🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 92-0334 Decided October 18, 1993 Modified Judge Richard DeBenedetto

Bancker Construction Corp.

Trench support violation affirmed with reduced penalty

Apply this to your situation

This order from 1993 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1993
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Bancker Construction was installing a protective system in an excavation for a telephone equipment vault in Bethpage, New York. Employees entered the excavation while the support system was only partly installed, and the trench was more than five feet deep with vertical walls in unstable Type C soil. The judge found that a three-month delay in issuing the citation did not prejudice Bancker because the company already had measurements, photographs, and soil information. Bancker also failed to prove greater hazard or infeasibility because it could have begun installation at a depth of four feet or used another protective method. The amended serious violation was affirmed, but the proposed $4,000 penalty was reduced to $1,000.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.652(e)(1)(ii)
  • Outcome: The serious excavation-support violation was affirmed, and the proposed penalty was reduced from $4,000 to $1,000.
  • Key point: Greater-hazard and infeasibility defenses failed because the employer did not disprove available methods for protecting employees during installation of the trench support system.

Full text (OSHRC public release)

/ eA&R
v UNITED STATES OF AMERICA
L% OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
%
P
One Lafayette Centre
F z5 1120 20th Street, N.W. - 9th Floor
-‘I 3 2’ Washington, DC 20036-3419

PHONE: FAX:
COM (202) 6064100 COM(202)60~5O50
Frs (202) 6064100 FTs(202)606-5050

           SECRETARY             OF LABOR
                                     Complainant,
                         v.                                                       OSHRC DOCKET
                                                                                  NO. 92-0334
           BANCKER CONSTRUCTION CORPORATION
                       Respondent.


                                      NOTICE OF DOCKETING
                                OF ADMINISTRATIVE MW JUDGE’S DECISION . .
                The Administrative Law Judge’s Report in the above referenced case was
           docketed with the Commission on September 16, 1993. The decision of the Judge
           will become a final order of the Commission on October 18, 1993 unless a
           Commission member dire& review of the decision on or before that date. ANY
           PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
           COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
           Any such petition should be received b the Executive Secretary on or before
           October 6, 1993 in order to ermit suf rlcient time for its review.            See
           Commission Rule 91, 29 C. Fp.R. 2200.91.
              All further pleadings or communications              regarding this case shall be
           addressed to:

                                         Executive Secretary
                                         Occupational Safety and Health
                                          Review Commission
                                         1120 20th St. N.W., Suite 980
                                         Washington, D.C. 20036-3419
           Petitioning        parties shall also mail a copy to:

                                         Daniel J. Mick, Esq.
                                         Counsel for Regional Trial Liti ation
                                         Office of the Solicitor, U.S. DOc
                                         Room S4004
                                         200 Constitution Avenue, N.W.
                                         Washington, D.C. 20210
            If a Direction for Review is issued by the Commission, then the Counsel for
            Regional Trial Litigation will represent the Department of Labor. Any party
            havmg questions about review nghts may contact the Commission’s Executive
            Secretary or call (202) 6065400.
                    w-


          Date: September           16, 1993

DOCKET NO. 92.0334
NOTICE IS GIVEN TO THE FOLLOWING:

Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DOgL
Room S4004
200 Constitution Ave., N.W.
Washington. D.C. 20210
” I

Patricia Rodenhausen, E%l l

Re ional Solicitor
Of&e of the Solicitor U.S. DOL
201 Varick, Room 70?
New York, NY 10014

James McGahan, Esquire
Martin, Van de Walle, Guarino & .
Donohue
17 Barstow Road
Post Office Box 2074
Great Neck, NY 11021

Richard DeBenedetto
Administrative Law Jud e
Occupational Safety an f Health
Review Commission
McCormack Post Offic and
Courthouse, Room 420
Boston, MA 02109 4501

00101486785 :02

                                                 UNITED    STATES OF AMERICA
                      OCCUPATIONAL        SAFETY          AND       HEALTH        REVIEW   COMMISSION
                                JOHN   w. McCORMACK     POST OFFICE AND COURTHCUSE
                                                        ROOM 420
                                         BOSTON,    MASSACHUSETTS   02109-601


PHONE
COM (617) 223-9746

.
F-E 223-9746

                                                                             ..
                                                                             ..
   SECRETARY           OF LABOR,
                                                                              .
                     Complainant,

                     v.                                                      : OSHRC Docket No. 92-0334
                                                                             .
   BANCKER CONSTRUCTION                    CORP.

