🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 95-0494 Decided October 30, 1996 Mixed result Judge Benjamin R. Loye

Globe Contractors, Inc.

Power-line and trench items affirmed, inspection item vacated

Apply this to your situation

This order from 1996 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1996
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

OSHA inspected Globe's underground-construction site on a public road and observed a backhoe operating within ten feet of an overhead wire and an employee standing on a ladder and later a water main inside an unprotected trench. The judge rejected Globe's warrant and inspection-conduct objections because the open roadway site carried no reasonable expectation of privacy and Globe showed no prejudice. The power-line-clearance item was affirmed as serious with a $2,000 penalty. The competent-person inspection item was vacated because it did not address a changed trench condition and duplicated the cave-in-protection item. The cave-in item was affirmed as willful because the foreman knew of the entries, the work rule did not address standing on ladders or pipes in a trench, and employees attempted to conceal the conduct from OSHA. The proposed $56,000 penalty was reduced to $20,000 because the likelihood of a cave-in injury in the specific positions was remote, producing a total penalty of $22,000.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.600(a)(6), incorporating § 1926.550(a)(15); 29 C.F.R. § 1926.651(k)(2); 29 C.F.R. § 1926.652(a)(1)
  • Outcome: The power-line and cave-in items were affirmed, the inspection item was vacated, and penalties totaling $22,000 were assessed.
  • Key point: An employee can be exposed to a cave-in hazard while standing above the trench bottom on a ladder or pipe, and knowing tolerance of that conduct supported a willful classification.

Full text (OSHRC public release)

                             United States of America
      OCCUPATIONAL        SAFETY AND HEALTH REVIEW COMMISSION
                        1120 20th Street, N.W., Ninth Floor
                           Washington, DC 20036-3419



                                                              \           Phone:(202)606-5400
                                                                           Fax:(202)606-5050

SECRETARY OF LABOR
Complainant
v. OSHRC DOCKET
NO. 954494
GLOBE CONTRACTORS, INC.
Respondent. -

                      NOTICE OF DOCKETING
           OF ADMINISTIXITVE              L4W JUDGE’S         DECISION

The Administrative    Law Judge’s Report in the above referenced case was

docketed with the Commission on September 30, 1996. The decision of the Judge
will become a final order of the Commission on October 30, 1996 unless a
Commission member directs review of the decision on or .before that date. ANY
PARTY DFIRING REWW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A I’ETITION FOR DISCRETIONARY REVIEW.
Any such petition should be received b the Executive Secretary on or before
October 21, 1996 in order to ermit sIlk cient time for its review. See
Commission Rule 91, 29 C.F. w .2200.91.
All further pleadings or communications regarding this case shall be
addressed to:
Executive Secretary
1 Occupational Safety and Health ’
Review Commission
1120 20th St. N.W., Suite 980
Washington, D.C. 20036-3419

Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DOgL
Room S4004
200 Constitution Avenue, N.W.
Washington, D.C. 20210
If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
having questions about review nghts may contact the Commission’s Executive
Secretary or call (202) 606-5400.
FOR THE COMMISSION

Date: September 30, 1996
.
DOCKET NO. 95-0494
NOTICE IS GIVEN TO THE FOLLOWING:

Richard J. Fiore
Re lonal Solicitor U.S. DOL
23fSouth Dearbakn St., 8th Floor
Chicago, IL 60604

Charles B. Palmer
Palmer Law Offices
Crossroads Co orate Center
20800 Swenson% rive, Suite 425
Waukesha, WI 53186

C.H. Stuart Charlson
Krukowski and Costello
7111 West Ed erton Avenue
Milwaukee, d 53220

Benjamin R. LQ e
Administrative la w Jud e
Occupational Safety an B Health
Review Commission
Room 250
1244 North S eer Boulevard
Denver, CO tr0204 3582

00114153133:05
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1244 IN. Speer Boulevard
Room 250
Denver, Colorado 802044582

SECRETARY OF LABOR,
Complainant, ’

                           V.                              i OSHRC DOCKET NO. 95-0494
                                                           I

GLOBE CONTRACTORS, INCORPORATED, i
1
Respondent. 1m

APPEARANCES:

      For the Complainant:
               Steven E. Walanka, Esq. U.S. Department   of Labor, Office of the Solicitor, Chicago, Illinois

      For the Respondent:
               Charles 8. Palmer, Esq., Palmer Law Ofices,      Waukesha, Wisconsin;    C.H. Stuart Charlson, Krukowski and
                 Costello, Milwaukee, Wisconsin

