Arc Erecting, Inc.
Access, crane, and welding citations affirmed
Apply this to your situation
This order from 2013 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
Arc Erecting was the structural steel subcontractor on a Maine arena project. Employees climbed to the top of steel joists about 10 feet above the ground without a ladder, and a crane operated near a power line without the required marked work-zone boundary and elevated warning line. A welder also worked without a practicable arc screen protecting a nearby worker and without knowing the location of the nearest fire extinguisher, which was about 60 feet away. The judge rejected the company's challenge to OSHA's programmed inspection because the general contractor consented and the site selection followed OSHA's neutral scheduling plan. The ladder and crane items were serious, while the two welding items were other than serious. All four items were affirmed, with total penalties of $2,750.
Decision snapshot
- Cited standard(s): 29 C.F.R. § 1926.1051(a); 29 C.F.R. § 1926.1408(a)(2); 29 C.F.R. § 1926.351(e); 29 C.F.R. § 1926.352(d)
- Outcome: All four citation items were affirmed, with total penalties of $2,750.
- Key point: An existing landmark does not demarcate a crane work-zone boundary unless it is marked as the regulation requires.
Full text (OSHRC public release)
United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington, D.C. 20036-3457
SECRETARY OF LABOR,
Complainant,
v.
ARC ERECTING, INCORPORATED, OSHRC DOCKET No. 12-1592
Respondent,
and
IRON WORKERS DISTRICT COUNSEL
OF NEW ENGLAND, LMCT SAFETY
DEPT.,
Authorized Employee
Representative.
APPEARANCES:
James L. Polianitis, Jr., Esquire, U.S. Department of Labor
Boston, Massachusetts
For the Complainant.
Jeff Mitchell
Brewer, Maine
For the Respondent, pro se.
Patrick McDermott
South Boston, Massachusetts
For the Authorized Employee Representative.
BEFORE: William S. Coleman
Administrative Law Judge
DECISION AND ORDER
Background
This matter arose following the programmed inspection on April 5, 2012, in
Bangor, Maine, of the Bangor City Arena construction project. The Respondent, Arc
Erecting Incorporated, was on site at the time performing work as the structural steel
subcontractor.
A compliance safety and health officer (CO) from the Bangor area office of the
Occupational Safety and Health Administration (OSHA) conducted the inspection.
During the inspection, the CO observed a crane that was controlled by the Respondent
operating in close proximity to an overhead power line. The CO also observed
Respondent’s employees preparing to offload two steel joists from a flatbed trailer by
accessing the top surface of the joists without the use of a ladder or stairway. In addition,
the CO observed one of the Respondent’s employees engaged in arc welding without
using a protective screen, and also without having a fire extinguisher within his
immediate reach.
After the inspection, on June 19, 2012, OSHA issued a citation (Citation) to the
Respondent alleging two “serious” and two “other than serious” (“other”) violations of
certain OSHA construction standards contained in 29 C.F.R. Part 1926, which were
promulgated pursuant to the Occupational Safety and Health Act of 1970, 29 U.S.C. §§
651-678 (the Act). 1
Citation 1, Item 1, alleged a serious violation of 29 C.F.R. § 1926.1051(a), which
requires that a “stairway or ladder … be provided at all personnel points of access where
1
As a result of the inspection, OSHA also issued a single-item citation to the
project’s general contractor. (Ex. D).
2
there is a break in elevation of 19 inches.” The alleged violation occurred when the
Respondent’s employees accessed the top surface of the steel joists without the use of a
ladder or stairway. The Citation proposed a penalty of $2,200 for this item.
Citation 1, Item 2, alleged a serious violation of 29 C.F.R. § 1926.1408(a)(2), which
requires an employer to take certain measures if crane equipment (or its load) could get
closer than 20 feet to a power line while operating up to its maximum working radius in the
defined work zone. The alleged violation occurred because no elevated warning line had
been erected and maintained during crane hoisting operations. The Citation proposed a
penalty of $2,200 for this item.
Citation 2, Item 1, alleged an “other” violation of 29 C.F.R. § 1926.351(e), which
states as follows: “Shielding. Whenever practicable, all arc welding and cutting operations
shall be shielded by noncombustible or flameproof screens which will protect employees and
other persons working in the vicinity from the direct rays of the arc.” The alleged violation
occurred when the Respondent’s employee was engaged in arc welding activity at the site
without using any protective screen.
Citation 2, Item 2, alleged a violation of 29 C.F.R. § 1926.352(d), which states as
follows: “Suitable fire extinguishing equipment shall be immediately available in the work
area and shall be maintained in a state of readiness for instant use.” The alleged violation
occurred when the Respondent’s employee was engaged in arc welding and the nearest fire
extinguisher was about 60 feet away from him.
The Citation proposed no penalty for either of the alleged “other” violations.
The Respondent timely contested the Citation. Thereafter, the Iron Workers District
Counsel of New England (Union) elected party status as the authorized employee
representative.
3
The hearing was conducted in Boston, Massachusetts, on January 15, 2013. Post-
hearing briefs were filed on April 5, 2013. 2
This matter having been designated for Simplified Proceedings pursuant to
Commission Rule 203, 29 C.F.R. § 2200.203, the issues for hearing were defined by the
parties’ joint prehearing statement. The Respondent denies all the alleged violations and
asserts affirmative defenses. It also seeks dismissal of the Citation on the ground that the
selection of the project for the programmed inspection was contrary to OSHA’s general
administrative plan for random programmed inspections of construction sites, as set out
in OSHA Instruction CPL-02-00-141, Inspection Scheduling for Construction (July 14,
2006). (Ex. B).