                     Respondent.


   Appearances:

             Steven D. Riskin, Esq.                                  James McGahan, Esq.
                     Office of the Solicitor                                Martin, Van de Walle, Guarino,
                     U.S. Department of Labor                                & Donohue
                              For Complainant                               Great Neck, New York
                                                                                    For Respondent


   Before: Administrative       Law Judge Richard DeBenedetto
                                          DECISION AND ORDER
              On November      11, 1991, Bancker Construction                Corp. (“Bancker”)     was cited for a
   repeat      violation   of 29 C.F.R. 8 1926.652(a)(l),              which requires       employees   working in
   excavations that are five feet or more in depth to be protected from the possibility of a cave-
   in by an adequate protective system. The Secretary amended the citation in his complaint
   to allege, instead,       serious violation      of 29 C.F.R. 8 1926.652(e)(l)(ii),             which requires
   employees who are insta ling and removing support systems from such excavations to be


                                                                1

protected from cave-ins, structural collapse, and being struck by parts of the support system

itself. The Secretary also reduced the original proposed penalty of $8000 to $4000.
The citation was issued as a result of an inspection conducted by Compliance Officer

Richard Andree on August 5th and 6th, 1991, of an excavation site in Bethpage, New York,

where Bancker was installing a controlled environment vault (“CEV”) or manhole designed
to house electronic equipment for New York Telephone Company (Tr. 19, 58, 81-82, 95-96,
99, 141-42; Exhibit R-2). It is undisputed that the excavation in question was approximately
18 feet wide, 36 feet long, and dug in Type C soil with vertical walls (Tr. 15, 85, 118, 146,
Exhibits C-3, C-5 & R-15).
THE “REASONABLE PROMPTNESS” ISSUE
Section 9(a) of the Occupational Safety and Health Act of 1970 (“Act”), 29 U.S.C.
8 658(a), provides:
If, upon inspection or investigation, the Secretary or his
authorized representative believes that an employer has violated
a requirement of...any standard-or of any regulations prescribed
pursuant to this Act, he shall with reasonable prm?yhieSs issue
a citation to the employer.
(Emphasis added). Bancker contends that in issuing the citation in question more than three
months after the 03% inspection, the Secretary. failed to comply with this requirement.l
According to Bancker, at no point prior to the issuance of the citation was it ever informed
that it was to be cited for a violation .2 Bancker’s Post-Hearing Brief at 27-28. As a result,
Bancker maintains that it was unable to gather important information about the excavation

1 The citation was issued well within the six-month limitation set forth in 5 9(c) of the Act, 29 U.S.C. 8 658(c):
“No citation maybe issued...after the expiration of six months following the occurrence of any violation.”

2 Walter Behrens, Bancker’s general manager, testified, however, that Bancker first learned of the alleged
violation almost two weeks prior to the issuance of the citation when the compliance officer held a closing
conference on October 29, 1991 with Rudy Giaccaglia, Bancker’s project superintendent (Tr. 26, 108, 120-22,
145-46).