Before: Administrative Law Judge: Benjamin R. Loye

                                          DECISION AND ORDER

      This proceeding arises under the Occupational Safety and Health Act of 1970 (29 USC. Section

65 1 et seq.; hereafter called the “Act”).
Respondent, Globe Contractors, Incorporated (Globe), at all times relevant to this action maintained
a place of business at 4543 Meade Street, Appleton, Wisconsin, where it was engaged in underground

construction. Respondent admits it is an employer engaged in a business affecting commerce and is subject
to the requirements of the Act.
On October 21, 1994 the Occupational Safety and Health Administration (OSHA) conducted an
inspection of Globe’s Appleton work site. As a result of that inspection, Globe was issued citations alleging
violations of the Act together with proposed penalties. By filing a timely notice of contest Globe brought

this proceeding before the Occupational Safety and Heaith Review Commission (Commission).
On April 10, 1996, a hearing was held in Oshkosh, Wisconsin. The parties have submitted briefs
ori the issues and this matter is ready for disposition.
Alleged Violations of the Fourth Amendment
and 68(a) and 8(e) of the Act. and Selective Prosecution

    As a threshold matter Globe argues that OSHA’s inspection of its work site was conducted without

either its consent or a warrant, in violation of the Fourth Amendment. Globe further maintains that the
OSHA inspection and citations at bar resulted from the the OSHA Compliance Officer’s personal animosity
towards Respondent, and that the OSHA inspection was not conducted within reasonable limits as required

by $8(a) and S(e) of the Act.
Facts
OSHA Compliance Officer (CO) Tom Crandall testified that on October 21, 1994, he was assigned
to inspect Globe’s Appleton work site (Tr. 45). Globe’s work site was located on a public road, which was

closed to all but dump truck traffic because of the construction in progress (Tr. 47, 266). Barricades
blocked the street, stating “Road Closed, Local Traffic Only.” (Tr. 47, 470). About five private homes

were located on the street (Tr. 47, 470). Kevin Van Straten, Globe’s foreman, testified that the residents
did not enter the area during the day while work was going on, by “mutual understanding” (Tr. 470).
Crandall admits that, upon his arrival on Globe’s work site, he yelled at Globe employees as he
exited his vehicle; ‘What the f is the matter with you guys? Are you trying to kill yourselves?” (Tr. 5 1,
153, 159). Van Straten testified that Crandall repeated such statements at least twice before asking who
was in charge, and presenting his business card a couple of minutes later (Tr. 160, 452-53). Van Straten
testified that Crandall continued to use profanity, and accused employees of lying in answer to his questions
(Tr. 454-55). Crandall remained on the site for approximately 15 minutes without asking for Van Straten’s
consent (Tr. 454). Later that day, Crandall returned to the work site with another compliance officer,
Gordon Krohn, because he had doubts about Van Straten and his crew (Tr. 70-71). There is no question
that the Globe crew knew who Crandall was when he arrived on the site in the afternoon.

The then Fields Doctrine
The Commission has consistently held that an employer cannot claim a reasonable expectation of
privacy, or evoke the protections of the Fourth Amendment, where the worksite is observed from a public
thoroughfare, open to public view. concrete constr. co., 15 BNA OSHC 1614, 1991-93 CCH OSHJ)
729,681 (No. 89-2019, 1992). In Tri-State Steel construction Inc., 15 BNA OSHC 1904, 1991-93 CCH
OSHD 729,852 (Nos. 89-2611, 89-2705, 1992), the Commission found that the “open fields” doctrine is
generally applicable to roadway construction activities conducted out of doors, as there is no societal
interest in protecting the privacy of such activities. The Commission’s holding in Tri-State Steel was

                                                  2

unaffkcted by the employer’s erection of traffic control barricades to keep the public out of its work area.

