🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC Commission decision Docket 90-1349 Decided September 30, 1993 Citations affirmed

Pitt-Des Moines, Inc.

Derrick safety-device violation affirmed

Apply this precedent to your situation

This is citable Commission precedent from 1993, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1993
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Pitt-Des Moines used a derrick to carry employees in a man-basket more than 90 feet up a water tower without an anti-two-blocking device. The device prevents the overhaul ball from contacting the boom tip and severing the line supporting the basket. The Commission rejected the company's infeasibility defense because existing technology could have been adapted to its derricks and its eventual installation of a working system showed technological feasibility. The record showed that internal approval procedures, unclear responsibility, and low priority delayed compliance rather than unavailable technology. The derrick's design and the remote likelihood of an accident did not amount to alternative protection. The Commission affirmed the serious violation and a $500 penalty.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.550(g)(3)(ii)(C)
  • Outcome: The serious anti-two-blocking violation was affirmed, and a $500 penalty was assessed.
  • Key point: An infeasibility defense fails when available technology can be adapted and the delay in compliance results from the employer's administrative choices rather than barriers beyond its control.

Full text (OSHRC public release)

UNITED STATESOF AMERICA
OCCUPATlONAL SAFETY AND HEALT’H REVIEW COMMISSION
One Lafayette Cents
1120 20th Street, NW. - 9th Floor
Washington, DC 20036-3419
I

                                                                                Ei (202) 6o8-wso
                                                                                Frs(202)606-m50


                                       ..

SECRETARY OF LABOR, ..
.
Complainant, _ :
..
v. ..
Docket No. 904349
..
PITT-DES MOINES, INC., ..
.

          Respondent.


                           NOTICE OF COMMISSION DECISION

The attached decision by the Occupational Safety and Health Review Cc)n~lnissi()ll w;hs issllt:Cf01)
September 30,1993. ANY PERSON ADVERSELY AFFECTED OR AGGRIEVED WH() W~S}~E:S
TO OBTAIN REVIEW OF THIS DECISION MUST FILE A NOTICE OF APPEAL, W[‘rH ‘THE
APPROPRIATE FEDERAL COURT OF APP&KS WITHIN 60 DAYS OF THE DATE OF ‘rws
DECISION. See Section 11 of the Occupational Safety and Health Actt)t’ 1970~ 29 u.S.C. Q ~a.

                                               FOR THE COMMISSION

September 30, 1993
Date
R, #Q&!j
Ray H. Darling, Jr.
Executive Secretary

Docket No. 90-1349

NOTICE IS GIVEN TO THE FOLLOWING:

Daniel J. Mick, Esq.
Counsel for Regional Trial Litigation
Office of the Solicitor, U.S. DOL
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210

John H. Secaras, Esq.
Regional Solicitor
Office of the Solicitor, U.S. DOL
Room 844
230 South Dearborn St.
Chicago, IL 60604

Richard F. Gisler, Esq.
Pit t-Des Moines, Inc.
3400 Grand Avenue
Neville Island
Pittsburgh, PA 15225

Benjamin R. Loye
Administrative Law Judge
Occupational Safety and Health
Review Commission
Room 250
1244 North Speer Boulevard
Denver, CO 80204-3582

                                      UNITED STATES OF AMERICA
         OCCUPATIONAL           SAFETY       AND HEALTH REVIEW                COMMISSION
                                      One Lafayette Centre
                                1120 20th Street, N.W. - 9th Floor
                                   Washington, DC 20036-3419


                                                                                                  FAX:
                                                                                                  COM (202) 6064050
                                                                                                  Frs (202) 606-5050
                                                         .
                                                         .

SECRETARY OF LABOR, ..
..
Complainant, ..
..
.
v. . OSHRC Docket No. 90-1349
.
a
PITT-DES MOINES, INC., ..
..
Respondent. ..
..

                                              DECISION -

BEFORE: FOULKE, Chairman, and MONTOYA, Commissioner.
BY THE COMMISSION:
On February 17,1984, the Occupational Safety and Health Administration (“OSHA”)
issued a proposed standard governing “Crane or Derrick Suspended Personnel Platforms.”
The final rule was issued on August 2, 1988. The rule initially required anti-two-blocking
devices’ to be installed by October 3, 1988. However, in response to a flurry of temporary
variance applications and industry complaints that manufacturers of the devices were unable
to fill all their delivery orders promptly, OSHA issued a bulletin on June 26, 1989 extending
the compliance deadline to December 31, 1989.
On March 30, 1990~-three months after the previously extended abatement deadline
and twenty months after the issuance of the final rule--0SHA inspected a Beloit, Wisconsin
worksite where Pitt-Des Moines, Inc. (“PDM”) was building a water tower. Employees were
being carried via a derrick-hoisted man-basket over 90 feet up to what are known as the

‘An anti-two-blocking device prevents the overhaul ball and the boom tip of a crane or derrick from
contacting each other so as to sever the line holding the load--here, employees in a man-basket. Such a
device--activated by radio signals or, in a hard-wire system, by electrical signals--shuts down the hoist apparatus
before the ball reaches the boom tip.