                                                    2

                                                                                               .

necessary to its defense of this case since the CEV project had been completed by the time
the citation was issued. .
The Review Commission has held that “the appropriate consideration for determining
whether to vacate a citation for the Secretary’s noncompliance with section 9(a) of the Act
is the prejudice to the employer from the delay rather than the justifiability of the delay.”
Natl. Indus. ConsnUctors,Inc., 10 BNA OSHC 1081, 1084, 1981 CCH OSHD ll 25,743 (No.
76.4507,198l). See alsoBland Corrstr.Co., 15 BNA OSHC 1031,1040-41, 1991 CCH OSHD
7 29,325 (No. 87-992, 1991). Thus, it is not a question of whether the Secretary’s delay in
issuing the citation was proper, but whether the delay demonstrably prejudiced the employer
in the preparation of its case. Id. See ako Steams-Roger, he., 8 BNA OSHC 2180, 2183,
1980 CCH OSHD 1 24,870 (No. 780819,198O) (Review Commission rejects holding set forth
in Jack Coke & Sorts Cop., 4 BNA OSHC 1378, 1976-77 CCH OSHD li 20,849 (No. 6794,
1976) that a citation should be vacated pursuant to 6 9(a) of the Act if the circumstances
surrounding the citation’s issuance indicate that the delay was unnecessary and unjustifiable).
To support its allegation of prejudice, Bancker cites to several aspects of its case
which it claims was hindered by the delay. Specifically, Bancker states that it was unable to
“more accurately” measure the excavation at the time of the inspection, to conduct an
analysis of the soil making up the trench’s walls, to photograph the excavation “in more
detail”, and to hire surveyors or other qualified persons to evaluate the site (Tr. 145;
Bancker’s Post-Hearing Brief at 28). However, Bancker already had a significant amount
of information about the excavation available to it by the time the citation was issued. For
instance, several photographs of the excavation were taken by Giaccaglia, Bancker’s project
superintendent, both during and after the inspection (Tr. 94-98, 106; Exhibits R-3 through
R-11). Two of these photos depict a Bancker employee measuring the depth of the
excavation and, according to Giaccaglia, measurements of the excavation’s depth were also
taken earlier that morning on August 5th after the initial pilot cut was made (Tr. 86,116.17).
Moreover, Bancker has admitted that the soil in which the excavation was dug was granular,
sandy, Type C soil and has not shown that the performance of a soil analysis would have
indicated otherwise (Tr. 118, 146; Exhibit C-3 at 5). On the basis of these facts, it would be
unreasonable to hold that Bancker’s ability to gather information about the excavation site

                                             3

and prepare    a defense in this case was materially harmed by the three month lapse between
the OSm        inspection   and the issuance of the citation.             Accordingly,      the “reason;~bl~
promptness ” defense is rejected.

.
THE EXCAVATION SUPPORT SYSTEM UNDER 5 1926.652(e)(l)(iil

        Bancker acknowledges          that on the day of the inspection,           three of its employees
entered the excavation during the installation of a protective system consisting of steel beams
and wood planks (Tr. 8-9, 19-21, 23, 47, 100-01, 115). These employees entered the trench
to level off the area underneath       a square of steel beams that was resting on the floor of the
excavation and had four, dark blue, wood uprights attached at each corner (Tr. 87-88, loo-
01, 115, 147-48; Exhibits C-6 & R-15).3 This was accomplished                   by lifting the beams with
a cable attached to the excavator and placing blocks or boards underneath                     as needed (Tr.
100-01, 126-27, 147-48; Exhibits C-6, C-7, C-8, C-10, R-3, R-5 & R-6).
        Bancker maintains        that the excavation was cut at a precise depth of five feet as
demonstrated     by the fact that the six-foot-high blue upright pictured in Exhibits R-5 and R-6
seems to extend about one foot above the top of the trench (Tr. 85-86, 93-94, 114, 116-17,
124-25, 133, 142, 146). The compliance officer’s measurements,                 on the other hand, indicate
that the excavation ranged in depth frdm five feet, six inches to six feet, eight inches (Tr. ll-
13; Exhibit C-4). While it is true that in one of the photographs                taken by the compliance
officer, the trench pole he used to measure the depth of the excavation does appear to be
leaning at some sort of angle (Exhibit C-12), the four other measurements                    documented in
these photos clearly indicate that the excavation’s depth was over five feet in most areas.
Moreover, it is highly unlikely that the excavation could have been cut to precisely five feet
at all points; Giacagglia conceded as much at the hearing (Tr. 87, 124-25). Even Bancker’s
general manager, Behrens, admitted that due to the imprecision of the excavator, it was


3 To complete the protective system, a second square of beams was attached to the top of these uprights, then
wood planks were lain vertically, side-by-side, against these beams to create a large, walled “box” (Tr. 25, 91.
93, 10344; Exhibits C-6, C-8, C-10, & R-3 through R-l 1).