The erection of barricades, intended to keep motorists out of the work area, did not create a reasonable
expectation of privacy. Id. at 1910, fin.15-16.
The undersiped finds that, under Commission precedent, Globe had no legitimate expect&On of
privacy in its worksite, which was located on a public road, and failed to create a privacy right by erecting
traffic barricades. Because Globe’s work site is not subject to Fourth Amendment protections, neither its
consent, nor a warrant is required to conduct an OSHA inspection of that site.
Selective Prosemtion
Globe maintains that CO Crandall conducted the October 21, 1994 inspection with the intent to
harass Globe. Globe, however, introduced no evidence whatsoever which would support its contention that
the October 1994 OSHA inspection was based on impermissible criteria. Globe introduced evidence of
Crandall’s later conduct to show personal bias; i.e., in April, 1994 Crandall was observed using binoculars
to watch the Globe crew at work (Tr. 465-68). Nothing in the record, however, indicates that Crandall had
any predisposition against Globe in October, 1994.
Moreover, the conscious exercise of some selectivity in enforcement is not in itself a constitutional
violation. Relief is available only if decision to prosecute is shown to have been deliberately based on an
unjustifiable standard such as race or religion or other arbitrary classification. Cuyahoga Valley Ry. K

United Traqportation Union, 474 U.S. 3, 106 S.Ct. 286 (1985). In the absence of any allegation that
OSHA chose Globe for inspection based on a proscribed classification, Globe fails to state a claim for
which relief may be granted.
Sections 8(a) and 8fel
Globe maintains that CO Crandall fkiled to present proper credentials, thus denying Globe the right
to accompany him on his inspection. Globe further maintains that the inspection was not conducted in a
“reasonable manner,” in that the CO behaved inappropriately during the inspection.’

        1 Section S(a) provides:
        In order to carry out the purposes of this Act, the Secretary, upon presenting appropriate credentials to the
        owner, operator, or agent in charge, is authorized--
            (1) to enter without delay and at reasonabletime any factory, plant, establishment, construction site or other
        area, workplace or environment where work is performed. . . and
            (2) to inspect and to investigate during regular working hours and at other reasonable times, within reasonable
        limits and in a reasonable manner any such place of employment and all pertinent conditions, structures,
        machines, apparatus, devices, equipment, and materials therein, and to question privately any such employer,
        owner, operator, agent or employee.
            Section 8(e) requires:
        Subject to regulations issued by the Secretary, a representative of the employer. . . shall be given an opportunity

                                                              3

The Commission has held that any rights granted by section S(a), requiring credentials, should be
read as coinciding with those of the Fourth Amendment. See, e.g. Gem Indusfrial, Inc., 17 BNA OSHC
1185,1995 CCH OSHD 730,762 (No. 93-1122, 1995); Hmilton Fixture, 16 BNA OSHC 1073, 1991-93
CCH OSHD 730,034 (No. 88-1720, 1993). In addition, Globe concedes that under Commission precedent
there can be no remedy for the Secretary’s failure to comply with other provisions of $8(a) or $8(e)

[reasonable time/place, walk arounds], unless the record reveals a failure by the Secretary to substantially
comply with those sections, and such noncompliance substantially prejudices the cited employer. Gem
IndxshzZ, Inc., szpa. The Commission has held that a general claim of prejudice is not enough; specific
evidence of the loss of material or mitigating information is required. Id.
As discussed above, the October 1994 OSHA inspection conformed to the requirements of the
Fourth Amendment. The evidence establishes that not only were adequate credentials presented to Globe’s
foreman within a reasonable time of the CO’s arrival on site, but that Globe’s foreman was present from
the CO’s arrival until such credentials were presented. Although the record reflects that CO Crandall
behaved in an unprofessional and belligerent manner, Globe ftiled to establish that his behavior resulted in
any prejudice in its ability to present its defense. Globe’s contention that it was prejudiced by Crandall’s

failure to conduct a more thorough investigation, or his refusal to credit the explanantions of Globe’s
employees is without merit. Globe had ample opportunity to examine and record conditions at the work
site and to question its own employees during and after the OSHA inspection. Moreover, Globe was
afforded a full opportunity to correct any of Crandall’s misapprehensions at its informal settlement
conference in December 1994 (Exh R-l). Finally, as is shown by the record, Globe was able to mount a
complete defense at the April 1996 hearing.
In the absence of a showing of prejudice, there is no basis for the suppression of evidence obtained
during the inspection.
Alleged Violation of ~1926.600~a~~6~

    Serious citation 1, item 1 alleges:

29 CFR 1926.600(a)(6): Equipment operating in vicinity of power lines did not comply with requirements
of29 CFR 1926SSO(a)(l5). 29 CFR 1926.55O(a)(l5) requires all equipment not to be operated within 10
ft. of electrical distribution or transmission lines rate 50 kv or below and/or insulating barriers not part of,
or an attachment to the equipment shall be erected to prevent physical contact with the lines:

       to accompany the Secretary or this authorizedrepresentative during the physical inspection of any workplace
       under subsection (a) for the purpose of aiding such inspection.