                                                  2

stem and bowl of a pedestal-type water tower. No anti-two-blocking device was installed on
the derrick. PDM was cited for a serious2 violation of 29 C.F.R. 6 1926.S50(g)(3)(ii)(C)3,
which requires anti-two-blocking , devices to be installed on such derricks.
PDM did not dispute any of the elements of the Secretary’s prima facie showing of
a violation, i.e., the applicability of the standard, knowledge, exposure or non-compliance.
See Astra Pharmaceutical Rod& Inc., 9 BNA OSHC 2126, 1981 CCH OSHD Tl25,578
(1981), afd in part, remanded in part, 681 F.2d 69 (1st Cir. 1982). It asserted, however, the
affirmative defense of infeasibility. After a hearing on November 6-7, 1990 and March 12,
1991, Administrative Law Judge Benjamin Loye issued a decision on June 18, 1991 rejecting
PDM’s affirmative defense, affirming the citation and assessing a $500 penalty. PDM
petitioned for review of the judge’s decision and the case was directed for review.
I. Pwddural Issue: Untb&‘y Complaint
At the time this citation was contested, Commission Rule 34 required the Secretary
to file a complaint no later than thirty days after he forwarded the notice of contest to the
Commission.4 On May 15, 1990, the Secretary forwarded the notice of contest received
from PDM but, without filing a motion for an extension of time, failed to file his complaint
until thirty-six days later, on June 20, 1990. The Secretary offered no explanation for the
delay. PDM did not move to dismiss the complaint, but rather raised the Secretary’s failure

2At the hearing, the Secretary’s motion to amend the citation to “willfW’ was granted from the bench, but the
judge did not ultimately find the violation to be willful. The “willful” characterization was not a subject of
the petition or direction for review.

?he standard provides:

    s 1926.550 Cranes and Derricks
    ....
    (g) Crane or de&k suspended personnel plaforms-
      ...
    i3) c ranes and deni&--
    ....
    (ii) Instruments and components.

    ibi k positive acting device shall be used which prevents contact between the load block or
    overhaul ball and the boom tip (anti-two-blocking device), or a systemshall be used which
    deactivates the hoisting action before damage occurs in the event of a two-blocking situation
    (two block damage prevention feature).

4The Rule has since been revised to require the complaint to be filed no later than twenty days.

                                                    3            I

to comply with the rules as an affirmative defense in its answer, and argues that the judge
erred in failing to vacate the citation or at least consider the issue in his decision.
The judge did consider the issue in his decision, however. Noting that action under
Rule 415 is at the discretion of the judge, he concluded: “As Respondent has not been
prejudiced in any way by the Secretary filing [his] Complaint two days late, this judge finds
that dismissal would be inappropriate.‘*
The Commission has since held that prejudice is only one of the factors to be
considered in determining whether a sanction is warranted under Rule 41. See Chartwell
Corp., 15 BNA OSHC 1881,1883,1992 CCH OSHD ll 29,817, p. 40,627 (No. 9102097,1992)
(Secretary’s citations vacated after considerable, unexplained delays in filing a long-promised
settlement agreement). Other factors include willful or contumacious conduct, which PDM
does not allege here; whether there is a clear record of substantial delay; and principles of
judicial economy. See Ford Dev. Corp., 15 BNA OSHC 2003, 2005, 1992 CCH OSHD
li 29,900, p. 40,797 (No. 90-1505, 1992), petition for review jiled, No. 93-3090 (6th Cir.
Jan. 29, 1993), citing Duquesne Light Co., 8 BNA OSHC 1218, 1980 CCH OSHD ll 24,384
(No. 7805034,198O) ( consolidated cases). In Ford, the Commission considered an employer’s
motion to dismiss for the Secretary’s failure to transmit the notice of contest within the
period required by the Commission’s rules. The employer alleged no prejudice and the
Commission found that the 7-day delay was not the result of contumacy on the Secretary’s
part. “Nor,” the Commission held, “do any of the other factors indicate that such a harsh
sanction would be in order.” Id. Similarly, in Jensen Constr. v. OSHRC, 597 F.2d 246, 247

‘Rule 41 provides in relevant part:

    Failure to obey rules.
    (a) Sanctions. When any party has failed to plead or otherwise proceed as provided by these
    rules . . . he may be declared to be in default either: (1) on the initiative of the . . . Judge
         or (2) on the motion of a party. Thereafter, the . . . Judge, in [his] discretion, may . . .
    strike any pleading or document-not filed in accordance with these rules.

    (b) A4otionto set aside sanctions. For reasons deemed sufficient by the Commission or Judge
    and upon motion expeditiously made, the Commission or Judge may set aside a sanction
    imposed under paragraph (a) of this rule.

tie judge apparently miscalculated the deadline. According to a 1990 calendar and the Secretary’s brief, the
filing deadline was June 14, 1990 and the complaint was filed six days late.

                                                   4

(10th Cir. 1979), a case in which the Secretary filed a complaint forty-eight days late due to
“an extraordinary caseload,” the court found that the judge did not abuse his discretion in
excusing the untimely filing.
In some circumstances, a review of the pertinent factors demands harsh results, e.g.,
Chartwell;Cornell & Co. v. OSHRC, 573 F.2d 820 (3d Cir. 1978) (cited in Jensen); in others,
such an “extreme sanction” is seen as “incongruous.” See Marshall v. CF. & I. Steel Cop.,
576 F.2d 809,814 (10th Cir. 1978) (cited in Jensen). The judge in this case appears to have
focused on the “prejudice” factor in deciding to excuse the untimely filing. Although the
Commission subsequently recognized that prejudice is but one of the factors to consider in
imposing sanctions, consideration of the other factors does not lead us to find that the
judge’s decision to allow the case to proceed was so clearly erroneous as to constitute an
abuse of discretion. We therefore affirm the judge’s decision insofar as it rejects PDM’s
affirmative defense based on the Secretary’s failure to file a timely complaint, and turn to
the merits of the violation.
II. 27ie Metits
A. The Employer’s Arguments
As previously stated, PDM acknowledges on review that the Secretary had established
a prima facie violation of the standard and focuses exclusively on its arguments that the
judge erred in rejecting its assertion of the affirmative defense of infeasibility.’ PDM’s
arguments in this regard are threefold.