                                                       4

“very possible and very likely” the trench could be fiv,p feet deep in one spot, but six feet
deep in another (Tr. 151).4
Bancker also challenges the Secretary’s allegation that the excavation posed ;f h;lz;rrd
to the employees at the time that they entered it. It has already been established, however,

that the protective system was only partially installed at the time these employees were

inside the excavation which, as noted above, was over five feet in depth (Tr. 15-17, M-25,
65-66, 88, 101-04). Bancker has also admitted that the soil in which the excavation was dug
was granular, sandy soil that can be classified as Type C soil pursuant to Appendix A of
Subpart P (Tr. 118, 146; Exhibit c-3 at 5). Because granular soil has “no cohesive strength”,
it is, by definition, unstable soil. Appendix A, subsection (b), Definitions. As a result, the
conditions of this excavation were such that the employees inside the trench were clearly
exposed to the hazard of a potential cave-in. Accordingly, the Secretary has satisfied his
burden of proving a violation of the cited standard.
THE GREATER HAZARD AND INFEASIBILITY DEFENSES

    Bancker argues that in order to ensure the protection system utilized at this site was

properly installed in the excavation, its employees had to enter the trench to level the
bottom square of beams; if they had not done so, Bancker claims, the system could have
collapsed, exposing the employees to an even greater hazard than that posed by entering the
unprotected trench. Bancker also contends that any alternative to installing the protective
system in this manner was infeasible, essentially because the efficacy of the system would be
seriously compromised if it were installed in any other way? Although one may agree with

4 Even if the trench were shown to have been exactly five feet deep, contrary to Bancker’s interpretation of
the trenching standards’ requirements, only excavations which are less than five feet in depth, not five feet or
less, are exempt from the protection requirements set forth in Subpart P, 29 C.F.R. 65 1926.650 - 1926.652
(Tr. 118, 133, 135.36,150-51). # 1926.652(a)(l)(ii). As a result, Bancker could not validly argue that because
the excavation at this site was cut at a “safe” initial depth of five feet, compliance with these standards was
not required.

5 The compliance officer suggested that one possible alternative to having the employees enter the excavation
during the installation process was to utilize the bucket of the excavator from outside the trench to perform
whatever adjustments to the system were necessary (Tr. 30-31). According to both Giaccaglia and Behrens,
the specific task of levelling off the area beneath the bottom steel beams was much too delicate to be
performed in this manner; indeed, it is difficult to envision being able to place blocks underneath a square of
steel beams without actually entering the trench and manually doing so (Tr. 100-01, 126-27, 147-48).

                                                   5

Bancker that the type of protective      system utilized here must be installed in a precise
manner in order to be effective, Bancker has nonetheless failed to satisfy its burden of p~~~of
with regard to both of these defenses.
       In order to prove a greater hazard defense, an employer must show that the hazard