                                                         4

(a) Link belt, LS-3400, Series: CII, Crawler Excavator in operation at the extreme west end of the
excavation. Boom with bucket was directly below overhead energized electric power line which
crossed Meade St. fkom primary source to residence, when boom was raised it came within an
estimated 5’ distance of contact with the line. Power pole had been removed and line was supported
by a tree branch. .

    The cited standard provides:

    All equipment covered by this [subpart O-Motor Vehicles, Mechanized equipment, and Marine
    Operations] shall comply with the requirements of §1926.55O(a)(15) when working or being moved
    in the vicinity of power lines or energized transmitters.

    Section 1926.55O(a)(l5) requires that:

    Except where electrical distribution and transmission lines have been deenergized and visibly
    grounded at point of work or where insulating barriers, not a part of or an attachment to the
    equipment or machinery, have been erected to prevent physical contact with the lines, equipment
    or machines shall be operated proximate to power lines only in accordance with the following:

    (i) For lines rated 50 kV, or below, minimum clearance between the lines and any part of the crane
    or load shall be 10 feet. . ..

Facts
CO Crandall testified, without contradiction, that during his afternoon inspection he observed
Globe’s backhoe operating below an energized low hanging overhead power line that came across Meade
Street and into the residence at 4543 Meade Street (Tr. 110-13, 124; Exh. C-18). Crandall testified that
as the boom of the backhoe was elevated to remove the spoil to the spoil pile, and to return to the trench,
it was within five to seven feet of the power line (Tr. 114, 125-27). Crandall testified that contact between
the boom and the energized line could result in electrocution ofthe operator and/or employees working near
the backhoe when it became energized (Tr. 117).
Globe presented no evidence on this item, though the backhoe operator, Bob Hansen, testified at
the hearing (Tr. 501-25). In its briefj Globe argues that the overhead wire pictured in Complainant’s exhibit
C-18 is not a power line, but a telephone line not covered by the regulation.
Discussion
Section 1926.55O(a)(l5)(vi) states that: -
Any overhead wire shall be considered to be an energized line unless and until the person owning
such line or the electric utility authorized indicates that it’s not an energized line and that it has been
visibly grounded.
The Secretary’sprimafacc~e burden of showing the applicability of the cited standard is met by the
presumption contained in subsection (a)( 15)(vi); the burden of proving that the conditions cited here are
otherwise exempted from coverage lies with Globe, the party claiming the benefit of the exception. Falcon
Steel Co., 16 BNA OSHC 1179, 1991-93 CCH OSHD 730,059 (No. 89-2883, 89-3444, 1993). No
evidence in the record supports Globe’s contention that the pictured wire is a telephone wire.
The uncontested testimony of the compliance officer establishes that the standard was violated and .
that at least one employee, the backhoe operator, was exposed to the hazard. Aprimafacie case of actual
or constructive knowledge is made out where, as here, an established violation is in plain view. Williams
Enterprises, Inc., 10 BNA OSHC 1260, 1981 CCH OSHD 725,83O(No. 16184, 1981).
The violation has been proven.
Penalty
A penalty of $2,000.00 was proposed for this violation. Globe is a medium sized employer, with
at least 50 employees (Tr. 375). Globe has a history of prior OSHA violations dating from 1989 through
1993 (Exh. C-1 9 through C-35). Although Globe has a written work rule prohibiting the operation of
overhead equipment within ten feet of an overhead line, no evidence that the rule was communicated or
enforced was introduced at the hearing (Exh. R-6, Rule H-2). One employee was shown to have been
exposed to the cited hazard. Crandall testified that although the potential for harm posed by the boom’s
proximity to the energized wire was high, the probability of an accident occurring was lesser (Tr. 12 1). The
proposed penalty is well below the statutory maximum allowed for “serious” violations of the Act, and is
deemed appropriate. $2,000.00 will be assessed.
Alleged Violations of 81926.6SUkM21 and 652hMl\

