🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 93-0648 Decided April 4, 1994 Citations vacated Judge Paul L. Brady

Danella Construction Corporation of Florida, Inc.

Inspection and power-line-clearance items vacated

Apply this to your situation

This order from 1994 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1994
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Danella Construction was installing telephone lines in Lake Worth, Florida, and used a boom truck to place an eight-foot trench shield. OSHA alleged that the company failed to have competent-person inspections and operated the boom within 10 feet of energized overhead lines. The judge found that two competent persons inspected the site before work and that one remained onsite throughout the operation. OSHA took no measurements of the boom's distance from the lines and relied on a compliance officer's visual estimate from a distance. Two employees who were closer to the operation testified that the boom stayed outside the 10-foot zone. The judge found that OSHA did not prove either violation and vacated both items.

Decision snapshot

  • Cited standard(s): 29 C.F.R. §§ 1926.20(b)(2) and 1926.550(a)(15).
  • Outcome: Vacated. The competent-person-inspection and power-line-clearance items were vacated.
  • Key point: A visible overhead-line hazard does not by itself prove an inadequate inspection, and an unsupported distant estimate did not establish that the boom breached the required clearance.

Full text (OSHRC public release)

                             &j@NTED
                                 smE8 or AMIERUCA
    OCCUPATIONAL SAFETY AND HEALTH REVIEW
                      [email protected]
                 two 20th Sttwt, NM - 9th Fbor
                           ~ingt~,     DC 2003+m@

%gi$kZitF
SECRETARY OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 93-0648
DANELLA CONS’IRUCI’ION CORP. OF FL,IN
Respondent.

                       NOTICE OF DOCKETING
                 OF ADMINISTRATIVE LAW JUDGE’S DECISION
       The Administrative Law Judge’s Re rt in the above referenced case was
  docketed with the Commission on Mar cr 3,1994. The decision of the Judge
  will become a final order of the Commission on April 4,1994 unless a
  Commission member directs review of the decision on or before that date. ANY
  PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY ‘IHE
  COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
  Any such petition should be received b the Executive Secretary on or befixe
  March 23 1994 in order to rmit sud cient time for its review. See
  Commissibn Rule 91, 29 C.fi. 2200.91.
     All further pleadings or communications regarding this case shall be
  addressed to:
                         ExecutiveSecretary
                         Occupational Safety and Health
                           ReMew Commission
                         1120 20th St. N.W., Suite 980
                         Washington,
                         .            D.C. 20036-3419
  Petitioning parties shail also mail a copy to:
                         Daniel J. Mick, Esq.
                         Counsel for Re ‘onal Trial Liti ation
                         Office of the So%‘&or, U.S. Dck
                         Room S4004
                         200 Constitution Avenue, N.W.
                         Washington, D.C. 20210
  If a Direction for Review is issued by the Commission, then the Counsel for
  Regional Trial Litigation will represent the Department of Labor. Any party
  havmg questions about review nghts may contact the Commission’s Executive
  Secretary or call (202) 606-5400.
                                        FOR THE COMMION
                                                  .                             /


  Date: March 3, 1994

DOCKET NO. 93-0648
NOTICE IS GIVEN TO THE FOLLOWING:

Daniel J. Mick, m. ‘:
Counsel for Re *od Trial Liti’ation
Office of the So1 ‘dtor, U.S. Dck
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210

Don McCoy, Es l

Assoc. Re onal 5 elicitor
Office of tEe Solicitor, U.S. DOL
Federal Building, Rm. 407B
299 East Broward Boulevard
Ft. Lauderdale, FL 33301

David E. Jones, Es uire
Ogletree, De&ins, % ash, Smoak &
Stewart
3800 One Atlantic Center
1201 West Peachtree Street, N. w.
Atlanta, GA 30309 .