. of compliance is greater than that of noncompliance; that an alternative means of protection
is not available; and that a variance was either unavailable or inappropriate. Lauhoff Grail2
CO., 13 BNA OSHC 1084,1088, 1986-87 CCH OSHD !I 27,814 (No 81-984, 1987). See also
Falcon Steel CO., 16 BNA OSHC 1179, 1185 (NO. 89-2883, 1993). Giaccaglia and Behrens
stated that if the steel beams were not level, the system could fail, but neither explained in
what way that possibility would pose a1 greater hazard than that created by not complying
with the standard (Tr. 100-01, 104-05, 127, 147-48). Even if Bancker had established that
the hazard of compliance was greater, the record is devoid of any evidence relating to a
variance and Bancker has failed to show that an alternative method of protecting these
employees was not available.
According to the compliance officer, the violation could have been avoided by cutting
the excavation to an initial depth of four feet, as opposed to five feet or over, thereby
rendering the requirements set forth in the trenching standards inapplicable (Tr. 30-31).
Although Giaccaglia testified that this alternative was not feasible since at an initial depth
of four feet, the system’s steel framework would “drop down” as the trench was dug deeper
and the system as a whole would fail (Tr. 128-29, 133), Giaccaglia himself suggested a viable
way in which this problem could have been eliminated when he described the procedure
utilized by Bancker at this site to keep the protective system intact and prevent it from
“dropping down” as the excavation was dug to a depth of approximately 14 feet (Tr. .131-32).
Indeed, in response to questioning by the Secretary’s counsel, Giaccaglia was unable to
explain why this procedure could not be used to avoid the same problem he claims would
occur if the excavation was installed at an initial depth of four feet (Tr. 128-29, 131-35).
Even Behrens, who had initially testified that it was not possible to install the protective
system at an initial depth of four feet, conceded that it was possible to adapt the design of

the system to accommodate an initial installation depth of four feet (Tr. 148-52).6 Thus,
Ban&r has failed to prove that an alternative method of protecting its employees at this
site was unavailable.
The availability of this option also defeats Bancker’s claims of infeasibilitv. 4 Indeed,
the testimony of both Giaccaglia and Behrens suggests that it was possible to cut the trench
at an initial installation depth of four feet and still maintain the integrity of the system.
Furthermore, nothing in the record suggests that using this alternative installation depth
would have significantly altered or interfered with Bancker’s performance of work at this
site. Tnitityhdustries he., 15 BNA OSHC 1985, 1987, 1992 CCH OSHD ll 29,889 (No. 89
2317, 1992). It is not unreasonable to expect employers to alter routine work practices to
the extent that such changes are “reasonably necessary” to achieve compliance with OSHA
standards. Seibel Modem M”g. & FVeldirrgCorp., 15 BNA OSHC 1218, 1227, 1991 CCH
OSHD li 29,442 (No. 88-821, 1991).
It should also be observed that one of the alternative methods of protecting
employees from a cave-in is the sloping protective system described in Appendix B to
Subpart P, which calls for Type C soil to be sloped at an angle not steeper than one and
one-half horizontal to one vertical (34 degrees measured from the horizontal). Bancker
failed to explain why this abatement system was not a feasible option under the
circumstances for which Bancker was cited. Where a feasible alternative to noncompliance
exists and the employer has failed to show that the alternative was infeasible under the
circumstances present at the worksite, a defense of infeasibility cannot be found. Id. at 1228;
State Sheet hJeta1 Co., 16 BNA OSHC 1155, 1160-61 (No. 90-2894, 1993).
Because it is likely that an employee would suffer serious physical injury or even
death in the event of a cave-in, the violation is properly characterized as serious. 29 U.S.C.

6 Behrens had originally indicated that at this depth, ten feet of the 14.foot-long wood planks used to shore
the walls of the excavation would extend above the top of the trench (Tr. 148-49). He never actually
identified, however, how this condition renders the four foot alternative infeasible, stating only that the boards
might “flap around” and have to be pushed down by a machine or tool which, in turn, might involve the
erection of scaffolding (Tr. 148-49).

                                                    7

8 666(k). A penalty in the amount of $l,ooO is appropriate under the penalty criteria of 29
U.S.C. 5 666(j).
Based upon the foregoing findings and conclusions, it is
ORDERED that the citation is affirmed and a penalty of $1,000 is assessed.

                                                RICHARD DeBENEDETTO
                                                Judge, OSHRC

Dated: September 10, 1993
Boston, Massachusetts

Get today's answer for your situation

You just read what one judge decided for one employer in 1993, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.