Facts
CO Crandall testified that when he arrived on Globe’s work site on the morning of October 21,
1994 he noted a man standing on the south side of an excavation holding onto a ladder. Crandall testified
that as he approached the excavation he saw two people come up the ladder, remove the ladder from the
trench and leave the site (Tr. 48-49, 181). Crandall stated that during his approach, he could not see the
men because the trench was over their heads (Tr. 49). Crandall stated that he was approximately 25 feet
from the excavation when he saw the men exit the trench (Tr. 49). Crandall stated that the man who had

been holding the ladder identified himself as Kevin Van Straten (Tr. 50, 152). All of Globe’s employees
denied being in the trench (Tr. 68).
Kevin Van Straten testified that when Crandall arrived on the site, he was standing by his pick-up,
approximately 20 yards from the trench; Steve Jackson, the top man, was holding a ladder on the south side
of the trench; the pipe layer, Dean Van Straten, was standing on the ladder chest deep in the trench (Tr.
445-47; See also, Testimony of Dean Van Straten, Tr. 53 1, 536-38). Kevin Van Straten stated that when

the employees saw Crandall drive up, Dean Van Straten climbed out of the trench and “gave the ladder a
fling” (Tr. 451). Bob Hansen testified that when Crandall arrived, Steve Jackson was not in the trench;
Dean Van Straten was standing partway down the ladder, giving him signals (Tr. 5 12-13).
Crandall testified that the trench ran east to west from the centerline of Meade Street towards the
residence at 4543 Meade (Tr. 52). Inside that trench Crandall noted a capped six-inch PVC pipe with a
locating bar wedged in the dirt holding the cap in place (Tr. 52-53; Exh. C-2). A second, perpendicular
trench intercepted the east-west trench from the south (Exh C-l). Globe’s ladder had been placed against
the west wall of the trench from the south at its intersection with the east-west trench (Tr. 47 l-72, 546-47;
Exh. C-3). Backfill added at the east end of the trench created a slope; footprints indicate the slope was
used for access (Tr. 53, 57,63; Exh. C-l, C-4). Kevin Van Straten testified that a trench box was used in
the area during the installation of the PVC pipe (Tr. 497). Dean Van Straten stated that he was in the
trench box after the backfill had been placed in the trench, and had made the footprints at that time (Tr.
532-3 5).

    Crandall stated that the walls were vertical, and no protective system was in place (Tr. 52, 58; Exh.

C-2). Crandall testified. that he measured the trench in the area where he had seen the ladder; from the
surface to the approximately three foot wide bench where the PVC pipe lay (Tr. 60-61). He stated that the
bench was approximately eight feet down (Tr. 61, 88-89; Exh. C-10, R-2). That testimony was

contradicted by Kevin Van Straten, who stated that the PVC pipe on the bench was approximately five feet
deep (Tr. 461.62,478). Crandall measured the depth to the bottom ofthe trench at 1I’-6” (Tr. 251; Exh.
C-4, C-5, C-6). The competent person on site, Kevin Van Straten (Tr. 42X24), told Crandall, that the

trench was excavated in type B soil (Tr. 58).
When he returned to the work site later that afternoon, Crandall again saw an employee standing
in the trench (Tr. 78). As he and CO Krohn approached the site, both heard the backhoe operator call out;
“Lay down so he can’t see you” (Tr. 79; 267). Crandall then saw and photographed the employee,
identified as Dean Van Straten, scramble from a water pipe up the side of the trench with the help of Steve
Jackson (Tr. 80; Exh. C-8). A ladder was in the east end of the trench; buckets of lubricant lay by the end