Paul L Brady
Administrative Law Jud e
Occupational Safety an d Health
Review Commission
Room 240
1365 Peachtree Street, N.E.
Atlanta, GA 30309 3119

00110062270:04
uunEDmmOF:m
OCCUPATIONAL SAFEW AND HEALTH REVIEW coMMlssloN
136SQEAcslfREE
STREEl,NE.,slm 240
AUNTA, GEoRGu 3om9-3119

                                                  :

SEQWIARY OFLABOR, l
0

,                                                 0
                                                  a
             v.                                   3        OSHRCDocket No. B-648
                                                 0
                                                 0

DANELLACONSIRUCI’ION a
CORPORATION OF FL,ORIDA,IN& ;

APPEARANCE%

    stepben Alan aa&      Bqllirc                DMdEJO!bC&BqUi#C
      oflb   of the solkitor                          Ogktree, DcaHns, Nab, Snmk & Stewart
      U.SDtputmentofLmbor                             -to-*
      Fort IA-     FIorida                               For Respondeat
        Fbr aMnplainant

Before: AdministrativeLaw Judge Paul L Brady

                                    DECISION AND ORDER


    This pmcecding is brought pursuant to section 10 of the Occupational safety and

Health Act (Act) to contest a citation issued by the Secretary of Labor (Secretary) pursuant
N
to section 9(a) of the Act.
The underlying facts in this case are not in dispute. On November 23, 1992,
respondent, Danella Construction Corporation of Florida, Inc. (Danella), was engaged to
ias&ll.telephone communication lines at the corner of Congress and Sixth Awnues in lalt;c
Worth,Fldda The work on that day invoked the shoring of a trench using an &foot shield
IIV~&wm being lifted with a boom truck An inspection of the worksite at that &e
resulttd in the issuance of the citation@
Prior to commencement of the hearing on the merits, the Secretary mwed to
withdraw item 2 of the citation and amend item 3. Both motions were granted, and item
3 was amended to allege a willful violation with a proposed penalty of $S,ooO.

               meged Serious Violation of 29 C.F.R. i 192GWb~


   The standard, which pertains to accident prevention, requires the employer to

“provide for frequent and regular inspections of the job sites, materials, and equipment to
be made by competent persons designated by the employers.”
The citation alleges that frequent and regular inspections of the work area were not
made by a designated person in the following instances:
(a) Employees were permitted to work under energizd power wires.
(b) Failing to contact power company to provide a safe work area.
(d) Competent person failed to inspect the work site while shoring a trench.

   In his posthearing briec the Secretary concedes that competent persons had

conducted an inspection of the worksite. The evidence shows that Messrs. Steven Pascale
and Nolan Marks, competent persons, inspected the worksite on November 23,1992, prior
to commencement of the shoring operation. Also, Nolan Marks remained on the site
throughout the day. The Secretary argues that the inspection of the worksite was deficient
because it failed to disclose that use of the crane in an area with overhead wires presented
a hazard to employees. It is pointed out that the inspection report (Exh. R-6) makes no
mention of the overhead wires.
The evidence establishes that the standard’s requirements have been met. There is
no dispute the site was inspected by competent persons prior to commencement of work on
the first day. In addition, a competent person was present during the entire period work was
being performed.

                                         2

Although the secretary argues the inspection was deficient in not revealing a hazard,
the standard’s hguage does not prcscriiii the manner in which an inspection should be
conducted. However, if Mous conditions are found, the “competent person,” as defined
in 8 1926.32(Q shall have “authorization to take prompt corrective measures to eliminate
them.” The f&t that work was being performed in the general area of overhead lines
cannot be considered substantial evidence to prwe a violation The mere presence of an
alleged hazard does not establish a violation of this standard. The evidence fails to show
that the requirements of the standard have not been met.
The standard was not violated as alleged.