‘At the time the judge rendered his decision, Commission precedent on the relative burdens of proof in cases
involving the affirmative defense of infeasibility was different from the current Commission position. At that
time, if an employer could’ demonstrate that compliance with a standard’s literal requirements was infeasible,
the burden would then shift to the Secretary to show that in lieu of literal compliance with the standard,
practical and realistic alternative means of protection were available to the employer. The judge observed that
in Dun-Par Engd. Form Co., 843 E2d 1135 (8th Cir. 1988), the Eighth Circuit had relieved the Secretary of
this burden, but that on remand, the Commission limited the Eighth Circuit’s view to being only the “law of
the case,” leaving intact Commission precedent that placed the burden on the Secretary. Dun-Par Engd Form
Co., 13 BNA OSHC 2147, 198790 CCH OSHD II 28,495 (No. 79-2553, 1989). Thus, the judge in this case
was bound by Commission precedent at the time. However, since he found that PDM did not establish the
initial quantum of proof, he did not reach the question of alternative measures. The Commission’s position
on this issue has since changed. See Seibel Modem Mfg. & Welding CO., 15 BNA OSHC 1218, 1991 CCH
OSHD Ii 29,442 (No. 88821, 1991) (Commission places entire burden on the employer). However, this does
not affect the validity of the judge’s findings in any way.

                                             5

   First, PDM claims that the judge’s finding that an anti-two-blocking    system could have

been assembled from components readily available was not supported by a preponderance
of the evidence. PDM criticizes the judge for relying on the opinion of James S. Kontos, a
mechanical engineer with the OSHA’s Office of Technical Support, who testified that the
technology to implement a hard-wire anti-two-blocking system was available before OSHA’s
inspection. That is, Kontos testified that the various parts of a hard-wire system were
manufactured and were available for purchase. PDM would have the judge rely, instead,
on the testimony of its Operations Manager, John Newmeister, that while devices were
available on the market for the majority of PDM’s rubber-tired and crawler cranes, and that
other cranes had been purchased with the devices already installed, the manufacturers he
had contacted were unable to provide PDM with a device which could be used for the
guyless derricks at issue in this case. Newmeister further testified that he and other high-
level PDM managers had formed a committee to research and determine how to approach
the problem of adapting this technology. He noted that he had also contacted PDM’s trade
association, the Steel Plate Fabricator’s Association, which informed him that none of its
members had been able to procure an anti-two-blocking device appropriate for use on
derricks such as PDM’s.
Carrying this argument further, PDM argues that requiring an employer to invent and
implement safety equipment that is not currently available “is a major step beyond current
precedent and deserves the scrutiny of the Commission.” If employers are to be expected
to comply with standards in this way, PDM urges the Commission to accept its affirmative
defense of infeasibility. It claims that its efforts to implement safety equipment not readily .
available should be adjudged on “a level of activity which is reasonably commensurate with
the likelihood or remoteness of the harm occurring which the standard is designed to
prevent.” PDM characterizes this as a “reasonable efforts test.” While acknowledging that
it subsequently did implement a safety system that complied with the standard, PDM argues
that the level of effort it was required to put into this implementation process should bear
a reasonable relationship to the actual risk involved.

                                                  6

    Lastly, PDM argues that it had implemented             an “alternative   measure” of protection

because of the infeasibility of literal compliance. This alternative, it argues, is present in the
very design of the derrick which minimizes the risk of a two-block accident.
B. l7Ze Secretary’s Arguments
The Secretary maintains that PDM has failed to establish that it was infeasible for it
to achieve literal compliance with the standard through the installation of an anti-two-
blocking device and reminds the Commission that this burden of proof lies squarely on the
employer. See Seibel Modem M’jjg& Welding, 15 BNA OSHC 1218, 1991 CCH OSHD
ll 29,442 (No. 88-821, 1991). The Secretary argues that the testimony of Kontos, OSHA’s
engineer, rebutted any showing that PDM may have made concerning the infeasibility of
compliance. The Secretary claims that Kontos’ testimony that a hard-wire system could have
been installed on PDM’s guyless derricks established that it was feasible to comply with the
standard. The Secretary notes that although PDM raised a number of objections, both
safety-related and technological, to the hard-wire system, PDM failed to produce evidence
to counter this rebuttal testimony.
The Secretary concedes that the standard does not restrict an employer’s choice of
an appropriate compliance method in that it specifies the use of an “anti-two-blocking
device” or a “two block damage prevention feature.” See Note 3, supra. He argues,
nevertheless, that the implementation of the radio-signalled system that PDM chose over the
hard-wire system was delayed by internal, corporate administrative obstacles rather than by
technological problems. This delay the Secretary attributes to PDM’s failure to assign
responsibility effectively and to establish appropriate priorities for the development of the
device, as well as to its cumbersome system for approval of such expenditures. As an
example, the Secretary notes that this admittedly protracted corporate approval process
delayed PDM’s receipt of the components of this device from various manufacturers until
late 1989 and delayed installation of its first prototype until July 1990, a year and one half
after the radio-controlled device was chosen.
Lastly, the Secretary argues that because PDM never sought a variance, the
Commission should not permit the company to challenge the wisdom of the standard or
circumvent the variance procedures * established in the Act by raising the infeasibility defense

at this late stage. Further, to the extent that PDM claims that its derricks, based on a 27.
year old design, were unique and deserving of special treatment, the Secretary responds that
such problems were already specifically considered when the standard was issued. The final
rule contained an explicit finding by OSHA that while some older cranes would require
“considerable modification,” the standard does not require any devices that are not
“presently available.” To the extent that PDM claims not that it was infeasible to develop
and build the device, but that it was infeasible to develop and build it oyt time in keeping
with the Secretary’s compliance schedule, the Secretary responds that the Act already
recognizes that potential problem. He cites section 6(b)(6)(A) of the Act as providing a
procedure for employers to follow if a device is unavailable by the standard’s effective date: .
Any employer may apply to the Secretary for a temporary order granting a
variance from a standard . . . . Such temporary order shall be granted only
if the employer . . . establishes that (i) [it] is unable to comply witha standard
by its effective date because of unavailability of professional or technical
personnel or of materials and equipment needed to come into compliance
with the standard or because necessary construction or alteration of facilities
cannot be completed by the effective date, (ii) [it] is taking all available steps
to safeguard his employees against the hazards covered by the standard, and
(iii), [it] has an effective program for coming into compliance with the standard
as quickly as practicable.
Id. (emphasis added). PDM never sought a temporary variance, even though it was familiar
with the procedure.8 The Secretary claims that permitting an employer to rely on an infeas-
ibility defense as a substitute for seeking a temporary variance would deprive OSHA of the
opportunity to evaluate a company’s interim measures.

