🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC Commission decision Docket 84-0556 Decided April 26, 1989 Mixed result

Capform, Inc.

Excavation inspection and crane-load items affirmed for $800

Apply this precedent to your situation

This is citable Commission precedent from 1989, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1989
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Capform performed concrete formwork in a 25- to 30-foot-deep excavation at a Dallas construction site. After repeated rain, an unshored excavation wall collapsed while a 100-ton crane was operating above it, killing one Capform employee and injuring another. The ALJ vacated the citation under the multi-employer worksite defense because Capform had not dug or shored the excavation. The Commission held that Capform still had to ensure a competent-person inspection after each rainstorm and could not rely passively on the general contractor. It also held that Capform created or controlled the crane-load condition because the crane was lifting Capform's formwork on its behalf, even though another employer operated it. Those two serious items were affirmed with a combined $800 penalty. A third general excavation-wall item was vacated as duplicative of the crane-load item.

Decision snapshot

  • Cited standard(s): 29 C.F.R. §§ 1926.651(c), 1926.651(d), and 1926.651(q)
  • Outcome: Rainstorm-inspection and crane-load items affirmed as serious for $800 total; general wall-guarding item vacated as duplicative.
  • Key point: A subcontractor remains responsible for protecting its own employees and must make affirmative checks rather than assume another employer has satisfied excavation requirements.

Full text (OSHRC public release)

Docket No. 84-0556

SECRETARY OF LABOR,

Complainant,

v.

CAPFORM, INC.,

Respondent.

OSHRC Docket No. 84-0556

DECISION

Before:BUCKLEY, Chairman, and AREY, Commissioner.

BY THE COMMISSION:

The primary issue in this case is whether Capform, Inc., a
plywood formwork subcontractor on a multi-employer construction site, violated two OSHA
safety standards alleging (1) that it failed to inspect after every rainstorm the
excavation in which its employees worked and (2) that it failed to sheet-pile, shore, or
brace an excavation wall to resist the extra pressure created by the operation of a
100-ton crane above and near the excavation wall. We conclude that Capform violated those
two standards as alleged. We also conclude that the Secretary of Labor's allegation that
Capform violated a third safety standard is duplicative of the second allegation referred
to above and should therefore be vacated.

Subcontractor Capform built, erected, and dismantled the
plywood formwork into which concrete was poured at a site where a partially-underground
parking garage was being built in Dallas, Texas. The excavation in which the garage was
being constructed occupied a large city block, and was about 25-30 feet deep. Three sides
of the excavation were protected from collapse by shoring. The side closest to where
Capform employees worked was neither sheet-piled, shored, nor braced. At the time of the
alleged violations, there had been "lots of rain"--some of it heavy--at the site
for the preceding month (including during the most recent two-week period, when Capform
worked at the rite). A 100-ton crane was positioned at the top of the unshored side of the
excavation, and it was moving back and forth along the excavation top. The crane's
superstructure sometimes came as close as 30 feet to the edge of the embankment. The crane
was used to lift Capform's formwork out of the excavation after the concrete poured into
those forms had hardened and the forms had been stripped. While the job of removing the
formwork from the excavation was proceeding, three segments of, the unshored wall of the
excavation collapsed. One Capform employee was killed. Another was injured.

On the day following the accident, one of the Secretary's
compliance officers, Henry R. Slagle, investigated the accident site. As a result of that
investigation, Capform was issued a serious citation alleging that it had violated three
different safety standards: 29 C.F.R. � 1926.651(d), by not having a competent person
inspect the excavation after every rainstorm; 29 C.F.R. � 1926.651(q), by not protecting
the excavation from the extra pressure exerted on it by the crane; and 29 C.F.R. �
1926.651(c), by not guarding the unshored wall of the excavation that exposed Capform
employees to a danger of moving ground. An $800 total penalty was proposed by the
Secretary.

The administrative law judge vacated all three items of the
Citation. He found that Capform did not create or control the hazardous conditions, and
that it did not have--and with the exercise of reasonable diligence could not have
had--notice of the hazardous conditions. The judge therefore concluded that Capform had
established the "multi-employer worksite" affirmative defense that it had
raised. See Anning-Johnson Co., 76 OSAHRC 54/A2, 4 BNA OSHC 1193, 1198,
1975-76 CCH OSHD � 20,690, pp. 24,783-84 (No. 3694, 1976); Grossman Steel &
Aluminum Corp., 76 OSAHRC 54/D9, 4 BNA OSHC 1185, 1189-90, 1975-76 CCH OSHD � 20,691,
pp. 24,791-92 (No. 12775, 1976). Review was directed on whether the Secretary had made out
a prima facie case that Capform violated the three standards and, if so, whether the judge
correctly concluded that Capform had proven the multi-employer worksite defense.

I. Inspection of Excavation by Competent Person after
Rainstorms

The Secretary alleges that Capform violated section 1926.651(d)
by failing to have a competent person inspect the excavation after every rainstorm to
determine whether the excavation needed increased protection against cave-ins. Section
1926.6511(d) Provides:

� 1926.651 Specifics excavation requirements

(d) Excavations shall be inspected by a competent person after
every rainstorm or other hazard-increasing occurrence, and the protection against slides
and cave-ins shall be increased if necessary.

A "competent person" is defined at 29 C.F.R. �
1926.32(f):

� 1926.32 Definitions.

The following definitions shall apply in the application of the
regulations in this part:

(f) "Competent person" means one who is capable of
identifying existing and predictable hazards in the surroundings or working conditions
which are unsanitary, hazardous, or dangerous to employees, and who has authorization to
take prompt corrective measures to eliminate them.

To prove a violation of the standard, the Secretary must
establish (1) the applicability of the standard, (2) the existence of noncomplying
conditions, (3) employee exposure or access, and (4) that the employer knew or with the
exercise of reasonable diligence could have known of the violative condition. Dun- Par
Engineered Form Co., 86 OSAHRC 40/A8, 12 BNA OSHC 1962, 1965, 1986-87 CCH OSHD �
27,651, p. 36,033 (No. 82-928, 1986).