As set out below, a preponderance of the evidence establishes that the Respondent
violated the cited standards in the manners alleged. Moreover, the Respondent’s
affirmative defenses and the matter asserted in avoidance are not meritorious. All the
citation items are affirmed, and an aggregated penalty of $2,750 is assessed.
Jurisdiction
The Respondent timely filed a notice of intent to contest the Citation. The
Commission has jurisdiction over the matter pursuant to § 10(c) of the Act, 29 U.S.C. §
659(c).
The Respondent is a Maine corporation with an office and place of business in
Brewer, Maine, and at any given time employs between five and twenty employees. (Ex.
1; Tr. 161, 174). On April 5, 2012, the Respondent was working as the steel erection
subcontractor on the Bangor City Arena project in Bangor, Maine. At all times relevant
2
The Union has advocated in support of the Respondent’s positions throughout the
proceedings, to include filing a post-hearing brief. The Respondent relies on the Union’s
brief and has chosen not to file a brief in its own right.
4
to this matter, the Respondent was engaged in construction work, which is a class of
activity that as a whole affects interstate commerce. Clarence M. Jones, 11 BNA OSHC
1529, 1531 (No. 77-3676, 1983). The Respondent therefore was an “employer” engaged
in a business affecting commerce with employees as defined in § 3(5) of the Act, 29
U.S.C. § 652(5).
The Union is a proper party to these proceedings pursuant to § 10(c) of the Act
and Commission Rule 20(a), 29 C.F.R. § 2200.20(a).
Discussion
Respondent’s Challenge to Scheduling of the Inspection
The Respondent’s threshold contention is that the Citation should be dismissed
because OSHA scheduled the inspection contrary to the protocol set forth in OSHA
Instruction CPL-02-00-141, Inspection Scheduling for Construction (July 14, 2006) (Ex.
B) (hereinafter “Scheduling Instruction”). 3 This argument is treated as a contention that
the inspection violated the Respondent’s Fourth Amendment protection against
unreasonable searches on the ground that the inspection was not supported by
“administrative probable cause.” Evidence obtained in violation of an employer’s Fourth
Amendment protections is subject to potential exclusion from evidence. See Sanders
Lead Co., 15 BNA OSHC 1640, 1650-51 (No. 87-260, 1992).
Section 8(a) of the Act authorizes OSHA to enter “without delay and at
reasonable times any factory, plant, establishment, construction site, or other area” for the
purposes of inspection and investigation. 29 U.S.C. § 657(a). If an employer refuses to
consent to an inspection, the inspection may be compelled by issuance of a judicial
3
The Respondent also relies on OSHA Instruction CPL-02-00-148, Field Operations
Manual Chap. 2.VI.B. (Nov. 9, 2009), which expressly references the Scheduling
Instruction. (Ex. A).
5
warrant. A judicial warrant may be issued upon a showing of administrative probable
cause, which may be established by “showing that a specific business has been chosen for
an OSHA search on the basis of a general administrative plan for the enforcement of the
Act derived from neutral sources.” Marshall v. Barlow's, Inc., 436 U.S. 307, 321 (1978).
The Scheduling Instruction constitutes OSHA’s “general administrative plan” for
conducting random programmed inspections of construction sites. See Ex. B, ¶ VII.B
(indicating that the selection system was designed “to comply with court decisions on
OSHA’s process of selecting worksites for inspection”). In accordance with the
Scheduling Instruction protocol, each month OSHA area offices are provided with “a
randomly selected list of construction projects from all known covered active projects”
that the area office must inspect the following month. (Ex. B, ¶ VII.A.). These monthly
lists of projects to be inspected were referred to at the hearing as “Dodge reports.” 4
The Dodge report for the month of April 2012 identified the Bangor City Arena
project for inspection. (Tr. 147). Subject to limited exceptions not applicable here, the
Scheduling Instruction required the Bangor area office to inspect the construction site
sometime during the month of April 2012. (Ex. B, ¶ X.C.1; Tr. 143, 147). The director
of the Bangor area office determined to dispatch a CO to inspect the site early in the
month, on April 5, rather than later, because of the relatively large size of the project, and
also because of the swift progress of the construction since the time of OSHA’s previous
4
The universe of active construction projects is derived from a commercially
published list that is compiled by an organization known as F. W. Dodge. (Ex. B, ¶ VII.)
The monthly list of construction projects to be inspected by a particular area office is
generated by a computerized system that is administered by the University of Tennessee
under contract with OSHA. (Exs. A & B; Tr. 128, 153).
6
programmed inspection of the site, which had been conducted on December 13, 2011.
(Tr. 131, 144-51).
The Respondent contends that the Scheduling Instruction prohibits OSHA from
conducting randomized inspections of any particular construction project at intervals of
less than four months between inspections. The Respondent bases this contention on
paragraph X.D. of the Scheduling Instruction (Ex. B), which provides as follows:
Limitation on Frequency of Selection. Normally, no site will be
selected for inspection more frequently than once per trimester.
Therefore, any project selected for an inspection will be removed from the
master file for a period of four months and reentered in the fifth month if it
is still active.
