E & R Erectors, Inc.
Steel-erection fall-protection and crane items affirmed against E & R, related companies dismissed, $3,000
Apply this to your situation
This order from 1996 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
OSHA inspected the steel erection at the ASTM International Headquarters
construction site in West Conshohocken, Pennsylvania, and cited E & R Erectors,
Inc. E & R claimed it was not on the site that day, so the Secretary amended the
complaint to add two related companies, Samuel Grossi and Sons, Inc. and
Bensalem Steel Erectors, Inc. The central question was which company employed
the ironworkers doing the cited work. Judge John H. Frye, III found the workers
were E & R's employees, based on identifications by the general contractor's
superintendent and by the ironworkers themselves, and dismissed the complaints
against Grossi and Bensalem, who were found not to be erecting steel at the site.
On the merits, the judge affirmed both remaining items against E & R (a third
item had been withdrawn before trial). The serious item was a fall-protection
violation under § 1926.105(a) for failing to provide safety nets or equivalent
protection at heights where it was required; the judge rejected the argument that
the newer Subpart R steel-erection rules displaced § 1926.105(a) and assessed the
proposed $3,000 penalty. The other-than-serious item under § 1926.550(a)(9)
concerned crane operation and carried no penalty. Total penalty: $3,000 against
E & R Erectors, Inc.
Decision snapshot
- Cited standard(s): 29 C.F.R. § 1926.105(a) (serious), § 1926.550(a)(9) (other than serious)
- Outcome: Both items affirmed against E & R Erectors ($3,000 serious, no-penalty other-than-serious); complaints against Samuel Grossi and Sons and Bensalem Steel Erectors dismissed
- Key point: OSHA can pin a citation on the company whose workers were identified on site, and § 1926.105(a) fall protection still applied to steel erection at this site.
Full text (OSHRC public release)
```text
United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington, DC 20036-34 19
Phone: (202) 606-5 100
SECRETARY OF LABOR Fax: (202) 606-5050
Complainant.
A /
v. OSHRC DOCKET
NO. 95-0190
E & R ERECTORS, INC.
Respondent.
NOTICE OF DOCKETING
OF ADMINISTRATIVE LAW JUDGE’S DECISION
The Administrative Law Judge’s Report in the above referenced case was
docketed with the Commission on February 22, 1996. The decision of the Judge
will become a final order of the Commission on March 25, 1996 unless a
Commission member directs review of the decision on or before that date. ANY
PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
Any such petition should be received by the Executive Secretary on or before
March 13, 1996 in order to ermit sufficient time for its review. See
Commissron Rule 91, 29 C.if .R. 2200.91. .
All further 1. zadings or communications .regarding this case shall be
addressed to:
Executive Secretary
Occupational Safetyand Health
Review Commission
1120 20th St. N.W., Suite 980
Washington, D.C. 20036-3419
Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DOgL
Room S4004
200 Constitution Avenue, N.W.
Washington, D.C. 20210
If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
having questions about review rights may contact the Commission’s Executive
Secretary or call (202) 606-5400.
Date:’ February 22, 1996
DOCKET NO. 95-0190
NOTICE IS GIVEN TO THE FOLLOWING:
Deborah Pierce-Shields
Re ional Solicitor
Of&e of the Solicitor, U.S. DOL
14480 Gatewa Building
3535 Market Htreet
Philadelphia, PA 19 104
John Phili Diefenderfer, Es .
Attorney Por E&R Erectors, 4nc.
340 Harrisbur School Road
Quakertown %ucks Cou, PA 18951
John H. Frye, III
Administrative Law Jud e
Occupational Safety an cf Health
Review Commission
One Lafayette Centre
1120 20th St. N.W., Suite 990
Washington, DC 20036 3419
00123254369:03
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
ROBERT REICH, SECRETARY OF LABOR,
UNITED STATES DEPARTMENT OF LABOR
Complainant,
I
v. Docket Nr. 95-0190
E & R ERECTORS, INC./
SAMUEL GROSSI AND SONS, INC., and
BENSALEM STEEL ERECTORS, INC.,
Respondents.
Appearances
Thomas S. Williamson, Jr., Esq. John Philip Dief-enderfer, Esq.
Solicitor of Labor Quakertown, PA
For Respondent
Deborah Pierce-Shields, Esq.
Regional Solicitor
Gayle M. Green, Esq.