81nits reply brief, PDM points out that application for a variance is not an element of the infeasibility defense,
only of the greater hazard defense, citing Seibel Modem Mfg. & Welding, 15 BNA OSHC 1218, 1991 CCH
OSHD ll 29,442 (No. 88-821, 1991), and thus argues that its failure to seek a variance in this case should not
stand in the way of its infeasibility defense. We agree. Seeking apemanent variance pursuant to section 6(d)
of the Act is properly an element of the greater hazard defense because such variances are granted to
employers whose workplaces are “as safe and healthful as those which would prevail if [they] complied with
the standard.” PDM seems to have confused the so-called “permanent” variance under section 6(d) with the
so-called “temporary” variance under section 6(b)(6)(A) noted by the Secretary. While applying for a variance
of any kind is not an element of the infeasibility defense, it is this latter section that may be suited to obtaining
short-term relief for an employer who, despite its best efforts, is technologically incapable of meeting the
requirements of a standard before the effective date of a standard, but still has time to seek a temporary
variance.

                                     C. Judge’s lkisbn
    The judge found that PDM had failed to show that compliance with the standard was

infeasible on two grounds.
First, with respect to PDM’s argument that the technology was unavailable, the judge
found that a preponderance of the evidence established that PDM could have implemented
the technology for a hard-wire system, even if problems were encountered in implementing
the radio-controlled system it preferred. The judge noted that evidence presented by the
Secretary’s expert witness, who outlined a workable hard-wire system, was not rebutted by
PDM. The judge found that PDM’s claims that it would be more dangerous to implement
a hard-wire system were not fully established. He found that PDM never explained how the
risks associated with installing a hard-wire system would be any different from those to which
employees were already exposed while erecting the *derrick itself, since the system would be
largely installed on, the ground, with the connections inside each section of the derrick
plugged in as the crew assembled the derrick. He also found that no evidence was offered
to show that PDM’s reservations about using electrical power were insurmountable or any
different from those associated with the radio system it eventually selected.
Second, and of greater importance in the context of our decision, the judge found that
PDM’s failure to comply was due not to technological obstacles, but rather to “the lingering
installation delays [that] were caused . . . by unwieldy administrative procedures, and a
failure of personnel to appreciate any urgency in having an operational anti-two-blocking
system.” The judge noted that PDM had implemented the radio-controlled device by July
1990, three months after the date of inspection, and had failed to establish that compliance
before that date was infeasible.
D. Analysis
As a preliminary matter, we note that the standard at issue is not broadly worded,
but specifies the means of compliance. Therefore, here, it is PDM’s burden to show
infeasibility as an affirmative defense, not the Secretary’s burden to show feasibility as an
element of his case.
I See Modem Drop Forge Co. v. Secretaryof Labor, 683 F.2d 1105, 1113
(7th Cir. 1982). With this in mind, our review of the judge’s decision follows.

                                                   9

    me essence of PDM’s claim is that it was infeasible for it to have complied with the

literal requirements of the standard before the date of inspection. PDM asserts that this is
so because an “off-the-shelf’ device that would have enabled it to comply was not
commercially available. Thus, compliance was dependent on PDM’s implementation -- or
as PDM describes it, “invention” -- of a workable device which could be applied to its
guyless derricks. In this regard, PDM asserts that how it carried out this duty to invent a
method of abatement should turn on whether the efforts it made were reasonable in relation
to the remote likelihood of any harm occurring. For the reasons that follow, we reject each
of these arguments.
As we noted above, the judge found that PDM’s failure to develop and install its anti-
two-blocking device in a timely manner was principally caused not by technological problems,
but by administrative delays that postponed the implementation of compliance. Our review
of this record reveals ample evidence to support this finding.
The Commission has long recognized that standards will, in some instances, require
some creativity on the part of employers seeking to achieve compliance. In Castle & Cooke
Foods, 5 BNA OSHC 1435,1977-78 CCH OSHD ll21,854 (No. 10925,1977), afd, 692 F.2d
641 (9th Cir. 1982), a noise control case, the Commission found that the judge’s finding that
certain engineering controls were not available for immediate implementation on the date
of the alleged violation did not necessarily mean that such controls were technologically
infeasible. Relying on testimony by the employer’s own expert that controls were “presently
available to significantly reduce the noise levels” at the employer’s plant, the Commission
found that the employer “would not be required to develop new technology, but rather to
adapt presently available technology.” Id. at 1437 (emphasis added).
As the judge noted, PDM itself proved the technological feasibility of anti-two-
blocking devices for its guyless derricks by eventually developing and installing them on its
derricks in July 1990. See Ametican Steel Woh, 9 BNA OSHC 1549, 1981 CCH OSHD
lI 25,285 (No. 77-553, 1981) (spray paint booth gauges and alarms installed after citation;
Commission specifically rejects finding by judge that employer’s “best efforts” were
satisfactory); Masonry Contrac., Inc., 8 BNA OSHC 1155, 1980 CCH OSHD ll 24,338 (No.