As noted above, the Bangor City Arena project had been previously identified for
inspection by the Dodge report for December 2011, and consequently the Bangor area
office had inspected the site on December 13, 2011. (Ex. E; Tr. 145). The inspection on
April 5, 2012, was conducted slightly less than four months after the inspection on
December 13, 2011. (Tr. 132). The Respondent argues that this contravened the
provision quoted above and that as a consequence the Citation should be dismissed.
This contention fails for at least two reasons. First, the CO had consent to
conduct the inspection. The Commission ruled in Cody-Zeigler, Inc., 19 BNA OSHC
1410, 1412 (No. 99-0912, 2001) (consolidated), that consent to an inspection precludes a
challenge under § 8(a) to OSHA's selection of a particular worksite for inspection:
Cody-Zeigler argues that a challenge to OSHA's selection of a particular
worksite for inspection is cognizable under section 8(a), but its consent to
the inspections in each of these cases makes it unnecessary to address that
issue here. For as the Commission held in Adams Steel Erection, Inc., 13
BNA OSHC 1073, 1079 … (No. 77-3804, 1987), “section 8(a) of the Act
does not require the Secretary to obtain evidence of any particular sort to
support his decision to seek a consensual inspection.” Cody-Zeigler's
7
consent extinguishes any challenge it might otherwise have been able to
make here.
The CO here conducted the inspection with the consent of the project’s general
contractor, which had authority and control over the site, and whose representative
accompanied the CO throughout the inspection. (Ex. 1, p. 2; Tr. 26-27). There is no
evidence or contention that the Respondent sought to refuse consent at any time during
the inspection. (Tr. 176; Ex. 1, p. 2). But even if the Respondent had attempted to do so,
such an effort would not have negated the consent given by the general contractor. “If
there has been valid consent [to inspect] by a third party with common authority over the
premises, that consent is not negated by the objections of an employer against whom
evidence is found.” Laforge & Budd Const. Co., Inc., 16 BNA OSHC 2002, 2005 (No.
91–2264, 1994) (finding that consent given by two parties having joint access to or
control of multi-employer worksite rendered warrantless inspection consensual as to
subcontractor who had refused consent); see also Adams Steel Erection, Inc., 13 BNA
OSHC 1073, 1078 (No. 77-3804, 1987) (finding subcontractor consented to warrantless
inspection at multi-employer construction site where its foreman had joined the
inspection party and there was no evidence that subcontractor objected to the warrantless
inspection or requested that OSHA obtain an inspection warrant).
Secondly, the overwhelming evidence establishes that the selection of the Bangor
City Arena site for inspection on April 5, 2012, was consistent with the Scheduling
Instruction and was thus supported by administrative probable cause. In stating that
“[n]ormally, no site will be selected for inspection more frequently than once per
trimester” (emphasis supplied), the Scheduling Instruction does not establish an
unyielding standard but rather simply describes the norm for inspection frequency. (Tr.
8
145-47). The area director’s testimony regarding his decision to send a CO to inspect the
site on April 5, 2012 was cogent, convincing, and uncontroverted. (Tr. 144-54). The
selection of the Bangor Arena site for inspection slightly less than four months after the
previous programmed inspection of that site was reasonable and consistent with the
protocol set out in the Scheduling Instruction. The selection of the site was thus
supported by administrative probable cause that would have supported the issuance of a
judicial warrant if consent to the inspection had been refused.
The Secretary’s Burden of Proof
To prove a violation of an OSHA standard, the Secretary must show by a
preponderance of the evidence that: (1) the cited standard applies; (2) its terms were not
met; (3) employees had access to the violative condition; and (4) the employer either
knew or could have known with the exercise of reasonable diligence of the violation.
Astra Pharm. Prod., Inc., 9 BNA OSHC 2126, 2129 (No. 78-6247, 1981), aff’d in
relevant part, 681 F.2d 69 (1st Cir. 1982).
A violation is “serious” if there was a substantial probability that death or serious
physical harm could result from the violative condition. 29 U.S.C. § 666(k). If the
possible injury addressed by a regulation is death or serious physical harm, a violation of
the regulation is serious. Mosser Constr., 23 BNA OSHC 1044, 1046 (No. 08-0631,
2010); Dec-Tam Corp., 15 BNA OSHC 2072, 2077 (No. 88-0523, 1993). “This does not
mean that the occurrence of an accident must be a substantially probable result of the
violative condition but, rather, that a serious injury is the likely result if an accident does
occur.” Oberdorfer Indus. Inc., 20 BNA OSHC 1321, 1330-31, (No. 97-0469, 2003)
(consolidated) (citation omitted).
9
An “other” violation “is one in which there is a direct and immediate relationship
between the violative condition and occupational safety and health but not of such
relationship that a resultant injury or illness is death or serious physical harm.” Crescent
Wharf & Warehouse Co., 1 BNA OSHC 1219, 1222 (No. 1, 1973).
Citation 1, Item 1 – 29 C.F.R. § 1926.1051(a)
The Respondent’s employees were engaged in offloading two steel joists that had
been delivered to the site on a flatbed trailer. The trailer’s flatbed was about four feet
high. The joists were about six feet wide, and were resting on the trailer on their sides, so
that the top horizontal surface of the joists was about six feet higher than the bed of the
trailer and about ten feet above ground level. The CO observed employees of the
Respondent climb to the top surface of the joists without the use of a ladder or stairway.