                                                  7

of the pipe Crandall had observed in the morning; again footprints were noted in the backfill (Tr. 93-94;
Exh. C-16).
Dean Van Straten admitted during the inspection, and at trial, that when Crandall returned to the
work site that afternoon he was standing on top of the water main signaling the backhoe operator (Tr. 458,
543). CO Krohn estimated the depth of the water main at seven feet (Tr. 3 18). Kevin Van Straten and
Hanson both testified that the water main was between five and six feet deep in the trench (Tr. 459, 523).
Kevin Van Straten testified that he was again standing by his pick-up, but that he did not know Dean
Van Straten was back in the trench (Tr. 457058,483). Crandall, however, photographed the foreman on
the north side of the trench within a few seconds of his arrival on the site (Tr. 214-19; Exh. C-9).
The trench was dug out Wher towards the west when. Crandall returned the second time; the type
B soil became type C at the point the trench intercepted the water main (Tr. 87; Exh. C-9). The trench was
vertical with the exception of some sloping on the west end, and where the previously disturbed soil around
the main had collapsed (Tr. 87-88; Exh. C-9). The trench measured lo’-6” deep at the water main and
approximately 14 feet across where there was previously disturbed soil. The remainder of the trench was
approximately 8 feet across (Tr. 91,273.75,460; Exh. C-14).
Globe has a written safety program that contains the bare requirement that employees are to “[elnter
trenches over 5’ deep only when they are sloped to a safe angle of repose or if a trench shoring, sheeting
or shield system is in use.” (Tr. 396; Exh- R-6, p. 15). The rule provides no specific guidance as to whether
standing on ladders or pipes in the trench complies with the rule. Daniel Olson, Globe’s safety director
since 1990, admitted that depending on how deep an employee was in a trench, and other trench conditions,
an employee standing on a ladder or pipe in a trench could be exposed to a hazard (Tr. 408-l 1).
All employees are given a retiesher course on the trenching standards annually (Tr. 378-79,397-98).
The last training before the October 21, 1994 inspection was in March 1993 (Tr. 394; Exh. R-4, p.1).
Kevin and Dean Van Straten and Bob Hansen were all present at the March training session (Tr. 395).
Olson stated that he performed spot inspections of Globe work sites two to three times a week; any given
area was visited monthly (Tr. 185-86). Olson stated that he never found employees working in an
excavation more than five feet deep without sloping, a trench box, or other cave-in protection (Tr. 386).
Globe has no written disciplinary system, and Olson knew of no instance where any employee was
disciplined for working in an unsafe trench (Tr. 399).
Dean Van Straten testified that he was aware of Globe’s trenching work rule prior to October 21,
1994, but did not consider himself in violation of the rule on that date (Tr. 527, 544-45). Dean Van Straten
was not disciplined for being in the trench during the OSHA inspection (Tr. 496). i
Citation 2, Item 1,81926.65l~k)~2~
Willful Citation 2, item 1 alleges:

29 CFR 1926.65 l(k)(2): where the competent person found evidence of a situation that could result in a
possible cave-in, indications of failure of protective systems, hazardous atmospheres, or other hazardous
conditions, exposed employees were not removed fi-omthe hazardous area until the necessary precautions
had been taken to ensure their safety:

The competent person (foreman-in-charge) allowed employees to enter into an excavation which was not
protected by sloping of the ground, shoring or use of a trench shield. The employees were exposed to the
potential hazard of a cave-in.

    (a) Two employees were observed exiting from an unprotected excavation eleven feet six inches
    (1 Y-6”) deep at lo:42 AMI, 10/21/94.

    (b) One employee was observed in the bottom ofthe same unprotected excavation at a depth of ten
    feet six inches (lo’-6”). This incident occurred at 1:20 PM, 10/2 l/94.

    The cited standard provides:

    (k) Inspections. (1) Daily inspections of excavations, the adjacent areas, and protective systems shall
    be made by a competent person for evidence of a situation that could result in possible cave-ins,
    indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions.
    An inspection shall be conducted by the competent person prior to the start of work and as needed
    throughout the shift. Inspections shall also be made after every rainstorm or other hazard increasing
    occurrence. These inspections are only required when employee exposure can be reasonably
    anticipated.
      (2) Where the competent person finds evidence of a situation that could result in possible cave-in,
    indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions,
    exposed employees shall be removed from the hazardous area until the necessary precautions have
    been taken to ensure their safety.

Disctrssion
This judge finds that $1926.65 l(k)(2) is not applicable to the circumstances cited here.
The intent of the cited standard is to require interim inspections to address changing conditions in
a trench which may require the removal of employees working therein. see, Preamble to Final Rule, 54 FR
45894, at 45926 (October 3 1, 1989); See ah, secretary of L&or v. Americm Sterilizer CO., 15 BNA

OSHC 1476, 1991-93 CCH OSHD 729,575 (NO. 86-1179) [preamble is the most authoritative statement

                                                    9

of the Secretary’sintent.] In this case, the Secretary does not allege that inspections were not made, or that
previously undetected hazardous conditions were found or developed during the course of work in the
excavation. Instead the employer is cited for failing to exert adequate supervisory authority in preventing
employees from entering a trench known to require a protective system under §1926.652(a)( l), which is
also cited as item 2 below. The exposure of Globe’s employees, and the knowledge of Globe’s supervisory
personnel are elements of the substantive violation of 8 1926.652(a)( 1), rather than a separate violation of
5 1926.65 l(k)(2).
For the same reason, the cited violation is duplicative of item 2, below, in that both cited violations
require the same abatement conduct. J.A.Jones Consb~ctio~ Co., 16 BNA OSHC 1497, 1991-93 CCH
OSHD 129,964 (No. 87-2059, 1993).

    Item 1 is vacated.