                            Alleged Violation of 29 C.F.R. S 1926.55(Ka>(l5]


   The standard provides that:
   (15) Except where electrical distribution and transmission lines have been
   deenergized and vis~%iygrounded at point of work or where insulating barriers,
   not a part of or an attachment to the equipment or machinery, have been
   erected to prevent physical contact with the lines, equipment or machines shall
   be operated proximate to powerlines only in accordance with the fobwing

                 (i) For lines rated 50 kV. or below, minimum clearance
                 between the lines and any part of the crane or load shall be 10
                 feet;


   The alleged violation is &2WiIxd in the citation as follows:
   Equipment was operated where part of the equipment was within 10 feet of
   electrical distribution or transmission lines rated 50 kV or below that had not
   been de-energized and visibly grounded, nor had insulating barriers not a part
   oE, or an attachment to, the equipment been erected to prevent physical
   c o nta c t   with      th e   lines..   . l




   Mr. Joseph DiMartino, safety and health compliance officer, conducted the inspection

that gave rise to the issuance of the citation. He testified that, while driving his car along
Congress Avenue at the intersection of Sixth Avenue, he observed a crane being operated
with the tip of the boom close to overhead electrical lines. DiMartino stopped his car and
took photographs from a distance of approximately 100 feet. He estimated the boom to be

                                                            3

.

        Mr. Pascale, DaneIla%safety inspector, indicated that m                 the morning of the5
inspection, be and foreman Marks discus& the overbead ekctrid lines on the w&site.
They conchded their work would not be withinthe Wfwt danger zone of the lines vr. 143,
 149). Soon after the crane began to place the shoring plate or sbkid in the tre&h, it
became necessary to re-position the crane nearer to the truck. Mr. Marh observedthe
re-positioningand location of the boom and determined they were ‘Wwhcre near the power
lines”(Tr. 255256). At no time did he see the boom tipwithin 10 feet ofthe wetid                  lines
(Tr.265).     HettatedthatinmovingcloQertotheload,thekngthofthekKnnwas
shortened causing less possibilityof reaching tbe lines vr. 262463).
        Mr. GeorgeDunnaway, a laborer who was helping guide the shield into the trench,
testified the boom did not come witbin 10 feet of the overhead lines. He also stated, TUe
was watching the wires at all times, that’s why be couldn’t get no higher on account of the
wires. We seen the wires. We was staying away from the wires* (Tr. 286289).
        Tbe central question is whether the minimumclearance of 10fett between the boom
and overhead lines was maintained. No actual measurements were taken, and tbe
secretary’s evidence of the violation was based on the inspecting office& estimate of a
20fmt clearance whichhe made at a distance of approximately 10 feet. It is noted that the
visual approximationswere made at ground level of the moving boom which wzu in an




* “fbe photographs depicting the scene were recefvedinto evidence m Complainanti bhiiits   1 through 8.
No actual measwemts were taken at tk -

                                                  4

v-- .
. * *
.

                  elmted position. Danella refbtes the inspector’s observations with the testimony of two
                  emplayea who were much closer in proximityto the boom and its operation.
                         Wbik there was considerablediscussionof the crediiiilityof some witnesses, it is cl-
                  the Secretary has fkiled to establisb the violationby a preponderance of crediiile evidence.
                  The Secretary’sonly testimonyregarding the distance consistedof a visual estimate. Danella
                  adequately refI&edthe estimate with the testimony of two witnesses who were in a better
                  position to make more accurate estimates
                        Tbe evidence does not establish the violation as alleged.

                                                    FINDINGS OF FACI’
                                              AND CONCLUSIONS OF L,AW


                        The foregoing decision constitutes the findings of fact and conclusions of law in
              accordance with Federal Rules of Civil Procedure 52(a).

                                                           ORDER


                        Based on the foregoing decision, it is hereby ORDERED:
                        The citation alleging violations of 29 CF.R. 0 1926.20(b)(2)and 0 1926.55O(a)(l5)
              is hereby vacated.




                                                                  /s/ Paul L Brady
                                                            PAUL L BRADY
                                                            Judge

              Date: February 22, 1994

Get today's answer for your situation

You just read what one judge decided for one employer in 1994, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.