There is no substantial dispute about any of the elements of
the Secretary's burden. The standard applies whenever rainstorms occur while work is done
in an excavation, and frequent rainstorms occurred during the two-week period that Capform
employees worked at the excavation site. The excavation was not inspected by a competent
person after every rainstorm. Capform does not Contend that either its jobsite
superintendent, Pelletier, who was at the jobsite on a daily basis, or its project
manager, Cur., L. Hitt, who was at the jobsite on an every-other-day basis, were
"competent person[s]" as defined in section 1926.32(f). Capform does not contend
that any "competent person" inspected the excavation after every rainstorm.
Instead, Capform points to evidence that the general contractor's insurance agent and a
State of Texas safety inspector had each visited the site, viewed the excavation, and yet
not stated that anything further needed to be done to protect the unshored wall of the
excavation from collapse. This evidence, however, is of no avail to Capform, since it does
not establish when those persons appeared at the jobsite, much less that they appeared at
the site and inspected the excavation after every rainstorm that occurred during the
two-week period Capform employees worked there.

Capform's jobsite superintendent, Pelletier, was on the jobsite
daily and undoubtedly observed the soil after every rainstorm. But the standard clearly
contemplates more than casual observation. Moreover, Capform itself appears convinced that
Pelletier was not a "competent person". In a section of its review brief devoted
to contesting the Secretary's section 1926.651(c) allegation, Capform, relies on
Pelletier's testimony that he had never had responsibility for inspecting the condition of
soil in excavations and argues that Pelletier "lacks ... expertise in soils-related
areas". The Secretary has therefore established the existence of noncomplying
conditions, that is, that the excavation was not inspected by a competent person after
every rainstorm or hazard- increasing occurrence.[[1/]]

The existence of employee exposure is not in dispute. Capform
employees worked near the unshored excavation wall while erecting and dismantling
formwork. They also worked in the area while attaching dismantled formwork to the crane
line for lifting out of the excavation--the job that was being performed when the fatal
collapse of the unshored excavation wall occurred.

Knowledge of the violative condition is also not in dispute.
Capform's supervisors were continually present at the worksite. They admitted that they
knew about the rainstorms, yet did not assure that the excavation was inspected by a
competent person after the rainstorms. The Secretary has therefore established a prima
facie case of Capform's violation of the cited standard.

We must now decide whether Capform established its
multi-employer worksite defense. To establish the defense, Capform must prove, by a
preponderance of the evidence, that.

  1. It did not create the violative condition; and

  2. It did not control the violative condition such that it could realistically have abated
    the condition in the manner required by the standard; and

  3. (a) It made reasonable alternative efforts to protect its
    employees from the violative condition; or

(b) It did not have, and with the exercise of reasonable
diligence could not have had, notice that the violative condition was hazardous.

See Anning-Johnson ,4 BNA OSHC at 1198, 1975-76
CCH OSHD at pp. 24,783-84; Grossman Steel, 4 BNA OSHC at 1189-90, 1975-76 CCH OSHD
at pp. 24,791-92.

Capform argues that it did not create or control the violative
condition because it did not dig the excavation and was not responsible for shoring it. It
also argues that it did not have notice that cave-in risks were increased by rainstorms,
because it had no expertise in determining soil stability. According to Capform, the
general contractor was the employer on the worksite with some expertise and it was
responsible for assuring that the excavation was safe.

The judge concluded that Capform had established the defense.
He found that Capform had neither created nor controlled the hazardous condition, and that
although "it had rained from time to time in the month or so before the accident, the
respondent's supervisory personnel did not have sufficient knowledge in such matters as to
be able to conclude that the embankment might collapse."

The Secretary contends that inspection by a competent person
was clearly within Capform's control, and that if Capform's, did not have competent
persons on its own staff to do the inspecting, it could have obtained the services of
someone else. The Secretary emphasizes that Capform never requested an inspection, or even
inquired into whether the general contractor had conducted the inspections required by the
standard.

The multi-employer worksite defense does not alter the general
rule that each employer is responsible for the safety of its own employees. Anning-Johnson,
4 BNA OSHC at 1198-99,1975-76 CCH OSHD at p. 24,784. Capform's business involved work in
excavations. It had a duty to protect its employees who worked in the excavations. This
duty required Capform to familiarize itself with the OSHA standards and to take
affirmative steps to assure that its employees received the protection required by the
standards.

The standard at issue here, section 1926.651(d), requires that
a competent person inspect an excavation after every rainstorm to determine whether
protection for employees working within the excavation needs to be increased. Even if
Capform lacked expertise in soil stability, the standard put Capform on notice that
rainstorms can decrease the stability of an unsupported excavation wall and that
inspections to determine whether this had occurred were necessary. If Capform did not
itself employ a "competent person" within the meaning of the cited standard,
that did not prevent it from determining whether the general contractor, who Capform
contends was responsible for the safety of the excavation, had conducted the required
inspections.

If Capform had made such an inquiry and discovered that the inspections had in fact been
conducted, Capform would thereby have known that compliance with the standard had been
attained. If Capform had learned that the required inspections had not been conducted, it
would have been on notice that its reliance on the general contractor was not
well-founded. It then would have been required by the standard to take the additional
steps necessary to protect its employees--including itself hiring a competent person to
conduct inspections. Capform here, however, did not even take the minimal step of asking
the general contractor whether a competent person was inspecting the excavation after
every rainstorm.

Because Capform had a duty to know the terms of the cited
standard and because it made no attempt to protect its employees in the manner required by
the standard, Capform is unable to establish its affirmative defense. We therefore
conclude that it violated section 1926.651(d) as alleged.

II. Operation of Crane Near Excavation

The Secretary alleges that Capform violated section 1926.651(q)
by not sheet-piling, shoring, and bracing as necessary the unprotected excavation wall
next to the area where its employees worked. Section 1926.651(q) provides:

� 1926.651 Specific excavation requirements.