Attorney
U.S. Department of Labor
Philadelphia, PA
For Complainant
BEFORE: JOHN H FRYE, III, Judge, OSHRC
DECISION AND ORDER
INTRODUCTION
This case arose out of the inspection of the construction of
the ASTM International Headquarters Building in West Con&&o&en,
PA, conducted by Compliance Officer George Boyd on December 1,
1994 l As a result of the inspection, OSHA issued two citations to
E & R Erectors, Inc. A notice of contest was filed, and the
Secretary filed a complaint against E & R. After E & R claimed
not to have been present on the ASTM site on December 1, the
Secretary amended the complaint to join Bensalem Steel Erectors,
Inc., and Samuel Grossi and Sons, Inc., both of which are related
to E & R. Trial took place on September 29, 1995, in
Philadelphia, PA. Prior to trial, the Secretary withdrew Citation
No. 1, Item No. 2.
IDENTITY OF THE COMPANY
PERFORMING THE WORK WHICH WAS CITED
E & R relies on the testimony of Eugene Grossi, its vice-
president, as well as president and chief operating officer of
Samuel Grossi and Sons, Inc., to establish that it was not at the
ASTM site (Tr. 89, 94). Mr. Grossi testified that E & R does not
work in Pennsylvania because it believes that it is being harassed
by OSHA's Allentown office. (Tr. 94-95,) He produced payroll
2
records for E & R for the weeks ending November 29, December 6,
and December 13, 1994, for jobs in New Jersey. (Tr. 94, RX 2.)
Samuel Grossi and Sons had been awarded a contract to furnish
and erect the steel, joist, and metal deck for the ASTM
International Headquarters by the general contractor, John McQuade
Construction. (Tr. 111-12.) Mr. Grossi produced a subcontract
between Samuel Grossi and Sons, and Bensalem Steel Erectors which
covered the erection of structural steel, studs, and metal deck.
(Tr. 92-93, RX 1.) Mr- Grossi maintains that the contractor on
the site - presumably the one to which the citations should have
been directed - was Bensalem. Bensalem is run by Mr. Grossi's
niece and son, its principal officers. (Tr. 93,)
The Secretary points out that he cited E & R Erectors, Inc.
because:
1) the superintendent of the general contractor
on site, John McQuade Construction,
identified the ironworkers as employees of E
& R Erectors, Inc. (Tr. p. 15-16);
2) the ironworkers identified themselves as
employees of E & R Erectors, Inc. (Tr. p.
18) ;
3) the ironworkers' foreman, Mr. Brown, told
him that he worked for E & R Erectors, Inc.
(Tr. p. 1849, 72);
4) Walter Cantley introduced himself at the
worksite as the superintendent of E & R
Erectors, Inc. (Tr- p. 48, 72);
3
5) Mr. Cantley represented E & R Erectors,
Inc., at the closing conference at the
worksite (Tr. p- 48) -
Indeed, subsequent to the issuance of the citations, Mr.
Cantley attended the Informal Conference and discussed the
citations at the OSHA area office. (Tr. p. 111). Samuel Grossi,
who testified for respondent, conceded that Mr. Cantley was the
supervisor for E & R Erectors, Inc., and that he does not work for
either Bensalem Steel Erectors, Inc. or Samuel Grossi and Sons,
Inc. (Tr. p- 106-107).
E & R objects that Mr. Boyd's testimony on this point is
hearsay. However, Mr. Boyd testified as to what he had been told
by E & R employees.' It is well-settled that such representations
are admissions under Federal Rule of Evidence 801(d)(2) (D) and are
not hearsay.
The -evidence thus clearly shows that, even if the subcontract
for steel erection at the ASTM headquarters was initially awarded
by Samuel Grossi and Sons, Inc. to Bensalem Steel Erectors, E & R
Erectors, Inc, was present at the site at the time of Mr. Boyd's
inspection, performing the work which gave rise to the citations.
1
In one instance, Mr. Boyd related the representation of the general
contractor's site superintendent. While this individual is not an E & R
employee, there is no reason to question the reliability of his representation.
He clearly was in a position to know the identity of the companies working on the
site and would have no obvious reason to misrepresent the facts. I find that
this statement meets the requirements of Federal Rule of Evidence 803(l).
