🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 95-1482 Decided October 7, 1996 Citations affirmed Judge Paul L. Brady

Hemphill Construction Co., Inc.

Repeat trench spoil-pile violation affirmed

Apply this to your situation

This order from 1996 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1996
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Hemphill installed a water line in a trench while a backhoe placed excavated soil at the trench edge. An OSHA regional investigator observed employees enter the trench with the spoil pile nearby and photographed the condition. The judge credited that testimony despite the investigator's lack of compliance-officer training and found that employees were exposed to material falling or rolling into the excavation. A prior uncontested citation under the same standard involved the same type of spoil-placement hazard, establishing substantial similarity. The violation was affirmed as repeated, and a $4,500 penalty was assessed.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.651(j)(2)
  • Outcome: The repeat trench spoil-pile item was affirmed, and a $4,500 penalty was assessed.
  • Key point: A prior final order under the same standard establishes a prima facie repeat case when both violations involve excavated material placed too close to a trench edge.

Full text (OSHRC public release)

                             United States of America
      OCCUPATIONAL SAFETY AND HEALTH REMEW COMMISSION
                       1120 20th Street, N.W., Ninth Floor
                          Washington, DC 20036-34 19



                                                                        Phone:(202)606-5400
                                                                          Fax: (202)606-5050

SECRETARY OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 95-1482
HEMPHILL CONSTRUCTION COMPANY, INC.
Respondent.

                  NOTICE OF DOCKETING
           OF ADMINISTRATIVE LAW JUDGE’S DECISION
 The Administrative Law Judge’s Report in the above referenced case was

docketed with the Commission on September 5, 1996. The decision of the Judge
will become a final order of the Commission on October 7, 1996 unless a
Commission member directs review of the decision on or before that date. ANY
PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
Any such petition should be received by the Executive Secretary on or before
September 25, 1996 in order to permit sufficient time for its review. See
Commission Rule 91, 29 C.F.R. 2200.91.
All further pleadings or communications regarding this case shah be
addressed to:
Executive Secretary
Occupational Safety and Health
Revrew Commission
1120 20th St. N.W., Suite 980
Washington, D.C. 20036-3419
Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DOgL
Room S4004
200 Constitution Avenue, N.W.
Washington, D.C. 20210
If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
havmg questions about review nghts may contact the Commission’s Executive
Secretary or call (202) 606-5400.
FOR THE COMMISSION A /

Date: September 5, 1996 Ray H. Darling, Jr.
Executive Secretary
DOCKET NO. 95-1482
NOTICE IS GIVEN TO THE FOLLOWING:

Associate Regional Solicitor
Office of the Solicitor
Chambers Bldg., Highpoint Office
Center, Suite 150
100 Ceriterview Drive
Birmingham, AL 35216

Stephen J. Rimmer, Es l

Rimme:, Rawlings, MacP nnis &
Hedglm, PA.
210 E. Capitol Street
1290 Deposit Guaranty Plaza
Jackson, MS 392012302

Paul L. Brady
Administrative Law Jud e
Occupational Safety an d Health
Review Commission
Room 240
1365 Peachtree Street, N.E.
Atlanta, GA 30309 3119

00109254383:04
United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1365 Peachtree Street, N.E., Suite 240
Atlanta, Georgia 30309-3 119

Phone: (404) 347-4 197 Fax: (404) 347-0113

                                                              .
                                                              .
SECRETARY OF LABOR,                                           .. .
                                                                   .
     Complainant,                                             ..
                                                               ..
                       v.                                       ..                OSHRC Docket No. 95-1482
                                                                 .

HEWHILL CONSTRUCTION CO., INC.,
Respondent.

APPEARANCES

          Carla J. Gunnin, Esq.                               Stephen J. Rimmer, Esq.
                   Office of the Solicitor                            Rimmer, Rawlings, MacInnes & Hedglin
                   U. S. Department of Labor                          Jackson, Mississippi
                   Birmingham, Alabama                                         For Respondent
                            For Complainant

Before: Administrative Law Judge Paul L. Brady

                                         DECISION       AND ORDER

          This proceeding is brought pursuant to Section 10 of the Occupational Safety and Health Act

of 1970 (Act) to contest a citation and proposed penalty issued by the Secretary of Labor (Secretary)
pursuant to Section 9(a) of the Act. The citation alleges a repeat violation of an excavation standard
that occurred off Highway 80 in Brandon, Mississippi.
The facts are not in dispute that on August 1, 1995, Hemphill Construction Co., Inc.,
(Hemphill) was engaged in laying a ten-inch water line parallel to the highway. Johnny McDowell,
Regional Investigator for the Occupational Safety and Health Administration (OSHA), observed the
operation, which involved approximately six employees, a backhoe and a bulldozer.
The standard at 1926.651(J)(2) pertains to protection of employees from loose rock or soil:
(2) Employees shall be protected from excavated or other materials or equipment
that could pose a hazard by falling or rolling into excavations. Protection shall be
provided by placing and keeping such materials or equipment at least 2 feet (.61 m)
from the edge of excavations, or by the use of retaining devices that are sufficient to
prevent materials or equipment from falling or rolling into excavations, or by a
combination of both if necessary.