(q) If it is necessary to place or operate power shovels,
derricks, trucks, materials, or other heavy objects on a level above and near an
excavation, the side of the excavation shall be sheet-piled, shored, and braced as
necessary to resist the extra pressure due to such superimposed loads.

The judge vacated this item, as he had the prior one, on the
basis of his conclusion that Capform had established its affirmative multi-employer
worksite defense. The Judge also found it pertinent to observe that, although the
"movements of the crane might have been factors in the collapse of the
embankment...[the crane] was not operated by the respondent's employees."

The Secretary argues that she proved the crane was near the
unshored excavation, that Capform was using the crane to move forms, that Capform,
supervisor Pelletier knew where the crane was located, and that both Capform supervisors,
Pelletier and Hitt, knew the excavation was unshored in the area near where the crane was
operating. The Secretary also contends that Capform did not establish its multi-employer
defense because Capform knew of the violative conditions--conditions that did not require
any particular expertise to comprehend.

Capform contends that the cited standard requires the Secretary
to prove that the "hazard of extra pressure on the side of the excavation existed at
the jobsite, and that the Secretary failed to do so. Capform also contends that it
established the multi-employer worksite defense by proving that its lack of expertise in
soil-related matters deprived it of notice that the moving crane imposed extra pressure on
the unshored excavation wall.

We reject Capform's argument that the standard requires the Secretary to prove that the
crane's operation near the unshored side of the excavation created a hazard. The terms of
the standard require the Secretary only to establish that a crane was operating above and
near an excavation wall that was not sheet-piled, shored, or braced; it presumes that the
weight of the crane and the forces created by its operation can lead to the collapse of
unsupported soil. The standard does not require additional proof that the presence of the
crane created extra pressure. See H.H. Hall Construction Co., 81 OSAHRC
91/D12, 10 BNA OSHC 1042, 1047, 1981 CCH OSHD � 25,711, p. 32,056 (No. 76-4765).

We find that the Secretary has made out her prima facie case.
The 100-ton crane was operating above and as close as 30 feet from the excavation wall
that was neither sheet-piled, shored, nor braced. Also, Capform employees were exposed to
the hazard created by the crane while they worked, and particularly while they were
attaching their forms to the crane line. Further, the Secretary established that Capform
had actual knowledge of the violative condition by proving that Capform project manager
Pelletier and project superintendent Hitt knew the crane was operating above and near the
excavation wall.

Capform did not establish its multi-employer worksite defense.
The most fundamental element of the defense is that the employer did not create or control
the condition that violated the standard. Here, Capform created or controlled the
violation because the crane that was operating above and near the unshored excavation wall
was being operated in Capform's behalf, lifting Capform's formwork out of the excavation.
The fact that the crane was not operated by a Capform employee does not detract from our
conclusion that Capform created or controlled the violation. It is the use of the crane
above an unsupported wall, not the identity of its operator, that creates the hazard.

Even were we to find that Capform had neither created nor
controlled the hazard, we would still find that Capform had not proven its defense. The
defense also requires that Capform prove either (1) that it made reasonable alternative
efforts to protect its employees or (2) that it did not have, and could not have had,
notice that the violative condition was hazardous. Capform proved neither. Although it was
the responsibility of either the general contractor or the subcontractor that dug the
excavation, and not Capform's responsibility, to sheet-pile, shore, or brace the pertinent
excavation wall, Capform should at least have asked the general contractor to comply with
the standard by providing the required support for the wall that subsequently collapsed.
Capform wade no such request.

Further, Capform failed to prove that it did not have notice
that the violative condition (the unsupported excavation wall) was hazardous. Capform is
charged with notice (constructive knowledge) of the terms of the cited standard. The
standard requires that an excavation wall be sheet-piled, shored, or braced when a crane
is operating above and near that wall. Although Capform's onsite supervisors may have
lacked expertise in soil stability, they knew that a crane was operating above and near an
unsupported excavation wall. Under the specific terms of this standard, therefore, the
existence of these prohibited conditions placed Capform on notice that its employees were
exposed to a hazard. Accordingly, Capform's affirmative defense fails. We find that
Capform violated section 1926.651(q).

III. Sloping or Shoring of Excavation Wall

The Secretary's citation also alleges that Capform violated a
third safety standard, section 1926.651(c), by failing to slope or shore the excavation
wall to protect employees from the danger of moving ground. The judge vacated the
allegation on the basis of his finding that Capform had established its multi- employer
worksite defense. Section 1926.651(c) provides:

� 1926.651 Specific excavation requirements.

(c) The walls and faces of all excavations in which employees
are exposed to danger from moving ground shall be guarded by a shoring system, sloping of
the ground, or some other equivalent means.

The standard thus requires employers to guard certain
excavation walls by shoring, sloping or equivalent means. We have just concluded that
Capform violated section 1926.651(q), a standard that required Capform to sheet-pile,
shore or brace the excavation wall that partially collapsed. If Capform had complied with
section 1926.651(q) by sheet-piling, shoring, or bracing the wall, Capform would also
necessarily have been in compliance with the less stringent requirements of section
1926.651(c). We therefore vacate the section 1926.651(c) allegation because it is
duplicative of the section 1926.651(q) allegation. See Cleveland Consolidated Inc.,
13 BNA OSHC 1114, 1118, 1986-87 CCH OSHD � 27,829, p. 36,430 (No. 84-696, 1987).

We find that the affirmed violations are serious, as alleged by
the Secretary. Noncompliance with the cited standards increased the risk of cave-ins at
the excavation site, and cave-ins can, as they did here, result in death or serious
physical harm to employees.

The Secretary proposed a total penalty of $800 for violation of
the three standards contained in the citation. We find that a penalty of $800 is
appropriate even though we have affirmed only two of the items. Capform is a large
employer, with about 225 employees at the time of the citation. Its good faith is suspect
because it apparently made no efforts to comply with either of the violated standards. The
gravity of the violations is high because several employees were exposed to the hazard
presented by the unprotected, 25- to 30-feet high excavation wall over a two-week period.
We therefore assess a total penalty of $800.