The CO brought this activity to the attention of the Respondent’s foreman, who then had
an extension ladder placed on the ground for access to the top surface of the joists. (Tr.
45-49; Ex. 3, photos 3 through 12).
This item alleges a serious violation of 29 C.F.R. § 1926.1051(a). The citation
describes the alleged violation, as set out below:
29 CFR 1926.1051(a): (a) A stairway or ladder shall be provided at all
personnel points of access where there is a break in elevation of 19 inches
(48 cm) or more, and no ramp, runway, sloped embankment, or personnel
hoist is provided.
Bangor City Arena – A stairway or ladder was not utilized by employees
to access the load of steel joists 10 feet above ground.
The cited standard “applies to all stairways and ladders used in construction …
covered under 29 CFR part 1926, and also sets forth, in specified circumstances, when
ladders and stairways are required to be provided.” 29 C.F.R. § 1926.1050(a). The
Respondent contends that a standard contained in Subpart R of Part 1926, which is
10
specific to the protection of employees engaged in steel erection, preempts the more
generally applicable cited standard. Section 1926.760(a)(1) of Subpart R does not require
the use of fall protection measures for unprotected sides and edges that are no more than
15 feet higher than the next lower level. 5
This argument is rejected. The provisions of 29 C.F.R. § 1910.5(c) address the
circumstances in which a specifically applicable standard is deemed to preempt a
generally applicable standard, and provides as follows:
(1) If a particular standard is specifically applicable to a condition,
practice, means, method, operation, or process, it shall prevail over any
different general standard which might otherwise be applicable to the
same condition, practice, means, method, operation, or process....
(2) On the other hand, any standard shall apply according to its terms to
any employment and place of employment in any industry, even though
particular standards are also prescribed for the industry, as in Subpart B or
Subpart R of this part, to the extent that none of such particular standards
applies....
The Commission has articulated the following test for determining when a
specific standard preempts a general standard under § 1910.5(c)(1): “[W]hen application
of the general standard would defeat a rulemaking decision made by the Secretary in
promulgating the specific standard, … the general standard is preempted under the terms
of section 1910.5(c)(1).” Lowe Constr. Co., 13 BNA OSHC 2182, 2183 (No. 85–1388,
1989). The Commission has also stated that a “general standard is not preempted by a
specific standard when it provides meaningful protection to employees beyond that
5
Section 1926.760(a)(1) provides as follows:
Except as provided by paragraph (a)(3) of this section, each employee
engaged in a steel erection activity who is on a walking/working surface
with an unprotected side or edge more than 15 feet (4.6 m) above a lower
level shall be protected from fall hazards by guardrail systems, safety net
systems, personal fall arrest systems, positioning device systems or fall
restraint systems.
11
afforded by the more specific standard.” Cincinnati Gas & Elec. Co., 21 BNA OSHC
1057, 1058 (No. 01-0711, 2005).
The general standard (§ 1926.1051(a)) specifies the means by which construction
workers traverse a break in elevation between work areas. The specific standard (§
1926.760(a)(1)) prescribes when certain fall protection measures are required for steel
erection workers – it does not specify the means by which those workers traverse a break
in elevation between working surfaces. Because the specific standard does not apply to
the means specified by the general standard, it does not preempt the general standard. 6
29 C.F.R. § 1910.5(c)(2). Moreover, the general standard is not preempted because it
provides meaningful protection to employees beyond that afforded by the specific
standard. Cincinnati Gas. Section 1926.1051(a) applies to the cited activity of the
Respondent’s employees accessing the top surface of the steel joists.
The Respondent points to another interpretative letter in which OSHA concluded
that § 1926.1051(a) was applicable to employee access to flatbed trailers, but which also
announced that OSHA had “determined, as a matter of enforcement direction, that it will
6
OSHA reached the same conclusion in a 1992 interpretive letter wherein it stated,
“all of Subpart X--Stairways and Ladders applies to steel erectors as well as to all other
trades at construction sites.” The interpretative letter explained this view as follows:
The standard [29 C.F.R. § 1926.1051(a)] is intended to require a ladder or
stairway between levels in at least one location between levels so that
employees can change levels in an easy, safe, and convenient manner. The
obvious reason is to allow access to different elevations in a way that
minimizes the potential for fall injuries that can result when employees are
otherwise required to climb on items (i.e. columns, cross-bracing on
scaffolds) not properly designed for climbing.
This July 20, 1992, letter of interpretation can be found at the following URL:
www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=INTERPRETATIONS&p
_id=20753
12
not apply the standard to that situation.” 7 The Respondent contends the citation for
violation of § 1926.1051(a) contravenes this enforcement policy because its employees
were climbing four feet onto the flatbed trailer (without the use of a stairway or ladder)
before they climbed an additional six feet to the top surface of the joists. This argument
fails because the Respondent was not cited for failing to provide a stairway or ladder for
access to the flatbed trailer, but rather for failing to provide a stairway or ladder for
access to the top surface of the steel joists that were resting on the trailer. The CO
testified that the Respondent fully abated the violation when it placed an extension ladder
on the ground to enable workers to access the top surface of the joists. (Tr. 45-47; Ex. 3,
photo 11). The Respondent did not meet the requirements of the cited standard.
The Respondent’s employees had access to the violative condition. The CO
observed the employees climbing up and down the steel joists without the use of a
stairway or ladder. (Tr. 47-48; Ex. 3, photograph #9).
