “hold tight” to
mean the crew was to do no more digging “[u]ntil I got back or Jim got back, and especially no
digging around the gas line” (Tr. 194).
Amos did not say whether Zibbel told the crew to “hold tight,” but he was adamant that
Zibbel did not tell him to wait for Whalen’s return (Tr. 40, 43). Zibbel conceded that he did not
specifically order Amos not to dig, but he assumed Amos would know that Zibbel wanted him to
wait (Tr. 167):
I really can’t say that he violated any instructions, but I didn’t
specifically say, “Do not touch those controls until I get back.”
But, I don’t believe I’ve ever worked around any other operators
that would have taken it on themselves to work that close to a high-
pressure gas line without a qualified person there to work with
them.

    Zibbel testified that he planned to do some more hand digging around the gas line when

Whalen got back (Tr. 152). After Whalen’s return, Zibbel intended to expose more of the line
(Tr. 163):
[W]hen Jerry got back, we would have exposed the west side the
same way as we did the east, and we would have removed the old
sewer and put the new sewer in place of that, set a manhole, and
then we had two or three other pipe to run out and dump it into the
creek.

   The Secretary has failed to establish that Gradel committed a violation of §

1926.651(b)(3). The standard requires the employer to determine the exact location of the
installations when excavation operations approach their estimated locations. Gradel took the
following steps to determine the exact location of the gas line: (1) Gradel called UPS, which
notified the gas company, which came out and placed flags along the site of the gas line; (2)
Gradel’s crew uncovered by hand a 4-foot section of the gas line where it dipped in order to
determine its configuration in relation to the sewer line; and (3) a member of Gradel’s crew stuck
a shovel in the ground next to the gas line when Gradel temporarily stopped working in that area.
Gradel was still in the process of determining the exact location of the gas line when Amos
punctured the line. Zibbel testified that he intended to do more hand-digging and expose the west
side of the line after Whalen returned. Amos’s action in digging with the backhoe was done in
Zibbel’s absence and without his knowledge. Both Zibbel and Whalen thought that no digging
with the backhoe was to be done until Whalen’s return. Zibbel reasonably assumed that his
instruction to “hold tight” would be understood and followed by the crew. Neither Zibbel nor any
other supervisory person at Gradel knew or, with the exercise of reasonable diligence, could have
known, that Amos would either not understand or choose to ignore Zibbel’s instruction. This
item is vacated.
Penalty Determination
The Commission is the final arbiter of penalties in all contested cases. Under § 17(j) of the
Act, in determining the appropriate penalty, the Commission is required to find and give “due
consideration” to (1) the size of the employer's business, (2) the gravity of the violation, (3) the
good faith of the employer, and (4) the history of previous violations. The gravity of the violation
is the principal factor to be considered.
Gradel employed approximately 100 workers at the time of the inspection (Tr. 101). No
evidence relating to good faith was adduced. Gradel has a history of prior violations (Tr. 97).
The gravity of Gradel’s violation of § 1926.21(b)(2) is high. Failure to instruct employees in the
recognition and avoidance of hazards associated with underground installations of gas line could
result in an explosion. A penalty of $3,000.00 is assessed.
FINDINGS OF FACT AND CONCLUSIONS OF LAW
The foregoing decision constitutes the findings of fact and conclusions of law in
accordance with Federal Rule of Civil Procedure 52(a).
ORDER
Based upon the foregoing decision, it is hereby ORDERED that:
1. Item 1 of Citation No. 1, § 1926.21(b)(2), is AFFIRMED and a penalty of
$3,000.00 is assessed;
2. Item 2 of Citation No. 1, § 1926.651(k)(1), is withdrawn by the Secretary and no
penalty is assessed; and
3. Item 1 of Citation No. 2, § 1926.651(b)(3), is VACATED.

                                                          KEN S. WELSCH

Date: Judge