Accordingly, we affirm the Secretary's citation insofar as it
alleges violations of sections 1926.651(d) and (q), and vacate the citation insofar as it
alleges a violation of section 1926.651(c). We find that the affirmed violations were
serious and assess a total penalty of $800.

FOR THE COMMISSION

RAY H. DARLING, JR.

EXECUTIVE SECRETARY

DATED: April 26, 1989

SECRETARY OF LABOR,

Complainant,

v.

CAPFORM, INC.,

Respondent.

OSHRC Docket No. 84-0556

Appearances:

For the Complainant:

Allen Reid Tilson, Esquire

Department of Labor, Dallas, Texas.

For the Respondent:

Steven R. McCown, Esquire

Dallas, Texas.

Louis G. LaVecchia, Judge:

DECISION AND ORDER

This is a Proceeding under the Occupational Safety and Health
Act of 1970 (29 U.S.C. 651 et seq. ). A citation, characterized as
"serious" in view of the violations alleged, was issued to the respondent as a
result of a fatality investigation and inspection of its worksite on February 22 and 23,
1984 by compliance officers of the Occupational Safety and Health Administration
("OSHA"). A civil penalty of $800 was proposed.

The respondent contested the citation and the matter went to
hearing on January 29 and 30, 1985 at Dallas.

The respondent stipulated that it is engaged in a business
affecting commerce and that it is an employer within the meaning of Section 3(a) of the
Act.

Post-hearing briefs and/or replies have been filed by the parties. There were no
intervenors in the action.

The Alleged Violations

1a 29 CFR 1926.651(c): The walls oor(sic) faces of excavations(s) in which employee(s)
were exposed to danger from moving ground were not guarded by a shoring system, sloping of
the ground, or some other equivalent means:

(a) Embankment wall, northwest corner of the west wing of the
building under construction.

1b 29 CFR 1926.651(d): Excavations were not inspected by a
competent person after every rainstorm or other hazard-increasing occurrence for the
purpose of increasing the protection against slides and cave-ins where necessary:

(a) Unshored embankment wall of excavation for building under
construction.

1c 29 CFR 1926.651(q): The side(s) of the excavation(s) were
not sheet-piled, shored or braced as necessary to resist the extra pressure due to
super-imposed loads:

(a) A 100-ton capacity crawler crane was position and operated
at points along and near to the excavation at grade level on the west side of the west
wing of the building under construction.

The Standards

The safety standard at 29 CFR 1926.651 provides:

Specific excavation requirements.

(c) The walls and faces of all excavations in which employees
are exposed to danger from moving ground shall be guarded by a shoring system, sloping of
the ground, or some other equivalent means.

(d) Excavations shall be inspected by a competent person after
every rainstorm or other hazard-increasing occurrence, and the protection against slides
and cave-ins shall be increased if necessary.

(q) If it is necessary to place or operate power shovels,
derricks, trucks, materials, or other heavy objects on a level above and near an
excavation, the side of the excavation shall be sheet-piled, shored, and braced as
necessary to resist the extra pressure due to such superimposed loads.

The Relevant Evidence

Henry Slagle, compliance officer with OSHA, stated that he has
been so employed for 10 years. Before that, he performed similar work for the State Health
Department. He has a degree in mechanical engineering and a graduate degree in nuclear
engineering. He has taught mathematics, including algebra and trigonometry, at the college
level. He has also had many courses in hazard recognition and abatement procedures
associated with the construction industry in general, and with soil cave-ins in
particular. On-the-job training, as an observer at times, is a part of his job activities
has conducted more than 700 inspections for OSHA. (Tr. 18-21).

He conducted an investigation of the respondent's worksite on
February 22, 1984, where a subterranean parking garage was under construction. The
respondent wag performing form installations for the pouring of concrete structures. (Tr.
22).

The respondent had 225 employees at the time of the
investigation. It was engaged in removing wooden forms from a concrete wall that had been
poured and cured. A report of a fatal accident at the jobsite had triggered the
investigation. (Tr. 23).

The jobsite embraced a city block area or more, bordered on
five sides by Dallas city streets. (Tr. 24). (Ex. C-26).

The witness made a number of photographs of the jobsite on the second day of his
investigation. (Exs. C-1 through C-24).

The embankment directly above the place where the deceased
employee was working was photographed several times.

After the accident "benching" operations were
performed with a view to stairstepping the involved excavation to prevent further
caving-off of earth. (Ex. C-5).

Exhibit C-7 shows the area where the accident occurred in the
lower left corner. The fresh red soil next to the concrete wall was that which had caved
off from above. After the caving-off the earthen wall above the accident site appears
almost vertical.

Exhibit C-10 shows, in the opinion of the witness, that the
earthen walls remaining after cave-off were obviously not sloped to 45 degrees.

Exhibit C-12 shows the wooden forms with which the deceased
workman was working at the time of the accident.

Preparations were being made by the employees for hoisting the
wooden forms from the excavation by hooking them onto the crane cable. (Tr. 43).

The yellow-colored crane shown in exhibit C-14 was the crane
that was to be used to hoist the wooden forms from the point of the accident. (Tr. 45).

Exhibit 21 shows a water pump that had been used to remove
water from the area. (Tr. 48).

An underground garage was being built at the time of the excavation. The whole area had
been dug down to the level required. At the site of the accident the bottom of the
excavation was about 25 feet from the street level above. (Tr. 52). The excavation was
large, extending several hundred feet in width, and perhaps two city blocks in length. It
had been dug to various depths, and appeared to be incomplete at the time of the
investigation. (Tr. 52-52).

Auguste Pelletier [respondent's job supervisor] told the CO
that he was on the upper level when the accident occurred. He stated that he did not see
the first batch of earth cave off, but did see the second batch as it broke away from the
top level. The crane was stationed on the asphalt surface [Yeargen Street] overlooking the
excavation where the accident occurred. (Ex. C-26).(Tr. 54). The asphalt street or
driveway was scheduled to be destroyed during the course of the construction. (Tr. 55).