The Respondent’s foreman was assisting in the activity and knew employees were
accessing and exiting the top surface of the joists without the use of a stairway or ladder.
(Tr. 49; Ex. 2, p. 2). The actual knowledge of supervisors and foremen is generally
imputable to the employer. Rawson Contractors Inc., 20 BNA OSHC 1078, 1080-81
(No. 99-0018, 2003); A.P. O’Horo Co., 14 BNA OSHC 2004, 2007 (No. 85-369, 1991).
The Secretary has established the alleged violation. He has also established the
violation was serious. The standard is intended to minimize the potential for fall injuries
when employees are required to move from one level to another. See footnote 6. Serious
injury or death could have resulted if an employee had fallen after losing his footing or
7
This interpretative letter dated August 12, 1997, was received in evidence as
Respondent’s Exhibit O.
13
grip. (Tr. 48-49; Ex. 2, p. 2). This item was properly classified as serious because such a
fall could result in death or serious injury. 29 U.S.C. § 666(k). Item 1 is affirmed.
Citation 1, Item 2 – 29 C.F.R. § 1926.1408(a)(2)
The Respondent controlled the operation of a Manitowoc 4000W crane that was
set up on the north side of the site. This side of the site was bounded by a city street
along which ran a 12.5 kV power line. (Tr. 28, 175-77). The utility poles supporting the
power line were situated on the site itself, inside the temporary fencing that was erected
on the boundary. (Ex. 3, photo 13). The crane’s centerline was about 120 feet from the
nearest point of the power line. (Ex. R). The crane was set up so that its maximum
working radius was 160 feet, which would have enabled it to operate beyond the power
line. (Tr. 56).
The Respondent’s president, Jeff Mitchell, testified that during a “pre-meeting”
with personnel involved in the crane operations, everyone understood the crane would
not be operated beyond an existing “concrete knee wall” that ran on an axis parallel to,
and about 27 feet distant from, the power line. 8 (Tr. 164). The plan was for the crane to
lift each joist off the trailer and then swing the joist 180 degrees with the load passing
between the crane and the power line. (Ex. Q). No elevated warning line, barricade, or
line of signs equipped with flags or similar high visibility markings had been erected and
maintained 20 feet from the power line. (Tr. 31-32; Ex. 3, photo 13).
Item 2 of citation 1 alleges a serious violation of 29 C.F.R. § 1926.1408(a)(2).
The citation describes the alleged violation as set out below:
29 CFR 1926.1408(a)(2): Determine if any part of the equipment, load
line or load (including rigging and lifting accessories), if operated up to
8
The concrete knee wall is referred to elsewhere in the record as “the loading dock
foundation wall.” (Exs. Q and R).
14
the equipment's maximum working radius in the work zone, could get
closer than 20 feet to a power line. If so, the employer must meet the
requirements in Option (1), Option (2), or Option (3) of this section, as
follows:
Bangor City Arena – The maximum working radius of the Manitowoc
crane equipment could get closer than 20 feet to a power line and the
requirements of Option (1), Option (2), or Option (3) were not followed.
Abatement can be achieved by erecting and maintaining an elevated
warning line.
The cited standard applies to the Respondent’s operation of the crane. A
provision in Subpart R of Part 1926 expressly provides that almost all the provisions of
Subpart CC, “Cranes and Derricks in Construction,” in which § 1926.1408 is contained,
apply to hoisting and rigging in steel erection activities. 29 C.F.R. § 1926.753(a).
Section 1926.1408(a) establishes a two-step process for determining the necessary
precautions to prevent contact with power lines. A summary of this two-step process is
described in the preamble to the final rule as follows:
[T]he standard requires the implementation of a systematic approach to
power line safety for crane/derrick operations. This approach consists of
two basic steps. First, the employer must identify the work zone, assess it
for power lines, and determine how close the crane could get to them. The
employer has the option of doing this assessment for the area 360 degrees
around the crane or for a more limited, demarcated area. Second, if the
assessment shows that the crane could get closer than a trigger distance —
20 feet for lines rated up to 350 kV — then requirements for additional
action are triggered.
Cranes and Derricks in Construction, 75 Fed. Reg. 47906, 47952 (Aug. 9, 2010)
(to be codified at 29 C.F.R. pt. 1926).
Section 1926.1408(a)(1) sets out step one (identify the work zone) of the two-step
process as follows:
§ 1926.1408 Power line safety (up to 350 kV)—equipment
operations.
(a) Hazard assessments and precautions inside the work zone.
Before beginning equipment operations, the employer must:
15
(1) Identify the work zone by either:
(i) Demarcating boundaries (such as with flags, or a device such as a
range limit device or range control warning device) and prohibiting the
operator from operating the equipment past those boundaries, or
(ii) Defining the work zone as the area 360 degrees around the
equipment, up to the equipment’s maximum working radius.
The Respondent suggests that the manner in which the company had identified the
“work zone” in step one resulted in the 20-foot “trigger distance” not being encroached,
so that no additional precautions were required. 9 This contention fails because the
Respondent did not employ the method described in subparagraph (a)(1)(i) of identifying
the work zone by “[d]emarcating boundaries (such as with flags, or a device such as a
range limit device or range control warning device).”
As noted above, in a safety meeting conducted before crane operations
commenced on April 5, 2012, the Respondent identified the concrete knee wall as the
boundary beyond which the crane or its load would not encroach. (Exs. Q and R; Tr.