    The citation alleges as follows:

    Employees working in and around trench located along Highway 80 near Brandon
    MS were exposed to injury corn falling or rolling spoil that was not properly stored
    at least 2 feet away from the edge of the trench on the Terripen Skin Creek Sewer and
    Water project.

    McDowell testified and he noted the ongoing process of opening and closing the trench

while traveling on Highway 80 to his office. He observed two men exit a trench where a bulldozer
and backhoe were being operated. He “became very concerned” when the men re-entered the trench.
There was a large spoil pile on the side. By cellular telephone he notified the OSHA area office,
since he is not authorized to issue citations (Tr. 6-7, 11).
Before leaving the area, McDowell approached the trench and took some DhotograDhs. He
A Y A

testified that the spoil pile depicted in Exhibit C-l was to the edge of the trench, which was averaged
six to eight feet deep (Tr. 9-11). McDowell saw the backhoe operator excavate the trench and place
the dirt on the side (Tr. 19).
Compliance Officer James Pinnix received the referral from McDowell and went to the
worksite. The trench had been covered, but after conferring with McDowell and viewing his
photographs, Pinnix decided Hemphill had violated the standard. The citation was then issued.
Hemphill offered no evidence to directly refute McDowell’s testimony that employees
worked in the trench while spoil was piled to its edge. Charles Hubbard, a pipe layer at the site,
testified that he believed the spoil was required to be two feet fi-om the side of the trench and did not
recall any time it was closer than two feet (Tr. 1110113). In addition, the foreman, L. C. Reynolds,
testified a safety meeting was held that same day when placement of spoil piles was discussed (Tr.
98). Reynolds
m was not present when McDowell visited the site.
Hemphill’s main contention is that the Secretary failed to prove the violation based upon
McDowell’s testimony. It is argued that since he is not a compliance officer and not trained in

                                                2

trenching regulations, his report of the alleged violation lacks credibility. In support of this
argument, Hemphill refers to McDowell’s testimony at Page 21 of the transcript:
. . . [Llet’s just assume the spoil pile is more than two feet from the edge of the
trench, is it your position that if there is any loose dirt between the spoil pile and the
side of the trench, that the OSHA regs pertaining to spoil pile placement has been
violated?
A I don’t think that I can answer that. I don’t think I’m qualified to
answer that.

    In addition Hemphill points out that McDowell did not know how wide the trench was at the