762902, 1980) ( erection of guardrail and completion of job after inspection shows

                                                   10

compliance was neither functionally impossible nor would it unduly interfere with work).
PDM did not claim that the delay was caused by a manufacturer’s inability to respond to a
timely order for parts or components, or that only a late technological breakthrough enabled

it to complete its work. To the contrary, it attempted to justify its minimal efforts by
proposing that an employer’s efforts be judged in relation to the likelihood of an accident.
PDM warns that a rule that penalizes an employer who develops a device between
the time a citation is issued and the time the case is decided is undesirable in that such a
rule might deter an employer from working diligently on a solution, or even cause an
employer to suspend its efforts pending the conclusion of the proceedings. We see no such
danger lurking in any reasonable employer’s response to a citation. To the extent that PDM
is invoking Rule 407 of the Federal Rules of Evidence,g the rule which excludes evidence
of subsequent remedial measures from tort litigation, that rule is inapposite here, where the
issue is feasibility of precautionary measures. Furthermore, the employer’s duty to comply
with the standard is ongoing and applies to all employees at all times, not just to a particular
plaintiff at a particular time. Evidence of eventual compliance, like any voluntary post-
citation abatement, may enhance the good-faith factor in the penalty calculation but does
not retroactively revoke the violation.”
In the case before us, the evidence establishes that neither John Newmeister, PDM’s
operations manager responsible for assuring that PDM construction sites have the proper

%e rule provides:

             When, after an event, measures are taken which, if taken previously, would have
    made the event less likely to occur, evidence of the subsequent measures is not admissible to
    prove negligence or culpable conduct in connection with the event. This rule does not
    require the exclusion of evidence of subsequent measures when offered for another purpose,
    such as proving ownership, control, or feasibilityof precautionary measures, if controverted,
    or impeachment.

(Emphasis added).

‘@Thisis not to say that an employer who attains compliance between the time of the inspection and the time
of the hearing is automatically deprived of the opportunity to establish an infeasibility defense. An employer
may show that it was infeasible to have been in compliance at the time of the inspection by demonstrating that
its good-faith efforts to comply on time were stymied by the unavailability of parts, unexpected engineering
problems or other factors beyond its control. If, unlike the employer in this case, an employer were able to
demonstrate that abatement of the hazard was infeasible despite its vigorous efforts aimed at timely
compliance, an infeasibility defense might well be established.

                                                    11

equipment, nor Ingl Zeise, a safety consultant hired by PDM, nor Thurman                  Yost, a civil
engineer and PDM’s safety director with twenty-five years with the company, could point to
any specific technological barriers which would have forced PDM to develop new technology

. to reach compliance.
In contrast, this record supports the judge’s finding that delays in achieving
compliance were attributable to a failure to adapt existing technology. The testimony of .

PDM’s safety director Yost bears this out in his voicing his perception             that no one was
“real[ly], you know, putting 110 percent effort into it.” Moreover, Eugene Holmes, a 30.year
veteran with the company who served as tool house manager, and as such was responsible
for procuring, maintaining,     or building the necessary tools to erect water towers, addressed
this level of effort in the testimonv as follows:


          Q0     Earlier today I heard testimony that you were the person responsible               for
                 trying to comply with the standard[‘s] requirements; is that true?

          A.     Yes, I guess so.

          Q.     Well, you aren’t sure when you say I guess so?

          A.     I was never actually called in by Mr. Newmeister and told [: “Get that thing
                 ready.“]

          Q.     You found out about your responsibilities       today, is that right?

          A.     Yes, that’s right.
                 (Laughter)

          Q.     Well, did you receive any instructions on your responsibilities         at the time in
                 writing?

          A.     No .

Holmes also blamed the lengthy approval process for the delay in achieving compliance.              He
admitted that he was under no deadline and he agreed that compliance with the standard
was something less than top-priority.       This testimony supports the judge’s finding that PDM’s
failure to timely comply was due to corporate obstacles rather than to the infeasibility of the
device.

                                                     12

         Since we find that PDM did not establish that a radio-controlled     device was infeasible,
we need not reach the issue of the feasibilitv of the hard-wire system proposed by Kontos.
                                                 d


Finally, even if we were to find that PDM met its initial burden of proving that literal

. compliance with the standard by the date of inspection was infeasible, it failed to show the
second prong of the infeasibility defense: that alternative measures were either used or
infeasible. For its part, PDM claims that the “alternative measures” it instituted was the
very design of the derrick itself. While the admittedly remote chance of a two-block accident
occurring may help support a relatively low penalty, it does not prove the absence of a
violation. PDM fell short, however, of establishing that the design of its derrick constituted
the use of an alternative means of protection.
Accordingly, we find that PDM has failed to establish that adaptation to available
technology was infeasible and, thus, has failed to establish the affirmative defense.
III. or&r
The judge’s decision finding a violation of 29 C.F.R. 8 1926SSO(g)(3)(ii)(C) is
affirmed, and a penalty of $500 assessed.

                                                               Edwin G. Foulke, Jr.
                                                               Chairman


                                                               Velma Montoya
                                                               Commissioner

Dated:       September 30, 1993

                                         UNITED STATES Of AMERICA                                l


             occUPATIONAL        SA FETY.g5AND     HEALTH RE VIEW COMMISSION
                                             F ST!xE “J:Jl/
                                            4rt-i ‘L’,?CR
                                       wStilNG;6N    DC 20006- 1246

Secretary of Labor, .. =: I

                                                                                      - -a4
                                                                                                         -   .
                                                                                     -d    *   -,-
                                                                                     I__^,         .-.

           Complainant,            :                                                 -   .-.
                                                                                         _   _.-   -


                   v.
                                                     Docket No. 90-l 349

Pitt-Des Moines, Inc., .
Respondent. i
.

                               NOTICE OF DOCKETING

The Administrative Law Judge’s Report in the above referenced case was docketed with the
Commission on July 5, 1991. The decision of the Judge will become a final order of the
Commission on August 5, 1991 unless a Commission member directs review of the decision on
or before that date. ANY PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW. Any such petition
should be received by the Executive Secretary on or before July 25, 1991 in order to permit
sufficient time for its review. See Commission Rule 91, 29 C.F.R. Q 2200.91. .