4
Conversely, other than the subcontract, there is no evidence that
Bensalem was engaged in the steel erection in question, and the
uncontradicted evidence indicates that Samuel Grossi and Sons does
not engage in that activity. Consequently, the complaints against
these companies must be dismissed.2
THE CITATIONS
To establish a violation of any standard, Complainant must
establish the applicability of the standard, non-compliance,
employee exposure or access, and employer knowledge of the
condition. Dun-Par Engineered Form ComDany, 12 BNA OSHC 1949 (No.
79-2553)' RevId and remanded on other aroux& ' 843 F-2d 1135 (8th
Cir. 1988)' decision on remand, OSHRC docket No. 79-2553 (April
12' 1989).
. .
Irtatlon No . 1, Item No- b
The standard at 29 C-F-R- § 1926.105(a) provides, in relevant
part, that:
Safety nets shall be provided when workplaces are more
than 25 feet above the ground or water surface, or
other surfaces where the use of ladders, scaffolds,
catch platforms, temporary floors, safety lines, or
safety belts is impractical.
2
The Secretary urges that I find that Bensalem and E & R are so closely related
as to constitute a single enterprise in which the employees of one may be treated
as the employees of the other. The Secretary's evidence on this point is weak.
Moreover, because the evidence clearly shows that E & R, the original Respondent,
was present at the site and conducted the activity which was cited, there is no
need to reach this issue.
5
Section 1926.105 (a> applies to the steel erection industry
and requires the use of one of the appropriate listed devices to
protect against exterior falls. Century Steel Erectors. Inc. v.
Secretar& 14 OSHC 1273 (D.C. Cir. 1989); Brock v. willson & Sons,
773 F.2d 1377, 12 OSHC 1499 (D.C. Cir. 1985). The Secretary
establishes a prima facie case upon showing that the employees
were exposed to a fall in excess of twenty-five feet and that none
of the protective measures was used. Century Steel Erectors, Inc.
v. Secretary, 14 OSHC 1273 (D.C. Cir. 1989). An employer may be
cited for a violation of Section 105(a) in situations where safety
belts and lines are the more practical forms of fall protection
than nets. Secretary v. Anderson Excavating, 16 BNA OSHC 1601
(1993); Potomac Iron Works, 16 BNA OSHC 1299) (1993); Williams
Erection, 15 BNA OSHC 1463 (1992).
At the worksite, ironworkers were installing 27 foot steel
columns, each weighing approximately 6,300 pounds, on the third
floor (Level B-l) of a three-story pre-cast concrete building that
had no walls. (Tr. p. 17-18, 23, 31). Inspector Boyd observed the
following-procedure for setting the columns:
1. The foreman marks the columns, which are lying on
the floor, to show the sequence in which they should be installed;
6
2. The workers, via radio, direct the crane operator
where to boom over and place the loadline so it is above a column;
3. The workers attach the column to the load line with
shackle and wire rope sling, and direct the crane operator to lift
the load, suspending it vertically by the load line;
4. Two workers then walk the column to where it is to
be bolted up, while one worker directs the crane operator by
radio;
5. The workers orient the base plate of the column
with four bolts in the appropriate imbed plate that is in the
concrete deck, and lower the column onto the four bolts, rotating
the column as necessary; and
6. The workers hand tighten nuts onto the bolts and
then use a power wrench to fully tighten them. (Tr. p. 19-23, 26)
When Inspector Boyd arrived at the worksite, he observed that
guard rails were missing on the southeast corner of the structure.
These had been removed because they had been built over the imbed
plates and would have interfered with the erection of two columns,
which were put in place at approximately . 10:00 a.m. on December 1,
- (Tr. p. 23-24, 102). Although they were working at the
edge of the *open-sided floor, the employees were not wearing fall
protection while erecting these two columns, nor was any form of
7
fall protection was available to them. (Tr. p. 25) They were
exposed to a fall hazard of approximately 33 feet on one corner
where the column was set and approximately 30 feet in the other
location where the column was set. (Tr. p. 25, 28-34, 126; GX 2,
GX 3). At one location, the employees would have been standing
within inches of the unguarded open-sided floor. (Tr. p. 27).
Death could result from a fall from these locations. (Tr. p. 28).
The foreman was working in the area where the columns were
installed. The lack of guardrails was obvious and could be seen
from anywhere on the third floor. (Tr. p. 35-X). Fall protection
could have been provided by using a safety belt or harness and a
life line attached to an available imbed plate. (Tr. p. 36-37).