Pelletier further stated that he saw a man at the bottom of the
pit when the second cave-off happened and he shouted a warning to that individual. That
workman was the victim's uncle. (Tr. 55-56).

Pelletier indicated that it was felt that the asphalt surface
of the street would help hold up the excavation wall at that point. He expressed the
opinion that the cave-offs had happened because of the presence of the crane on the street
above. (Tr. 56).

The CO's investigation revealed that there had been recent rains in the construction area.
(Tr. 56-58). He expressed the opinion that soil stability changes with moisture content.
And he stated that he could find no one who had inspected the excavation following the
rains to determine if soil stability had degraded. (Tr. 58).

The general contractor's insurance representative had inspected
the job-site at some prior time. (Tr. 59).

The post-accident benching operations were voluntary on the
part of the parties so engaged on the day after the fatality. The CO had not yet made any
abatement recommendations. (Tr. 61).

The respondent's job supervisor (Pelletier) stated that the
general contractor nor anyone else had been requested to do anything about the slope
because it was not considered a dangerous situation. (Tr. 62).

The witness felt that it was obvious from observation and the
occurrence of the accident that the side of the excavation rising above the work pit had
not been sloped to a 45-degree angle. (Tr. 63).

It appeared to the compliance officer that the walls under
which the employees were working were originally 70 to 80 degrees in slope, rather than 45
degrees. The CO alluded to his background in mathematics and his other experience as
qualifying him for estimating the degree of slope in matters of this kind. (Tr. 63-64).

The CO stated that it was obvious that none of the walls in the excavation left
free-standing were at a slope of 45 degrees or less. A normal person, assuming he can get
a foothold, can climb a 45-degree slope. He could not see a single wall in the work area
or in any of the photographs that he made at the time, that he felt he could climb. (Tr.
65).

The only precautions against moving earth hazards seen by the
CO were the shoring projects on three sides of the pit. No shoring was seen on the fourth
side, where the accident took place. (Tr. 65).

The combination of the rains, the crane movements at the top of
the pit in which the employees were working, and the vibrations caused by the movements of
the crane, added to the hazard imposed by the unshored side of the excavation. (Tr. 65).
The CO expressed the opinion that the wall in question should have been sloped at a
45-degree angle. He estimated that the angle was actually 70 to 80 degrees, in some
instances 90 degrees, and in some places there was actually an overhang. (Tr. 71-72).

In addition to the deceased employee (Martin Ramirez) and the
injured employee (Epifonio Fernandez) the respondent had other employees working in the
excavation. They numbered about 22, and were engaged in installing and removing forms for
the construction of concrete structures. They had been working in the area for two or
three days. (Tr. 90-91).

The CO took soil samples at the jobsite. (Ex. C-30). This sample was taken at the surface
of the original grade, just under the asphalt pavement, following the scraping off of the
surface by the backhoe. (Tr. 95). The soil appeared to be a sandy clay, in the opinion of
the compliance officer. (Tr. 97).

Several methods of abatement of the hazard were mentioned by
the CO. The embankment could have been sloped to an angle of repose, where it would not be
inclined to fall by its own weight, or with the imposition of other loads on top of it.
Shoring could have been done, either at the lower level or at some point above, and
sloping in combination. Or it could have been benched (stairstepped) to prevent the soil
first of all from cracking off, or secondly, not to fall the full depth to the bottom of
the pit. None of these methods had been pursued at the accident site. (Tr. 97-98).

A backhoe would be suitable for accomplishing the sloping of
the earthen wall. There was a backhoe at the jobsite. No shoring or benching had been
done. The backhoe could have done both operations. (Tr. 99).

Another technique would be the use of a "work box" or
"mule" that can be lowered into the work area. In the event of a cave-off the
worker is protected by the sides of the box from possible injury or death. (Tr. 99).

On cross-examination the CO stated that neither he nor Gerald Forrester, the other CO,
took any measurements for distance or angle at the excavation. However, he had been told
by the general contractor, Longcrier, and by the respondent's representatives that the
depth of the excavation was 25 feet. (Tr. 102).

The CO concluded that the respondent did not do any of the
excavation work, and did not create the hazard alleged. He was not aware of any
contractual responsibility on the part of any contractor. He concluded that no request was
made by the respondent to Longcrier for correction of the hazard. (Tr. 104-105).

The CO did not establish for whom the operator of the backhoe
was working when the benching operation was performed following the accident. Upon
inquiring of the respondent he was told that the operator was not a Capform employee. (Tr.
106).

The general contractor, Longcrier, told the CO that the
excavation work had been performed by a sub-contractor, Weir Brothers. (Tr. 108).

In his conversations with Pelletier the CO was told that the
former didn't think there was any problem with the embankment before the accident. (Tr.
111).

The CO also talked with Mr. Hitt, another representative of the
respondent. Hitt did not say that the embankment looked hazardous prior to the accident.

The CO stated that he had been told by Longcrier's representative that the City [Dallas]
inspected the excavation site and had required the existent shoring. Nothing had been said
about the condition of the wall [embankment].

He had also been told that the insurance company representative
had inspected the construction site. (Tr. 114).

The CO made a note in his investigation file stating that Hitt,
the project manager, and Pelletier, the job foreman, had said that the respondent did not
create the hazard; that it did not have the authority or the ability to correct it; and
that Capform, the respondent had not requested the controlling employer to correct it.
(Tr. 115).

He confirmed that the red soil shown in Exhibit 10 was the
portion of the embankment that caved off and buried the deceased employee. (Tr. 129).

In view of the configuration of the bank at the site of the
accident, the CO expressed the opinion that the caved-off portion of the bank had been an
overhang before the collapse. (Tr. 133-134).

The greatest angle of slope observed by the CO in the unshored
area of the excavation was 60 to 65 degrees. This was not the result of shoring, but
appeared to the CO to have occurred when the embankment collapsed. This flattest slope
[easiest to climb] of 60 to 65 degrees was right above the accident scene. (Tr. 138-139).