Citation 2, item 2. 61926.652h)U)

    Willtil citation 2, item 2 alleges:

29 CFR 1926.652(a)( 1): Each employee in an excavation was not protected from cave-in by an adequate
protective system designed in accordance with 29 CFR 1926.652(c). The employer had not complied with
the provisioti of 29 CFR 1926.652(b)(l)(i) in that the excavation was sloped at an angle steeper than one
and one half horizontal to one vertical (34 degrees measured from the horizontal): ’

    (a) Two employees were observed exiting from an excavation eleven feet six inches (1 l’r6”) deep.
    The excavation was not shored, sloped or have a trench box installed for employee protection
                                                                                                 ,
    against cave-in. This incident occurred at lo:42 AM, 10/21/94.

    (b) One employee was observed in the bottom of the same excavation at a depth of ten feet six
    inches (lo’-6”) deep. The excavation was not shored, sloped or have a trench box installed for
    employee protection against cave-in. This incident occurred at 1:20 PM, 10/21/94.

    The cited standard provides:

    (a) Protection of empZoyeesin excavations. (1) Each employee in an excavation shall be protected
    from cave-ins by an adequate protective system designed in accordance with paragraph (b) or (c)
    of this section except when:
    0i       Excavations are made entirely in stable rock; or
    0ii      Excavations are less than 5 feet (1.52m) in depth and examination of the ground by a
    competent person provides no indication of a potential cave-in.

Dismssion
Globe’s witnesses consistently and credibly testified that no employees worked at the bottom of the
cited trench without cave-in protection. It is admitted, however, that upon CO Crandall’s arrival at Globe’s

                                                   10

work site, one Globe employee, DeanVan Straten, was standing on a ladder on a bench in an 11’ 6” trench.
CO Crandall’s actual measurement of the bench depth, at approximately eight feet, is credited over the
estimates of Globe’s witnesses. The foreman, Kevin Van Straten, admitted he was in the vicinity and
witnessed Dean Van Straten in the trench, but took no steps to prevent him from signaling the backhoe
operator f?om that position. It is also admitted that when Crandall tived on the site in the afternoon, Dean
Van Straten was standing on a water pipe between five and seven feet deep in the trench, which was 10’
6” at that point.
Globe maintains that the cited standard only prohibits employees in the bottom of the trench, that
the Secretary failed to prove employer knowledge of the violation, and that any violations were the result
of unpreventable employee misconduct.
Interpretation. Globe maintains that the standard does not prohibit the cited conduct, relying on
Madison Underground fix., 1991-93 CCH OSHD 729,614 (No. 90-3249, 1992), in which this judge found
that an employee on a ladder would not necessarily be dislodged by collapsing soil. However, at the hearing
in this matter CO Crandall testified convincingly that a potential for injury exists any time the employee is
in the trench; an employee standing on a ladder, for instance, could be thrown up against the opposite wall
or knocked from his perch in the event of a cave-in (Tr. 97). Based on Crandall’s testimony, this judge

cannot say that the Secretary’s application of this standard here is unreasonable. It is well settled that the
interpretation of a standard by the promulgating agency is controlling unless clearly erroneous. Martin v.
OSHRC (cF&r Steel Corp.), 111 S.Ct. 1171, 1179 (199 1). The Madison Underground decision was
unreviewed and is without precedential value; moreover, upon reconsideration, I find that the probability
of accident or injury is not relevant to the standard’s scope, but is properly a factor only in the

determination of an appropriate penalty.
I find, therefore, that Dean Van Straten’s presence on a ladder in the trench was in violation of the
cited standard. Likewise, Dean Van Straten was in violation of the cited standard as he stood on the water
main in the trench.*
Knowledge. The record establishes that Globe’s foreman had actual knowledge of Dean Van
Straten’s presence on the ladder in the trench at the time of CO Crandall’s morning and afternoon

          * Globe contends that the trench was properly sloped ifmeasured from the depth at which the exposure

occurred, i.e., the level of the water main, to the surface (Tr. 655). Globe’s method of determining the slope is rejected.
In order to determine a trench’s compliance with the standard, it is measured from the toe of the trench to the surface at
the lateral location at which the exposure occurred (Tr. 283). The cited trench would have had to measure
approximately 25 feet across the top to comply (Tr. 282).