E & R argues that fall protection requirements applicable to
steel erection are contained in Subpart R, not 5 1926.105(a),
which is a part of Subpart K3 It rests this argument on OSHWs
promulgation of a Final Rule, Safety Standards for Fall Protection
in the Construction Industry, 59 Fed. Reg. 40672, August 9, 1994.
That rule did incorporate the fall protection provisions of §
1926.105(a) in $$ 1926.753 of Subpart R pertaining to steel
erection. That change did not take effect until after the
3
E & R apparently also believes that it was cited under Subpart M, Fall
Protection. See its brief, p-6-7. This is not the case.
8
inspection and alleged violation in this case. See 59 Fed. Reg.
- Consequently, § 1926.lOS(a) is fully applicable.
E & R challenges Mr. Boyd's location of the two columns on
the southeast corner of the building. At the hearing, Mr. Grossi
marked GX 2, indicating his opinion that they were on the
northeast comer. (Tr. 96; GX 2.) Apparently concerned that his
position was not made clear at trial, Mr. Grossi submitted an
affidavit with E & R's brief to which is attached a landscape plan
for the ASTM Headquarters site. Mr. Grossi indicated that the
columns were on the southeast corner of the building depicted on
the landscape plan, in the same location where Mr. Boyd placed
them. Consequently, I do not consider Mr. Grossi's testimony on
this point to be reliable. I accept Mr. Boyd's testimony as
accurate.
E & R also challenges Mr. Boyd's conclusion that the vertical
distance from the location of these two columns to the ground was
approximately 33 and 30 feet, respectively. In order for 5
1926.105(a) to be applicable, this distance must be more than 25
feet. The Secretary introduced GX 3, which is an architect's
drawing of an exterior wall showing the elevations of level BI,
where the E & R employees were working, and P3, ground level. Mr.
Grossi indicated that this drawing furnished a way to estimate the
vertical distance "pretty well." (Tr. 100.) The drawing shows
that the overall vertical distance from Bl to P3 is 29 feet.
However, it also shows that earth has been filled up against the
side of the building, thus reducing the vertical distance to some
extent.
At trial, there was considerable discussion of whether the
columns in question were located over an area where soil had been
excavated next to the building to permit trucks to back down to a
loading dock, thus increasing the vertical distance, and, if not,
whether earth had been backfilled, thus reducing the vertical
distance. 1 find that it is not necessary to resolve this
dispute.
GX 3 provides sufficient information to conclude that the
vertical distance was at least 25.5 feet. Specifically, it shows
that the vertical distance between 81 and Pl is II feet, between
PI akd P2 is 9 feet, and between P2 and the bottom of an opening
in the panel enclosing level P3 is 5.5 feet, a total of 25.5
feet4 The drawing depicts the backfill at a level below the
bottom of the opening in the panel and sloping away from the
building. Section 1926.105 (a) is applicable.
4
Mr. Grossi calculated this distance to be 24 feet. (Tr. IOO-01.) However, it
is obvious that he overlooked the portion of the panel at the top of the opening.
This is 1.5 feet.
10
The Secretary introduced evidence that the use of safety
belts or a harness and life line would have been practical in this
situation. Mr. Boyd testified that the easiest way to provide
fall protection would have been to attach a life line for each
exposed employee to one of the numerous imbed plates on the third
level. Specifically, he testified that a shackle could have been
attached to the imbed plate, with a lifeline attached to the
shackle, and a rope grab and a lanyard attached to the life line.
A retractable life line could have been used. (Tr. p. 37) If
tied off in this fashion, the employee would have been free to
move around, take down and replace the guardrails, and position
and bolt up the CO~UTIIIIS.
(Tr. p. 37-39, 132) Mr. Grossi conceded
that, if tying off were required, Mr. Boyd's recommendation would
be an option, and probably would have been used. (Tr. p. 102)
In its brief, E & R argues that Mr. Boyd conceded that the
use of safety nets was not practical? It also argues that, I
under the peculiar circumstances of the erection of the columns,
life lines were also impractical in that they restrict the
movement of the employees and make it difficult for them to avoid
an out-of-control column.
‘
5
E & R uses the term "feasible," which statesa different requirement than
"practical/ the term which appears in § 1926.105(a). Centurv Steel, supra.