All further pleadings or communications regarding this case shall be addressed to:

                          Executive Secretary
                          Occupational Safety and. Health
                           Review Commission
                          1825 K St., N.W., Room 401
                          Washington, 0. C. 20006-l 246

Petitioning parties shall also mail a copy to:

                          Daniel J. Mick, Esq.
                          Counsel for Regional Trial Litigation
                          Office of the Solicitor, U.S. DOL
                          Room S4004
                          200 Constitution Avenue, N.W.
                          Washington, D.C. 20210

If a Direction for Review is issued by the Commission, then the Counsel for Regional Trial
Litigation will represent the Department of Labor. Any party having questions about review rights
may contact the Commission’s Executive Secretary or call (202) 634-7950.

July 5, 1991
Date

Docket No. 904349

NOTICE IS GIVEN TO THE FOLLOWING:

Daniel J. Mick, Esq.
Counsel for Regional Trial Litigation
Office of the Solicitor, U.S. DOL
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210

John H. Secaras, Esq.
Regional Solicitor
Office of the Solicitor, U.S. DOL
Room 044
230 South Dearborn St.
Chicago, IL 60604

Richard F. Gisler, Esquire
Pitt-Des Moines, Inc.
3400 Grand Avenue
Neville Island
Pittsburgh, PA 15225

Benjamin R. Loye
Administrative Law Judge
Occupational Safety and Health
Review Commission
Room 250
1244 North Speer Boulevard
Denver, CO 80204-3582

                 UNITED STATES OF AMERICA

     OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION


                                 I

SECRETARY OF LABOR, I
Complainant, 1
1
v. I OSHRC DOCKET
I NO. go-1349
PITT-DES MOINES, INC., I
I
Respondent. 1
I

 APPEARANCES:
        For the Complainant:     -
            Leonard Borden, Esq., Office of the Solicitor,
            U. S. Department of Labor, Chicago, IL
        For the Respondent:
            Richard Gisler, Esq., Pittsburgh, PA


                    DECISION AND ORDER

LoYe I Judge:

 This proceeding arises under the Occupational Safety and

Health Act of 1970 (29 U.S.C. Section 651 et seq.; hereafter
called the vgAct").
Following an inspection of respondent's Beloit, Wisconsin
worksite on March 30, 1990 (Tr. 24-25) by the Occupational
Safety and Health Administration (OSHA), the Secretary of Labor
issued to respondent, Pitt-Des Moines, Inc. (PDM), a 'serious'
citation alleging violation 29 C.F.R. 1926.55O(g)(3)(ii)(c) and
proposing a penalty of $400.00.

  PDM was, at all times         relevant to   this   action, engaged in

the management and supervision of water tower construction

(Answer 13). PDM admits it is an employer within the meaning
of the Act and that the Commission has jurisdiction over this
matter (Answer 94; Tr. 7).
On November 6-7, 1990, a hearing was held in Milwaukee,
Wisconsin. Additional testimony was heard on March 12, 1991.
At the hearing, complainant moved to amend the pleadings to
characterize the cited violations as 'willful' (Tr. 13). That
motion was granted at the conclusion of the hearing (Tr. 101).
Alleged Violations
Citation 1, item 1 alleges: I_-
29 CFR 1926.550(g)(3)(C)(c): A positive acting device was not
used to prevent contact between the load block or overhaul ball
and the boom tips:
The derrick crane used to lift personnel was not
equipped with a anti-two blocking feature.
The cited standard provides:
$1926.550 Cranes and derricks.
* * *

  (9) Crane or derrick suspended personnel platforms
                    * * *

  (3) cranes and derricks
                    * * *

  (ii) Instruments and components.
                    * * *

  (a A positive acting device shall be used which prevents
  contact between the load block or overhaul ball and the
  boom tip (anti-two-blocking device), or a system shall be
                            *      2

used which deactivates the hoisting       action before damage
occurs in the event of a two-blocking       situation (two block
damage prevention feature).
                     Statement of Facts

On March 30, 1990,    respondent was engaged in the construc-

tion of a water tower on Cranston Road, in Beloit, Wisconsin

(Tr. 2% A derrick was erected on top of the water tower, and
a work platform, or man basket, was attached to the hook of the
derrick (Tr. 26-27; Ex. C-l, C-4). Respondent admits that the

work platform was used to perform welding on the tower, which
was located over 9d feet above the ground on a 'stern*(Tr. 8,
26 1 39-40). Respondent further stipulates that no anti two
blocking device had been installed on the derrick (Tr. 8, 29).
An anti two blocking device is generally located just
below the boom, and transmits an electrical or radio signal
when the overhaul ball, located just over the derrick's hook,
and approximately 20 feet above the work platform, comes in
contact with it (Tr. 33, 38, 47-48, 77; Ex. C-2). The signal

from the anti two blocking device shuts down the hoisting appa-
ratus, preventing contact between the overhaul ball and the
boom tip (Tr. 33-35, 365; Ex. C-3). Such contact would normal-

ly result in the severing of the cable which supports the load
(Tr. 33, 368). severing of the support for the work platform
would likely result in serious bodily injury, including death
(Tr. 42, 369).
Mr. John Newmeister, Operations Manager for PDM, testified
that he was responsible for securing construction equipment for

                              3

PDM (Tr. 67). Mr. Newmeister testified that in August, 1988,
he became aware of the anti two blocking device requirement of
1926.55O(g)(ii)(c) which was to become effective on October 3,

1988 (Tr. 49, 81). Newmeister testified that at that time he
secured the required equipment for PDM's rubber tired and
crawler cranes, but was unable to locate any comparable equip-
ment for use on the derricks employed by PDM (Tr. 68, 72-74,

a9 ; See also, testimony of PDM Safety Director Thurman Yost,
Tr l 204, 216). Newmeister stated that he thereafter formed a
committee to pursue methods of compliance with the OSHA stan-
dard (Tr. 74). That committee eventually had two anti two
blocking radio systems manufactured-? Those devices have been
installed on derricks at other sites (Tr. 75-76).
Newmeisterls committee first met in September, 1988
(Tr. 276). The committee considered and rejected ‘hard wire'
electrical systems because of perceived problems in the instal-
lation, including unacceptable employee exposure, weather
damage to wiring, and interference with the rotating boom
(Tr. 119-124). Early in 1989 the committee decided to pursue a
radio controlled system (Tr. 114, 279-280). Negotiations with
manufacturers resulted in quotes for such a system in