bottom or top and its slope (Tr. 16-17). Both Hubbard and Reynolds testified that the trench was
about six to ten feet wide at the top and 28 inches at the bottom contrary to McDowell’s testimony.
They believed it averaged about four and one-half feet deep (Tr. 94-95107).
Hemphill maintains that the spoil pile as seen in Exhibit No. 1 is actually back Tom the edge
of the trench, but admits there was “loose dirt” near the edge that fell Corn the bucket (Tr. 112,116).
To help make a distinction between the loose dirt and a spoil pile, Hemphill refers to Pinnix’s
testimony. In his opinion, it was a question of whether there was a “. . . large enough piece of soil
. . . that could fall off in that trench and injure an employee . . . ” Pinnix did not actually know if
a hazardous condition existed when McDowell was present and acknowledged McDowell’s lack of
training in the area (Tr. 50-Y). Since the compliance officer authorized issuance of the citation
solely on the basis of McDowell’s opinions and photographs, Hemphill argues the Secretary failed
to prove the violation.
To establish a violation of a standard, the Secretary must show by a preponderance of the
evidence that: (1) the cited standard applies, (2) its terms were not met, (3) employees had access
to the violative condition, and (4) the employer knew or could have know of it with the exercise of
reasonable diligence. Seibel Modern Mfg. & Weldirrg Corp., 15 BNA OSHC 12 18, 1991 CCH
OSHD 7 29,442, p. 39,678 (No. 88-821, 1991). There is no question the trenching standard applied
to the project. The essence of the standard in question is to provide protection to employees Tom
the hazard of material or equipment falling into excavations. There is no dispute that there was dirt
or a spoil pile within two feet of the edge of the trench. The issue presented is whether the material
posed a hazard to employees.
The Secretary’s evidence shows that McDowell, within three feet of the trench, observed
a large pile of excavated dirt on the opposite side. He saw the backhoe place the dirt to the edge of
the trench, and he saw employees enter it (Tr. 7,9, 15, 1, Exh. C-l). Although McDowell is not a
trained compliance officer, he was familiar with the standard and its requirements (Tr. 29). His
testimony is deemed credible for determining whether the terms of the standard were not met.
Although there were questions about the location of employees as viewed in some photographs,
McDowell’s testimony clearly established employees were in the trench and exposed to the hazard
of falling material.
The violation having been established, it must now be determined if it is of a repeat nature
as alleged. A violation is a repeated violation under Section 17(a) of the Act, 29 U.S.C. 8 666(a),
if, when it is committed, there was a Commission final order against the employer for a substantiallvd
similar violation. Potlatch Corp., 7 BNA OSHC 1061, 1063,1979 CCH OSHD 7 23,294, p. 28,17 1
(No. 16183,1979). The Secretary’s evidence shows a citation was issued to Hemphill on April 6,
1994, alleging a serious violation of 29 C.F.R. @1926.651(J)(2) (Exh. C-4). The citation was not
contested and under Commission precedent, the uncontested citation became a final order. See All
Phase Elect. & Mizint.,Inc., 15 BNA OSHC 1301, 1303, 1991-93 CCH OSHD 7 29,482, p. 39,781

(No. 900505,199l).
Although Hemphill does not deny the citation was issued or became a final order, it denies
a substantial similarity of conditions. Hemphill argues that the two work sites were 150 to 200 miles
apart, and that different types of trenches and different employees were involved (Tr. 45.46,69-70).
The Commission has held that the Secretary may establish a prima facie case of substantial similarity
by showing that the final order alleged a failure to comply with the same standard. The burden then
shifts to the employer to rebut that showing. Monitor Constr. Co., 16 BNA OSHC 1589, 1593.
1993-95 CCH OSHD 7 30,338, p. 41,825 (No. 91-1807, 1994). Under Potlatch, supra, the
conditions set forth by Hemphill bear on the size of the penalty and not on the “repeated” character
of the violations. Evidence of similar hazards is most relevant to determining substantial similarity
and if a violation is repeated. Stone Container Corp., 14 BNA OSHC 1757, 1762, 1987-90 CCH
OSHD f[ 29,064, p. 38,8 19 (No. 88-3 10, 1990). The violations found to exist in this case are not
only substantially similar, but are almost identical. In both instances, protection was not provided

                                              4

employees by placing excavated material at least two feet from the edge of a trench. The violations
were substantially similar and, therefore, the present violation is repeated.
Section 17(j) of the Act, 29 U.S.C. 3 666(j), provides that the Commission shall assess an
appropriate penalty for each violation, giving due consideration to the size of the employer, the
gravity of the violation, the good faith of the employer, and the employer’s history of previous
violations. Hemphill has approximately 90 employees and its history includes the April, 1994,
violation of the identical standard involved in this case. Several witnesses testified regarding
Hemphill’s good faith efforts and its safety training program.
The Commission considers the gravity of the violation the principal factor. See Nacirema
Operating co., 1 BNA OSHC 1001, 1003, 1971-73 CCH OSHD 7 15,032, pp. 20,043-4 (No. 4,
1972). Although the inspecting officer believed the depth of the trench to be seven to eight feet, two
witnesses working in and around the trench testified it was about four feet. The evidence shows that
the trench varied in depth at different pints; and, considering that it was continuously opened and
closed, the gravity is deemed moderate. Upon consideration of all the factors, the proposed penalty
in the amount of $4,500 is deemed appropriate.

                 FINDINGS OF FACT AND CONCLUSIONS OF LAW
    The foregoing decision constitutes the findings of fact and conclusions of law in accordance

with Federal Rule of Civil Procedure 52(a).

                                          ORDER
    Based on the foregoing decision, it is hereby ORDERED:
    The citation is affirmed and a penalty in the amount of $4,500 is hereby assessed.



                                                             ISI PAUL L. BRADY          e
                                           PAUL L. BRADY
                                           Judge

Date: August 26, 1996 ’

Get today's answer for your situation

You just read what one judge decided for one employer in 1996, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.