164-65). The mere identification of an existing landmark is insufficient to meet the
requirement to “demarcate” a work zone’s boundaries pursuant to subparagraph (a)(1)(i).
Rather, demarcation requires an actual marking, “such as with flags,” as the preamble to
the final rule explained:
Employers are not permitted to use existing landmarks to demarcate work
zone boundaries unless they are marked. For example, a line of trees
would be insufficient. Without anything more the trees would not signal a
reminder to the operator of there being a boundary that must be
9
The Respondent relies on Exhibit P, which is an OSHA interpretative letter dated
March 12, 2012, that states in part as follows:
If the demarcated boundary line is located at least the minimum clearance
distance from the power line, the operator understands that no part of the
equipment or load may go past the demarcated boundary line of flags, and
the operator is able to judge the position of the equipment with respect to the
demarcated boundary line, §1408(a)(2) is satisfied and no further
precautions are needed.
16
maintained. However, adding flags to those trees would be sufficient
because the flags would serve as a reminder that the trees are located
along a boundary that the operator must not breach.
75 Fed. Reg. 47952 (Aug. 9, 2010).
Here, the Respondent employed none of the methods described in the standard for
demarcating the work zone boundaries. No flags or similar markers were placed on the
existing landmark of the concrete knee wall. Moreover, the crane was not equipped with
either a “range limit control device” or a “range control warning device.” 10 (Ex. 2, p. 4).
Because the Respondent failed to demarcate the work zone boundaries in the
manner permitted under § 1926.1408(1)(a)(i), the work zone was necessarily defined by
the method set out in § 1926.1408(a)(1)(ii), which defines “the work zone as the area 360
degrees around the equipment, up to the equipment’s maximum working radius.”
10
The term “range control limit device” is defined in § 1926.1401 as “a device that
can be set by an equipment operator to limit movement of the boom or jib tip to a plane
or multiple planes.” Such a device “physically limits how far a crane can boom out and
the angle within which the boom can swing.” 75 Fed. Reg. 47952 (Aug. 10, 2010).
There is no evidence that the crane here was equipped with such a device. Moreover,
even assuming that the crane was equipped with such a device, there is no evidence that it
had been activated and calibrated in such a manner to prevent the crane or its load from
encroaching outside the work zone that the Respondent had intended to define by the
existing landmark (the concrete knee wall). Rather, the crane operator had merely been
instructed not to boom below 75 degrees. No range control limit device prevented the
crane from booming lower than 75 degrees (whether intentionally or not). (Exs. Q & R).
Similarly, there is no evidence that the crane was equipped with a “range control
warning device,” which is defined in § 1926.1401 as “a device that can be set by an
equipment operator to warn that the boom or jib tip is at a plane or multiple planes.”
Further, even if the crane had been equipped with such a device, there is no evidence that
the device had been activated and calibrated to prevent the crane or its load from
extending outside the intended work zone (i.e., the area no further than the existing
landmark of the concrete knee wall.)
The crane was equipped with a “load moment indicator” (Tr. 104, 108), but that
equipment is neither a “range limit control device” nor a “range control warning device.”
See § 1926.1401 (defining the term “load moment (or rated capacity) indicator”). The
crane was also equipped with electronic and manual boom angle indicators (Ex. R), but
that equipment is likewise neither a “range limit control device” nor a “range control
warning device.”
17
The work zone boundaries having been so defined in step one, the Respondent
was then required in step two to “[d]etermine if any part of the equipment, load line or
load (including rigging and lifting accessories), if operated up to the equipment's
maximum working radius in the work zone, could get closer than 20 feet to a power line,”
and “[i]f so, the employer must meet the requirements in Option (1), Option (2), or
Option (3) of this section ….” 29 C.F.R. § 1926.1408(a)(2).
As described above, the crane or its load could come in contact with the power
line if the crane were operated up to the its maximum working radius, and thus the
Respondent was required to meet the requirements of one of the three options specified
by § 1926.1408(a)(2). The Respondent contends that it complied with “Option 2,” which
is set forth in section 1926.1408(a)(2)(ii) as follows: 11
(ii) Option (2)--20 foot clearance. Ensure that no part of the equipment,
load line, or load (including rigging and lifting accessories), gets closer
than 20 feet to the power line by implementing the measures specified in
paragraph (b) of this section.
Subparagraph (b) of § 1926.1408 describes the measures an employer must
implement when utilizing “Option 2.” 12 Option 2 requires an employer to meet “all” of
11
The Respondent does not contend, and there is no evidence to support, a finding
that it complied with the standard by employing either Option 1 or Option 3.
12
Section 1926.1408(b) provides as follows:
(b) Preventing encroachment/electrocution. Where encroachment
precautions are required under Option (2) or Option (3) of this section, all of
the following requirements must be met:
(1) Conduct a planning meeting with the operator and the other workers
who will be in the area of the equipment or load to review the location of the
power line(s), and the steps that will be implemented to prevent
encroachment/electrocution.
(2) If tag lines are used, they must be non-conductive.
(3) Erect and maintain an elevated warning line, barricade, or line of
signs, in view of the operator, equipped with flags or similar high-visibility
markings, at 20 feet from the power line (if using Option (2) of this section)
18
the requirements set out in subparagraphs (b)(1) through (4). The Secretary contends
only that the Respondent failed to meet the requirement of subparagraph (b)(3) to “[e]rect
and maintain an elevated warning line, barricade, or line of signs, in view of the operator,
equipped with flags or similar high-visibility markings, at 20 feet from the power line.”