 1 This Judge finds respondent's claims to have expended

in excess of $200,000.00 in procurement costs to develop the
anti two blocking devices exaggerated (Tr. 75). Mr.
Newmeister testified that the cost to purchase new hoists
(which were needed anpay, See Tr. 275) was approximately
$65,000.00, with only an adaional $6,500.00 for the radio
control components (Tr. 101, 104-106, 403; See also, Ex. C-9).
Clearly, respondent's major expenditures were for new equip-
ment, rather than for safety devices.

                                      4

April, 1989 (Tr. 117; Ex. C-8; EL C-1OL A purchase order was

issued around July 1989, and the equipment was received late in
1989 (Tr. 103, 107). PDM’s derricks could not be fitted with

the equipment, however, until PDM retrofitted its hydraulic
hoists with solenoid valves which would open upon receipt of
the anti two block's radio signal, and installed a solar col-
lector to power the radio transmitter. This was completed in
July, 1990, and the device is now operational, though not fully
tested (Tr. 105, 149-150, 269-271).
Mr. Eugene Holmes, PDM's Tool House'Manager, was in charge
of procuring equipment, including the anti two blocking devices
at issue (Tr. 256, 266). Holmes testified that he spent up-
wards of 500 manhours on procuring and installing the anti two
blocking devices in 1990, but less than that in both 1988 and
1989 (Tr. 288).
Mr. Holmes stated that process was delayed by a long corporate
approval system as well as personnel problems experienced by
the manufacturer (Tr. 274, 289). Holmes believe that the de-
vices might have been in service earlier if the project had
been assigned a higher priority (Tr. 283).
James S. Kontos, a mechanical engineer with OSHA Technical
Support (Tr. 346), testified that it was feasible to equip
PDM's derricks with a hard wire electrical anti two block sys-
tem comprised of components readily available from electrical
suppliers (Tr. 369, 375, 396-402; Ex. C-21 through C-24).

                              5

A   circuit   running   from the hoisting apparatus's      power

source to the anti two blocking device and back to the hoist
could be created by installing wires inside a conduit perma-
nently attached to the inside of the risers which support the
derrick (Tr. 384-386; Ex. C-14). Electrical connector plugs at
each riser joint would be joined as the risers were bolted into
place (Tr. 382-383, 387). A 'bus bar' inside the rotating
raceway at the top of the risers would connect the circuitry in
the risers to wires running out the boom (Tr. 369-373;
Ex. C-13, C-15). Those wires would be connected to a switch
which is operated by a counterweight placed on the hoist cable
(Tr. 374-376). Should the overhaul-ball come into contact with
the counterweight, the switch would open the circuit, cutting
off power to the hoist (Tr. 378-380).
Mr. Kontos testified that the circuitry would be protected
from the weather by a conduit, the ‘bus bar' by a boot of sili-
cone rubber (Tr. 373, 382-384). The drop in voltage caused by
multiple connections, 18 by respondent's count, would be negli-
gible (Tr. 413; Vol. II, 73-75, 84). Because the circuitry is
permanently attached to the boom and risers, employee exposure
during installation would not exceed that already necessary to
erect the risers (Tr. 407-408).
Mr 0 Newmeister stated that the system designed by com-
plainant could not be implemented on the hydraulic hoists that
PDM used, because there was no electrical system available

                                6

(Tr. Vol. II, 81). The hydraulic hoist is halted by dumping
hydraulic fluids with a valve or manual lever (Tr. Vol. II, 86,

89) 0 Newmeister admitted, however, that an electrical system
could be provided, and that it was possible that a valve system
which could be signaled electrically could be developed
(Tr. Vol. II, 87, 91, 97, 100). Mr. Kontos' design envisions
use of a generator as an electrical source which would activate
solenoid valves in the hoist (Tr. 377-379). The system PDM
eventually developed involved a solenoid valve system which was
activated by- a radio signal (Tr. 95-96). Newmeister also ob-
jected to the system based on employee exposure, stating that
in some applications, the raceway--requires assembly in two
sections in the air (Tr. Vol. II, 82).
No variance was sought from OSHA during the period from
the regulation's effective date to the date of the inspection,
though PDM was familiar with the procedure for obtaining vari-
ances (Tr. 145, 241, Vol. II, 19-20). Mr. Thurman Yost, PDM's
Safety Director testified that PDM didn't believe there would
be a variance granted (Tr. 242).2

 2 Any reliance by respondent on OSHA Notice STD-3, which

establishes a grace period of 15 months from the effective
date of §1926.55O(g)(3)(ii)(C) for compliance with its stric-
tures, would be misplaced. Firstly, STD-3 expired in
December, 1989, over three months prior to the inspection
which led to this inspection. Moreover, respondent made no
effort to establish that it attempted to comply with the
guidelines set forth in STD-3, which contain specific alterna-
tive measures to be followed by employers using cranes without
anti two blocking devices (Tr. 90-96; Ex. R-C).
7

      Mr . Newmeister testified that PDM's derricks are designed

to provide alternative protection to workers in a man basket
(Tr. 78). The derrick is positioned such that the boom tip is

located approximately 40 feet above the top of the water tower.
In order for the overhaul ball to come into contact with the
boom tip, the man basket would have to be hoisted completely
above the top of the tank, an unlikely event (Tr. 78), Ingle
Zeise, an independent safety consultant retained by respondent

(Tr l 155), testified that the probability of a two blocking
incident occurring with the boom point so far above the work
station, as on PDM's derrick, was remote (Tr. 176). PDM per-
sonnel were aware of no two blocking incidents involving PDM*s
derricks on elevated water tanks (Tr. 77, 203).
Alleged Violation of Sl926.55O(g)(3)(ii)(c)
The cited standard requires that a positive acting device
(anti two block), which prevents contact between the load block
or overhaul ball and the boom tip, be installed on cranes and
derricks utilizing suspended personnel platforms. Respondent
admits that, on the date of the inspection, its derrick was
used to support a personnel platform without being equipped
with the anti two block equipment required by the standard.
Respondent raises the affirmative defense of infeasibility?

