OSHRC Commission decision Docket 78-1361, 78-2041 Decided September 30, 1981 Procedural

Pittsburgh Forging Company

Dockets severed and one judge decision affirmed

Apply this precedent to your situation

This is citable Commission precedent from 1981, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1981
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

The Commission severed dockets 78-1361 and 78-2041. It affirmed the administrative law judge's decision in docket 78-2041 and gave that ruling the precedential value of an unreviewed judge's decision. Docket 78-1361 remained under Commission review. The short order does not identify the underlying citations, standards, or penalties.

Decision snapshot

  • Cited standard(s): None identified in the Commission order.
  • Outcome: Dockets severed; judge's decision in 78-2041 affirmed; 78-1361 remained on review.
  • Key point: Severance allowed one docket to become final while Commission review continued in the other.

Full text (OSHRC public release)

Docket Nos. 78-1361; 78-2041

PITTSBURGH FORGING COMPANY

OSHRC Docket Nos. 78-1361; 78-2041

Occupational Safety and Health Review Commission

September 30, 1981

COUNSEL:


[*1]

Office of the Solicitor, USDOL

Marshall H. Harris, Reg. Sol., USDOL

W. Scott Railton, for the employer

George Prenatt, Staff Rep., Safety & Health Dept. - USWA, for the employees

OPINION:

ORDER OF SEVERANCE

Upon our own motion it is ordered that Docket Nos. 78-1361 and 78-2041 are hereby severed pursuant to Rule 10 of the Commission's Rules of Procedure, 29 C.F.R. �

2200.10.

The administrative law judge's decision in Docket No. 78-2041 is affirmed.

It is accorded the precedential value of an unreviewed judge's decision.

See Leone Construction Co., 76 OSAHRC 12/E6, 3 BNA OSHC 1979, 1975-76 CCH OSHD P20,387 (No. 4090, 1976).

Docket No. 78-1361 remains on review.