29 C.F.R. § 1926.1408(b)(3).
It is undisputed that the Respondent did not erect or maintain a warning line as
described by subparagraph (b)(3). The Respondent suggests, however, that because it
used a “dedicated spotter” as described in the second sentence of subparagraph (b)(3), it
met the requirements of the subparagraph. This argument is rejected. Subparagraph
or at the minimum approach distance under Table A (see § 1926.1408) (if
using Option (3) of this section). If the operator is unable to see the elevated
warning line, a dedicated spotter must be used as described in §
1926.1408(b)(4)(ii) in addition to implementing one of the measures
described in §§ 1926.1408(b)(4)(i), (iii), (iv) and (v).
(4) Implement at least one of the following measures:
(i) A proximity alarm set to give the operator sufficient warning to
prevent encroachment.
(ii) A dedicated spotter who is in continuous contact with the operator.
Where this measure is selected, the dedicated spotter must:
(A) Be equipped with a visual aid to assist in identifying the minimum
clearance distance. Examples of a visual aid include, but are not limited to:
A clearly visible line painted on the ground; a clearly visible line of
stanchions; a set of clearly visible line-of-sight landmarks (such as a fence
post behind the dedicated spotter and a building corner ahead of the
dedicated spotter).
(B) Be positioned to effectively gauge the clearance distance.
(C) Where necessary, use equipment that enables the dedicated spotter to
communicate directly with the operator.
(D) Give timely information to the operator so that the required
clearance distance can be maintained.
(iii) A device that automatically warns the operator when to stop
movement, such as a range control warning device. Such a device must be
set to give the operator sufficient warning to prevent encroachment.
(iv) A device that automatically limits range of movement, set to prevent
encroachment.
(v) An insulating link/device, as defined in § 1926.1401, installed at a
point between the end of the load line (or below) and the load.
19
(b)(3) does not make the use of a dedicated spotter an alternative to the use of an
“elevated warning line” or similar visual marking, but rather makes it an additional
requirement if the crane operator is “unable to see the elevated warning line.” See 75
Fed. Reg. 47955 (Aug. 9, 2010) (noting that where a crane operator is unable to see the
elevated warning line, subparagraph (b)(3) provides “two layers of protection.”)
The Secretary has established that the Respondent violated the cited standard by
not implementing all of the precautions required under Option 2, specifically for failing
to erect and maintain an elevated warning line as required by § 1926.1408(b)(3).
The Respondent’s employees had access to the violative condition. The CO
observed the employees using tag lines to guide a steel joist during a lift to prevent the
joist from getting closer than 20 feet to the power line. (Tr. 56-57).
The Secretary has also shown knowledge of the violation. The Respondent’s
foreman was serving as a spotter during the crane operations (Ex. Q), and he was aware
that there was no elevated warning line. (Tr. 56-57). The foreman’s knowledge of the
violation is imputable to the Respondent for the same reasons set out as to Item 1 above.
The Secretary proved the alleged violation. He has also proved the violation was
properly classified as “serious,” in that if the crane or its load had contacted with the
power line, death or serious injury from electrocution could have resulted. (Tr. 36-38).
Citation 2, Item 1 – 29 C.F.R. § 1926.351(e)
The CO observed one of the Respondent’s employees on the second level of the
structure welding metal decking with an arc welder. (Tr. 40; Ex. 3, photos 1, 2 and 3).
The employee was spot welding the final deck attachments, which required him to
frequently move from one place to another on the metal decking. (Tr. 109-110, 168).
20
The welder was not using a welding screen to prevent other persons from sustaining eye
damage from direct exposure to the rays of the arc. (Tr. 41).
A worker of another employer on the site had been working for about three hours
at a fixed position 20 to 25 feet from the welder. (Tr. 40-41, 59, 110). This worker was
wearing safety glasses that blocked UV (ultraviolet) rays, as did all of the Respondent’s
employees. (Tr. 167-68; Exs. U and X). The worker knew eye damage could result from
exposure to the rays of the arc, and he had been intentionally avoiding looking directly at
the rays. (Tr. 44). Besides this worker, no other employees were present on the second
level with direct exposure to the arc rays. (Tr. 110).
When the CO told the welder that a protective screen was required, the welder
went to search for one but he did not find any on the site. (Tr. 41-42).
This item alleges an “other” violation of 29 C.F.R. § 1926.351(e), which states:
Shielding. Whenever practicable, all arc welding and cutting operations
shall be shielded by noncombustible or flameproof screens which will
protect employees and other persons working in the vicinity from the
direct rays of the arc.
The cited standard applies to the Respondent’s arc welding operation on April 5,
2012.
There is no dispute that the Respondent’s employee was not using a protective
screen while he did the spot welding. In order to prove that the Respondent did not meet
the cited standard, however, the Secretary must also show that the use of a screen was
“practicable” under the circumstances.
The American Heritage Dictionary 1377 (4th ed. 2000), defines “practicable” as
follows: “1. Capable of being effected, done, or put into practice; feasible. See
21
synonyms at possible. 2. Usable for a specified purpose: a practicable way of entry.”
(Boldface and italics in original.)
The Respondent argues that the use of a screen was not practicable because the
welder would have had to reposition the screen on the uneven surface of the metal
decking every time he changed positions while spot welding.