The concrete wall that the men were working on was estimated by the CO to be three to five
feet from the bottom part of the embankment. The concrete wall was about nine feet tall.
(Tr. 140).

The CO stated that he had concluded that the respondent had no
ability to correct the hazard. (Tr. 144).

The concrete wall did not extend ever the entire length of the
unshored embankment, but the CO estimated that it was 100 to 200 feet long. (Tr. 146). He
indicated that exhibits 5 and 6 showed the overhang previously mentioned. (Tr. 147).

The CO had used the concrete wall as a vertical line of
reference in estimating the 60 to 65 degree-angle of slope in the embankment. (Tr.
144-149).

Epifonio Fernandez, through an interpreter, testified that he
had a ninth-grade education, and that he and his nephew, Martin Ramirez (the deceased)
were employed by the respondent, but could not recall how long they had been so employed.
It had been a little cool before the accident, and it had rained a few days before. (Tr.
149-152).

At the time of the accident he and his nephew were attaching a
"waler" to one of the wooden forms that had been used in the construction of the
concrete wall. They were waiting for the crane to lower a line so that the hook could be
attached to the waler. The crane had moved about in the performance of various lifting
jobs on the day of the accident and on the day before. (Tr. 152-153).

The witness stated that his boss, "Pedro" had
received instructions from Pelletier designating the witness and his nephew (the deceased)
for the performance of the work involved in hooking the crane cable to the wooden forms
for removal from the pit. (Tr. 153-154).

Pelletier shouted a warning to the witness when the witness
rushed to the assistance of his nephew. The witness was then struck by falling dirt.
Pelletier had just come to the work area when the accident occurred. (Tr. 155).

The witness identified the yellow crane in Exhibit 14 as the
crane that was at the scene of the accident. (Tr. 155-156).

There was only two or three feet between the concrete wall and
the embankment in the working area, just enough space to walk in. (Tr. 157).

Many other laborers employed by the respondent and supervised
by Pedro and Pelletier had been working in the area, removing the wooden forms from the
concrete wall. (Tr. 157-158).

The witness stated that he could not walk up the slope in the
embankment as shown in Exhibit 5. Access to the working area was gained by walking down
the embankment shown in Exhibit 22. (Tr. 160).

The witness was himself injured by falling earth and
hospitalized after being pinned against the forms. (Tr. 161).

Gerald Forrester, also a compliance officer for OSHA, has been so employed since 1973. He
has attended all safety courses presented at the OSHA Institute in Chicago. Included in
the courses have been matters involving soil mechanics and the stabilization of soil
materials. (Tr. 165-166).

The witness accompanied Mr. Slagle in the investigation of the
instant jobsite. Soil samples were taken at the site of the accident. Some sloping was
observed, but this had been created by the failed materials. Where there had been no
failure, there didn't appear to be any sloping at all. (Tr. 166).

In fact, it was virtually vertical, except for the portion that
had caved off. (Tr. 167). The concrete wall running parallel to Yeargen Street appeared to
be about 60 feet long to the witness.

The upper part of the bank in question was a sandy clay, while
below that was what the witness would describe as silty sand. The silty sand would he
considered the weakest strata and a sloping of 60 to 65 degrees, going from the floor of
the excavation to the top, would be the safest angle of sloping in the circumstances. (Tr.
168-170).

Other factors present, in addition to the nature of the soil,
were the imposed load in the form of the crane, and the heavy amount of traffic in the
jobsite area. The pit was 25 to 30 feet in depth at the point where the crane was located,
above the accident site. (Tr. 171-172).

The witness was not familiar with the circumstances under which the crane had been ordered
into place at the top of the embankment or under whose control it was at the time. (Tr.
175-176).

The heavy traffic referred to by the witness in his testimony
was on the streets other than Yeargen. (Tr. 176). He stated that Yeargen appeared to be an
access to the work area, and he did see some large trucks going into that area, possibly
delivering materials to the jobsite.

Considering the nature of the soil and the angle of the bank as
it probably was before the collapse, the witness felt there should have been some measures
taken to prevent a cave-in because this was not the type of material that could be
depended on to remain in place indefinitely at that angle. (Tr. 177).

Mr. Ralph Barnes, a geotechnical engineer, dealing with
foundation engineering, studies of soil and rock and the way they react under loads, and
different types of strains, testified with respect to the subsurface report prepared by
Hooper & Associates (Ex. C-25); the photographs of the jobsite received in evidence,
and the soil sample (Ex. C-10). (Tr. 183-203).

He stated that the materials at the jobsite appeared to be
sandy clays, clayey sands, and sands. (Tr. 193). In his opinion this type of soil is
subject to moving or caving in. (Tr. 194).

The soils shown in the photographs received in evidence; those
mentioned in the soils report; and the soil sample, appeared to have been the type of soil
that caved in. (Tr. 193-194).

The witness testified that basically these soils are variable all the way from clays
through sands at the jobsite. With the exception of pure sands, they all have a degree of
strength that would enable them to stand on vertical cuts for a period of time before
caving off or sloughing off. But there is no way to evaluate the time factor, whether it
be one day or one year. (Tr. 196). On the other hand, they will definitely cave off at
some time. (Tr. 196).

Weathering of the soil, which causes cracking, can lead to
ultimate caving off or sloughing off. Changes in the weather, such rain versus sunshine,
things that tend to wet and dry the soil, speed up the process. Loads near the top of the
bank can open tension cracks, weakening the soil, and speeding up the process of caving
in. (Tr. 197).

The crane in the photographic evidence, when moving about,
could hasten the weakening process. (Tr. 197).

Heavy rains for a two-week period before the cave-in, and light
rain in the days immediately preceding the cave-in could have speeded up the fall. (Tr.
198).