                                                            11

inspections. Taking into account his proximity to the trench, his knowledge that Dean Van Straten had
been signaling the backhoe operator from inside the trench, and his demeanor at the hearing, the
undersigned finds Kevin Van Straten’s testimony that he was unaware of Dean Van Straten’s presence on

the water main implausible, and affords it no weight.
Employee Misconduct. In order to prove an unpreventable employee misconduct defense, the
employer must show that it had: established work rules designed to prevent the violation; adequately
communicated those work rules to its employees (including supervisors); taken reasonable steps to discover
violations of those work rules; and effectively enforced those work rules when they were violated. New
York State Electric & Gas Corporation, 17 BNA OSHC 1129, 1995 CCH OSHD 7 (91-2897, 1995).
Here, the evidence fails to establish that Globe’s work rules either were sufficiently designed to
prevent the violation, or were effectively enforced.
Neither Globe’s written work rule, nor its training addresses the problem of being in a trench either
on a ladder or pipe, though Globe’s safety director admitted that an employee engaging in either conduct
could be in jeopardy. As a result Dean Van Straten did not feel he violated company rules by doing either.
Kevin Van Straten did not feel that Dean’s presence in the trench merited disciplinary action. No
reprimand or other action was taken as a result of the October 21 inspection- In fact, Globe failed to
introduce a single instance of disciplinary action taken to enfOrce its trenching rules, in spite of a history of
prior OSHA violations of the trenching standards, seven citations dating from 1989 through 1993 (Exh. C-
I9 through C-35).
Globe failed to establish the defense of employee misconduct. A violation of 5 1926.652(a)( 1) is
proven.
WillfirI
The cited violation was classified as “willfX” Despite the absence of a work rule specifically
prohibiting working on a ladder or pipe in a trench, the record shows that Globe employees knew their
conduct violated OSHA regulations. Dean Van Straten and Steve Jackson pulled the ladder out of the
trench and ran from the trench area when CO Crandall pulled up on the morning of the inspection.3 When
Crandall returned in the afternoon, Hanson told Dean Van Straten to lie down in the trench so that Crandall
would not see him. I find that Kevin Van Straten knew of both incidents, and either condoned or ignored
them.

         3 Dean Van Straten’s testimony,that he vacatedthe trench, with the ladder, in fear that CO Crandall would

drive into the trench is found implausible and is discounted.

                                                         12

Globe’s contention that, based on this judge’s decision iniMz&so~ Underground, it believed in good
faith that it was not violating the cited standard, allowing employees to enter a trench more than five feet
deep, but above the five foot level, is rejected. First, there is no evidence that Globe actually knew of, or
relied on&&on Undergrgrmd in formulating its safety program. Second, Crandall’s first appearance on
site should have cleared up any misconceptions Globe personnel had about OSHA’s interpretation of the
standard. Lastly, the behavior of Globe’s employees clearly demonstrates that they knew they were again
in violation of the standard when CO Crandall returned to the site.
The citation was properly classified as “willful”
Pena&

      A penalty of $56,000.00 was proposed.      Crandall testified that collapse of the trench walls could

result in death by asphyxiation or serious crushing injuries to the lower extremities (Tr. 99). During the
morning inspection, tension cracks were visible on the north side of the excavation
. (Tr. 63-64; Exh. C-6).
Crandall testified that tension cracks develop when soil dries out. and begins to lose its cohesiveness.
Cracking is indicative of impending failure of a trench wall (Tr. 63).
However, the gravity of the violation was overstated, in that the likelihood of an accident occurring
was remote. In neither instance was Dean Van Straten shown to have been in the bottom of the trench.
The ladder was grounded against the sloped backfill at the east end of the trench and was secured from
above. The soil above the water main was sloped and was unlikely to slough into the trench from above
or to knock the employee into the trench. The possibility of the employee being covered by falling soil was
remote.
Taking into account the gravity of the violation, as well as the employer’s size and history of prior
violations, I find that the proposed penalty is excessive. A penalty of $20,000.00 will be assessed.

                                                   13

ORDER

1 Serious citation 1, item 1, alleging violation of $1926,600(a)(6) is AFFIRMED, and a penalty of
$2,000.00 is ASSESSED.

  1. Willfbl citation 2, item 1, alleging violation of § 1926.65 l(k)(2) is VACATED.

3 Wilhl citation 2, item 2, alleging violation of §1926.652(aO(l) is AFFIRMED, and a penalty of
$~O,OOO.OOis ASSESSED.

Dated: September 20, 1996

                                                 14

Get today's answer for your situation

You just read what one judge decided for one employer in 1996, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.