I have substituted the latter for the former where it appears in E & R's brief.
11
E & R misreads Mr. Boyd's testimony with regard to safety
nets. Mr. Boyd regarded nets as impractical because the employees
installing them would be subjected to a fall hazard, not because
they would be ineffective or overly difficult to install. (Tr. 39.
40.) As the Secretary points out, if in fact life lines are
impractical for the erection of the columns because they restrict
the movement of the employees, the simple answer is to use life
lines while installing the nets. Mr. Boyd obviously felt that
life lines could be used during the erection of the columns
themselves, thereby avoiding the necessity of nets and simplifying
the job. E & R has not refuted the Secretary's prima facie case
that a practical means of fall protection was available.
The Secretary has demonstrated that E & R was-in serious
violation of § 1926.105(a). He has proposed a penalty of $3,000,
and Mr. Boyd testified as to how this was computed. E & R has not
contested the amount. I find that $3,000 is appropriate and
assess it.
Citation No. 2
The standard at 29 C.F.R. §1926.55O(a)(9) provides, in
relevant part, that:
Accessible areas within the swing radius of the rear of the
rotating superstructure of the crane, either permanently or
temporarily mounted, shall be barricaded in such a manner as
12
to prevent an employee from being struck or crushed by the
crane.
On this jobsite, Respondent was operating a Hawthorne lattice
boom crane. (Tr. p. 45) Thus, the standard is applicable. The
swing area or counterweight was not flagged off or barricaded to
prevent employees from walking through the area. (Tr. p. 46) In
fact, one of the two operators of the crane was in the swing area.
(Tr. p. 46) The operator told Inspector Boyd that he was an
employee of E & R Erectors. (Tr. p. 77) In addition, the area was
subsequently flagged off, and Mr. Cantley, superintendent for E &
R Erectors, walked underneath the yellow flagging and proceeded
though the entire counterswing area. (Tr. p. 48) Thus, employee
exposure and employer knowledge is established. The violation was
obvious. (Tr. p. 47-48) The Secretary has established a prima
facie case for a violation of the cited standard. E & R has not
addressed this citation in its brief. Accordingly, it has
abandoned any defense to the substance of this charge?
This violation was appropriately cited as Other-than-Serious
in that there was no pinch point in which the employee could have
been crushed between a counterweight and a stationary object.
6
Mr. Grossi indicated that E & R does not employ any crane operators.(Tr.
105.) I find Mr. Boyd's testimony that one of the crane operators indicated that
he was employed by E & R to be more reliable- In its brief, E & R defends on the
ground that it was not at the site. This defense has been rejected.
13
(Tr. p. 47) Accordingly, the $00 penalty proposed is appropriate
and reasonable and is assessed.
CONCLUSIONS OF LAW
A. Respondent E & R Erectors, Inc., is an employer engaged in a
business affecting commerce within the meaning of section 3(5) of the
Occupational Safety and Health Act of 1970, as amended, 29 U.S.C.
§ 652(5) ("the Act").
B. Jurisdiction of this proceeding is conferred upon the
Occupational Safety and Health Review Commission by section 10(c) of the
Act, 29 U.S.C. § 659(c).
Citation 1, Item 1.
c. Respondent E & R Erectors, Inc., was in serious violation of
the standard set out at 29 CFR §§ 1926.105(a). A penalty of $3000 is
appropriate.
Citation 2, Item 1
D. Respondent was E & R Erectors, Inc., in other-than-serious
violation of the standard set out at 29 C.F.R. § 1926.550(a)(9). A
penalty of $00 is appropriate.
E. Respondents Samuel Grossi and Sons, Inc., and Bensalem Steel
Erectors, Inc., were not engaged in erecting steel at the ASTM
Headquarters site.
14
ORDER
A. Citation 1, Item 1, is affirmed as a serious violation of the
Act.
B. Citation 2, Item 1, is affirmed as an other-than-serious
violation of the Act.
C. A total civil penalty of $3,000 is assessed against E & R
Erectors, Inc. I
D. The complaints against Samuel Grossi and Sons, Inc., and
Bensalem Steel Erectors, Inc., are dismissed.
It is so ORDERED.
Dated: m22199s
Washington, D.C.
15
```
Get today's answer for your situation
You just read what one judge decided for one employer in 1996, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.