Mr. Auguste Pelletier, a native of Quebec, Canada, testified
that he had been in the United States for about a year and a half. He is a supervisor for
the respondent in the construction of concrete forms. He has been in the construction
industry for 37 years, progressing from laborer to carpenter to foreman, and eventually to
supervisor. (Tr. 204-205).

During his 37 years of experience in concrete form work he has worked in and around
embankments and excavations, but he has never had the responsibility "to look
at" them. He has not performed any excavation work, and stated that he did not have
to inspect or observe the excavations to determine their condition. (Tr. 206).

The witness stated that he was aware of safety requirements for
embankments and excavations. He indicated that a 45 degree angle was supposed to be used,
and that shoring was necessary. (Tr. 206).

He was the job supervisor for the respondent at the jobsite
where the accident occurred. The respondent's job was to build forms for the pouring of
concrete structures. No work was done with reinforcement steel, nor did the respondent's
employees pour any concrete. (Tr. 207).

The excavation was about 27 to 30 feet deep at the point where
the respondent's employees were working. Twenty employees were engaged in the work. Pedro
Molina was assisting the witness as a supervisor. (Tr. 208)

The witness had been the supervisor at this jobsite for about a
month when the accident occurred. No excavation work had been done by the respondent nor
did it work on any of the embankments in the area. The embankments were shored on three
sides. There was no shoring in the area where the accident happened. With regard to the
embankments in the accident area, the witness stated "I find the slope was all right
to me." He made this determination "just by looking at it." He did not
recall seeing any cracks In the embankment near the accident site. (Tr. 209).

The witness stated that he saw no sloughing of material, nor did he see the embankment
slide or move in any way. (Tr. 210).

The employees had been working in the area for about a month,
and there had been no problem reported to him about the embankment that had failed. He
knew of no problems with any of the embankments in the area that had not been shored. (Tr.
210).

During the month prior to the accident there had been
"lots of rain, lots of rain." He saw no changes in the embankments after the
rains. (Tr. 210).

When the accident occurred the witness was just coming onto the
job-site. He "saw the dirt coming down, and that's it." He normally arrived on
the job at 3:00 a.m., or 5:00 a.m. (Tr. 211).

On the day following the accident the witness, arriving about
5:00 a.m., saw Longcrier employees sloping the bank where the collapse had occurred. The
witness had not had any discussions with any representatives of Longcrier concerning the
condition of the embankment that was not shored. He stated that Longcrier had its own
"safety guide" and that he was not concerned at all prior to the accident that
the embankment was hazardous. (Tr. 211-212).

The witness identified the yellow crane in exhibit C-15 as the
one that had been on the surface above the accident site before the accident occurred. He
indicated that it had moved about on that surface, but that it had not moved when in close
proximity to the accident site. (Tr. 215-216).

The witness completed the 12th grade in Canada, but has had no other formal education. He
had no courses in mathematics. (Tr. 216).

He knew that the respondent's employees were working below the
unshored embankment. (Tr. 217).

Mr. Curt Hitt, Project Manager for the respondent, has been so
employed for 5 years. (Tr. 219). The respondent was engaged in wall form work at the
construction site. The general contractor at the site was Longcrier. Capform does no
excavation work; no shoring activities; no steel operations; and does not own or have any
type of earth-moving equipment. It was employed only to do concrete form work at the
construction site. (Tr. 219-221).

The witness stated that the exposed embankment was sloped to
some degree along its full length. He assumed that the unshored embankment was adequate,
in view of the fact that the other three sides of the site had been shored. (Tr. 222). He
saw no indications of possible sloughing off of bank material on the unshored embankment.
(Tr. 223). Neither of the two pieces of machinery shown in Exhibit C-15 belonged to or
were leased by Capform. (Tr. 224). He assumed that the equipment was owned by the general
contractor. The equipment was not operated by the respondent's employees. (Tr. 224).

It had rained during the month or so that the respondent had
been engaged in form work at the excavation, but the witness saw no signs of deterioration
in the unshored embankment. (Tr. 225). He had observed the slope of the embankment before
the accident, and that it was adequate. (Tr. 226). However, he had not checked the sloping
in assuming that it was adequate. (Tr. 226).

The witness stated that he knew that the respondent's employees were going to be working
at the bottom of the slope. (Tr. 226).

Mr. Clyde Enright, an employee of the Longcrier Company, stated
that he was employed at the excavation site. (Tr. 227). He was not approached by the
respondent's representatives with any complaints about the unshored embankments. Nor was
there any complaint registered with respect to any lack of sloping. (Tr. 228-229).

Epifonio Fernandez was recalled by the complainant and asked
whether the crane shown in Exhibit C-15 had been working over the site where the accident
occurred. He replied that "it was there." (Tr. 231).

Henry Slagle was recalled by the complainant and asked about
the conversation he had with Gus Pelletier about the crane. He stated that Pelletier
expressed the opinion that the crane had helped to cause the cave-off. He further
indicated to the CO that the asphalt paving could have or should have helped hold the
embankment from collapsing. (Tr. 234).

Discussion

Multi-employer construction sites have been the subject of many
decisions by the Review Commission, which has applied the rules set forth in Anning-Johnson
Co., 76 OSAHRC 54/A2, 4 BNA 1193, 1975-76 CCH OSHD � 20,690 (Nos. 3694 & 4409),
and Grossman Steel & Aluminum Corp. , 76 OSAHRC 54/D9, 4 BNA OSHC 1185, 1975-76
CCH OSHD � 20,691 (No. 12775, 1976), in determining whether a subcontractor can be held
to have violated the Act in the circumstances present in that particular case.

The significant language in Anning-Johnson reads:

We... recognize... the availability to an employer of certain
affirmative defenses... [A]n employer ... has an opportunity to demonstrate that it did
not create the alleged hazard nor did it control the hazard such that it realistically had
the means to rectify the condition...

Once a cited construction subcontractor has established that it
neither created nor controlled the hazardous condition, it may affirmatively defend
against the Secretary's charge by showing either (a) that its employees who were or may
have been exposed to the hazard were protected by means of realistic measures taken as an
alternative to literal compliance with the cited standard, or (b) that it did not have nor
with the exercise of reasonable diligence could have had notice that the condition was
hazardous.