      3
    Respondent also raises the Secretary's untimely filing

of her Complaint, and asks that this Judge dismiss the action
as authorized under the Commission's Rules of Procedure
s2200.41. Action under S2200.41 is at the discretion of the
Judge. As respondent has not been prejudiced in any way by
the Secretary filing her Complaint two days late, this Judge
finds that dismissal would be inappropriate.
. 8

                            Infeasibility
 In order to establish a defense of impossibility or in-

feasibility, an employer must demonstrate, by a preponderance
of the evidence, that compliance with a standard's literal

requirements is not possible or would preclude performance of

the employer's work. If proven, the burden shifts to the See-
retary to show that practical and realistic alternative means
of ,protection were available to the employer. Dun-Par Engi-

neered Form CO,, 12 BNA OSHC 1949, 1953 (No. 79-2553, 1986),
rev'd, 843 F.2d 1135 (8th Cir. 1988)?
This Judge finds that the respondent in this case failed
to prove that the installation of an anti two block device was
infeasible. The respondent failed to convincingly rebut the
Secretary's evidence of the feasibility of a hard wire anti two
block system. Moreover, respondent currently has in place a
radio system which is operating successfully in some of
respondent's other worksites.
The Secretary's expert's testimony credibly outlined a
hard wire system which could be assembled from components
readily available on the market. Respondent's objections to
the system were unconvincing. Although its witnesses argued
that installation of the system would require repeated employee

    In Dun-Par Engineered Form Company, 13 BNA OSHC 2147,
    4

2150 (No. 79-2553, 1988), the Commission adopted the decision
of the 8th Circuit reversing its earlier Dun Par decision as
the Yaw of the case" only, specifically declining to
acquiesce in that decision, and leaving Commission precedent
intact.

exposure, it was never explained how such exposure would exceed
that needed for the initial erection of the derrick? Respon-
dent objected to the use of an electrical system, but admitted
that an electrical power source, such as a generator could be
easily provided. Its claims that an electrical signal could
not be used to dump the hydraulic valves were unsubstantiated,
and unbelievable in light of respondent% use of solenoids
which could accept radio signals on its own anti two block
device.
It was respondent's choice to develop a radio controlled
anti two block system, and it spent approximately a year and a
half pursuing that option. The evidence establishes that there
were no technological obstacles to installing a radio system,
though such a system was not commercially available as a unit.
It is clear that the lengthy installation delays were caused
rather by unwieldy administrative procedures, and a failure of
personnel to appreciate any urgency in having an operational
anti two block system.
Respondent has failed to prove its affirmative defense,
and the cited violation will be affirmed.

  5
    Respondent may not rely, in any event, on employee

exposure as a defense to this citation, as that issue raises
the separate, 'greater hazard' affirmative defense.
Respondent specifically declined to raise the greater hazard
defense (Respondent's Brief, p.4), noting that it had failed
to file for a variance, an element of the defense.

                           10

                          Willful
        The Commission has held that in order to establish

that a violation was willful:
It is not enough for the Secretary to show that an
employer was aware of conduct or conditions constitu-
ting a violation; such evidence is necessary to es-
tablish any violation, serious or nonserious. l 0 l

    there must be evidence that an employer knew of an
    applicable standard or provision prohibiting the
    conduct or condition and consciously disregarded the
    standard.

Wiiliams Enterprises, Inc., 13 BNA OSHC 1249, 1256-57 (No. 850
355, 1987).
The issue of willfulness focuses on "the employer's state
of mind, e.g. its general attitude toward employee safety."
Seward Motor Freight, Inc., 13 BNA OSHC 2230, 2234 (No. 860
1691, 1989).
This Judge cannot find that the evidence in the record
establishes a conscious disregard of the law on respondent's
part. Although respondent could certainly have speeded along
the process to come up with an operational anti two block sys-

tern, there were plans under
. development to provide the system

that respondent felt would best meet its needs. Respondent
provided systems for all its other types of cranes, for which .

those systems were commercially available (Tr. 68). Moreover,
both photographs and the unrebutted testimony of respondent's
safety consultant establish that the actual likelihood of a two

block accident occurring, given the configuration of the der-
rick set up, was remote (Tr. 155, 176). The citation will be
affirmed as a 'serious' violation.
I 11

                        Penalty

PDM is a large company with over 2,000 employees (Tr. 79).

The Compliance Officer observed two employees exposed to the
anti two blocking hazard (Tr. 44). As noted, the likelihood of
a two block accident occurring was remote.
Taking the relevant factors into consideration, a penalty
of $500.00 is deemed appropriate.
Findings of Fact and Conclusions of Law
All findings of fact and conclusions of law relevant and
necessary to a determination of the contested issues have been
found specially and appear in the decision above. See Rule
52(a) of the Federal Rules of Civil Procedure. Proposed
Findings of Fact or Conclusions of Law that are inconsistent
with this decision are denied.

                           Order
 10    Citation 1, item 1, alleging violat&on of S1926.550

(g)(3)(ii)(c) is AFFIRMED as a 'serious' violation and a penal-
ty of $500.00 is ASSESSED. ' :

Dated: June 18, 1991

                             12

Get today's answer for your situation

You just read Commission precedent from 1993. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.