Hence, if the respondent neither created nor controlled the
hazardous condition the remaining question is whether it had or with the exercise of
reasonable diligence could have had notice that the condition was hazardous.

It is undisputed that the respondent did not create the hazardous condition of the
embankment. It is likewise quite clear that the respondent did not control the hazard
because it lacked the authority or equipment to abate or correct the hazardous condition.

The respondent's project manager did not have an educational
background in soil mechanics, nor sufficient experience in the recognition of soil
degeneration in the embankment to be apprised of the hazardous condition of the embankment
at the site of the accident. He appears to have been justified in assuming that the
shoring of three sides of the excavation indicated that the unshored portion of the pit
was found to be safe by the general contractor's safety representative, as well as the
insurance company representative and the Dallas city inspector's tacit approval.

Neither can it be said that the respondent's job foreman, with
no experience in the excavation trades, and an education totally lacking in mathematics of
any kind, knew or should have known that the embankment was in a hazardous condition. He
saw nothing alarming in the angle of sloping of the embankment before the accident
occurred. The precise angle of sloping prior to the accident will never be Known since a
considerable portion of the embankment ended up at the bottom of the pit after the
collapse of the soil. Thus, it would be pure speculation to assume that common sense
should have warned the foreman that the bank was in a hazardous condition thereby
constituting a danger to the employees he assigned to perform the form work in the pit.

Findings

All of the evidence, including the testimony, demeanor, and credibility of the witnesses,
and the photographic, graphic, and documentary evidence, has been evaluated in the light
of the briefs of law and argument submitted by the parties. The following findings of fact
are made:

  1. The respondent, Capform, was engaged on February 22, 1984,
    as a subcontractor for the performance of concrete form work at a large building
    construction site in Dallas, Texas.

  2. The construction site embraced an area of one or more city
    blocks which had been excavated to a depth of 25 to 30 feet by another subcontractor
    (Weir) under the direction of the general contractor, Longcrier Construction Co.

  3. The respondent did not participate in the excavation
    activity, but was engaged at a later time by the general contractor for the performance of
    concrete form work at the bottom of the excavation.

  4. The respondent does not operate any excavation equipment or
    machinery; nor does it operate cranes or other lifting equipment.

  5. Since three sides of the excavation had been shored against
    the possibility of collapse, the respondent assumed that embankment left unshored was
    considered safe from possible collapsing of the soil.

  6. The excavation site had been inspected by a Dallas city
    inspector and by the general contractor's insurance company with no known disapproval.

  7. On February 22. 1984 the unshored embankment collapsed at a point directly above two of
    the respondent's employees, preparing to extract concrete forms from a wall that had been
    constructed on the floor of the excavation resulting in the death of one man and injuries
    to the other.

  8. A heavy-duty crane (100-ton capacity) was stationed an the
    pavement of the street above the accident site, apparently for use in removing the
    concrete forms from the pit below. The movements of the crane might have been factors in
    the collapse of the embankment, but it was not operated by the respondent's employees. The
    street (Yeargen) was not heavily traveled by general traffic.

  9. The angle of sloping of the collapsed embankment, viewed
    after the accident, appeared to be 60 to 83 degrees.

  10. The respondent's job foreman, with a limited education and
    command of the English language, lacked any expertise in soil mechanics or engineering,
    and failed to notice anything about the condition of the embankment before the fall which
    might have indicated that a collapse of earth might occur while the men were working
    below.

  11. The respondent's project manager, also lacking in expertise
    with respect to soil mechanics, did not notice anything in the condition of the embankment
    to indicate that a hazardous condition was present.

  12. Although it had rained from time to time in the or so
    before the accident, the respondent's supervisory personnel did not have sufficient
    knowledge in such matters as to be able to conclude that the embankment might collapse.

  13. The respondent did not create the hazardous condition, nor did it control the hazard.

  14. The respondent did not have nor with the exercise of
    reasonable diligence could have had notice that the condition of the embankment was
    hazardous.

In view of the findings above I conclude that the respondent did not violate either of the
three safety standards set forth in the citation. The citation will be vacated.

Conclusions of Law

  1. The Review Commission has jurisdiction of this proceeding
    and the parties.

  2. The respondent did not violate the safety standards set
    forth at 29 CFR 1926.651 (c), (d), and (q).

Order

The citation is vacated.

So ORDERED.

Louis G. LaVecchia

Administrative Law Judge

August 14, 1985

Dallas,

SECRETARY OF LABOR,

Complainant,

v.

CAPFORM, INC.,

Respondent.

OSHRC DOCKET NO. 84-0556

Pursuant to the provisions of Section 556 of the Administrative
Procedures Act (5 U.S.C. 556), the undersigned hereby certifies to the Occupational Safety
and Health Review Commission the record in this proceeding, consisting of the following:

  1. Those documents forwarded to the undersigned by notice dated
    July 27, 1984, from the Commission;

  2. All documents issued by or filed with the undersigned in
    this matter numbered J-1 through J-22;

  3. The original and three copies of the transcript of hearing,
    the original totaling 236 pages;

  4. All exhibits received into evidence; and

  5. The undersigned's decision and order in this matter dated
    August 14, 1985.

LOUIS G. LAVECCHIA

Administrative Law Judge

Dated: August 14, 1985

FOOTNOTES:

[[1/]] Capform also argues that the cited standard requires the
Secretary to prove that the hazard of cave-ins "was increased in the unshored
embankment at the jobsite after a rainstorm" (emphasis supplied), and that the
Secretary failed to do so. We reject this contention. The standard very clearly intends
that rainstorms be considered hazard-increasing occurrences unless and until an inspection
by a competent person establishes otherwise, and it only requires proof that rainstorms
had occurred. Capform does not dispute that rainstorms had occurred at the jobsite while
its employees worked there.

Get today's answer for your situation

You just read Commission precedent from 1989. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.