The CO believed that a screen could have been used to shield the other worker
from exposure to the arc rays by placing a screen near that worker’s fixed location,
thereby making it unnecessary to reposition the screen every time the welder changed his
position. (Tr. 110). There was no evidence that use of a protective screen in this fashion
was not capable of being done or put into practice. The Secretary has carried his burden
of establishing that the use of a protective screen was practicable under the
circumstances. The Respondent did not meet the standard’s terms.
The only worker exposed to the hazard worked for another employer. Exposure is
established where an employer creates or controls a hazard and exposes its own
employees or the employees of other employers on a multi-employer worksite. Summit
Contractors, Inc., 23 BNA OSHC 1196 (No. 05-0839, 2010), petition for review denied,
No. 10-1329 (D.C. Cir. Dec. 14, 2011) (unpublished). The evidence demonstrates that an
employee was exposed to the violative condition.
The Respondent knew of the violation. It did not have a protective screen at the
site, and the Respondent’s president testified that he has never used a welding screen
while welding metal decking. (Tr. 59, 167).
The violation is aptly characterized as “other.” The exposed worker and all of the
Respondent’s employees were wearing safety glasses that blocked most UV rays; also,
22
the exposed worker was aware of the danger of eye damage and avoided looking directly
at the rays. Crescent Wharf & Warehouse Co., 1 BNA OSHC at 1222.
Citation 2, Item 2 – 29 C.F.R. § 1926.352(d)
The Respondent’s welder had no fire extinguisher within 10 feet of where he was
working. The nearest fire extinguisher to the welder was in a fixed location about 60 feet
away from where he was working, and had been placed there by the general contractor.
The welder told the CO that he was aware there was a fire extinguisher on the level
where he was working, but that he did not know its exact location. (Tr. 121-124).
This item alleges an “other” violation of 29 C.F.R. § 1926.352(d), which
provides that: “Suitable fire extinguishing equipment shall be immediately available in
the work area and shall be maintained in a state of readiness for instant use.”
The cited standard applies to welding and cutting operations in construction, and
therefore applies to the Respondent’s arc welding operation on April 5, 2012.
The CO testified that he interprets the cited standard to require that a fire
extinguisher be available for instant use in the area where the welding is taking place. He
believed that a fire extinguisher should be within 10 feet of the welder to meet the
standard. (Tr. 42).
The standard evinces a clear intent to require that fire extinguishers be available
to enable workers to put out fires at the site of the welding with little or no delay. Here,
the fire extinguisher was located about 60 feet away from the welder and he did not know
its precise location. The terms of the standard were not met. 13
13
The Respondent notes that the fire extinguisher’s location complied with the more
generally applicable standard set forth at 29 C.F.R. § 1926.150(c)(1) and suggests that its
location met the cited standard, which applies only to welding and cutting activity. The
cited standard provides for greater protection than the more generally applicable standard.
23
The Respondent suggests that there was no fire hazard to be protected against
because the welder’s work area had been cleared of combustibles before welding
operations began. (Tr. 168). The presence of combustible material in the vicinity of the
welding is not an element of the cited standard and thus has no bearing on determining
whether an employer has met the terms of the standard.
The nearest employee with access to the violative condition was the welder. The
Respondent knew or should have known of the condition, as the welder had been welding
for about three hours in an open and exposed area. (Ex. 2, p. 8; Tr. 61).
The evidence supports the classification of an “other” violation. The Respondent
cleared the immediate vicinity of the work area of combustibles before the welding
began. 14 Also, the welder kept a “fire blanket” that was immediately accessible to him
while welding. (Tr. 171-72). Serious physical harm was not likely to result from the
violation. Crescent Wharf & Warehouse Co., 1 BNA OSHC at 1222.
Affirmative Defenses
The Respondent raised the affirmative defense of infeasibility as to all four
citation items. It also raised the affirmative defense of unpreventable employee
misconduct as to the item respecting crane safety. (Joint Prehearing Statement, p. 8).
Insufficient evidence was presented to support even a prima facie case on any
element of either defense as to any of the citation items. See V.I.P. Structures, Inc., 16
BNA OSHC 1873, 1874 (No. 91-1167, 1994) (describing elements of infeasibility); Am.
Cf. Cincinnati Gas & Elec. Co., 21 BNA OSHC at 1058 (a “general standard is not
preempted by a specific standard when it provides meaningful protection to employees
beyond that afforded by the more specific standard”). The cited standard is applicable
here, notwithstanding compliance with another more generally applicable fire protection
and prevention standard.
14
No evidence was presented as to whether the welder’s clothing was combustible.
24
Eng’g & Dev. Corp., 23 BNA OSHC 2093, 2096-97 (No. 10-0359, 2012) (describing
elements of unpreventable employee misconduct). Also, neither defense was argued in
the post-hearing brief. Issues not briefed are treated as waived or abandoned. Georgia-
Pacific Corp., 15 BNA OSHC 1127, 1130 (No. 89-2713, 1991).
Penalty Assessment
The Commission and its judges conduct de novo penalty determinations and have
full discretion to assess penalties based on the facts of each case and the applicable
statutory criteria. Valdak Corp., 17 BNA OSHC 1135, 1138 (No. 93-0239, 1995); Allied
Structural Steel, 2 BNA OSHC 1457, 1458 (No. 1681, 1975). The permissible range of
penalties for both “serious” and “other” violations is from no penalty to $7,000. 29
U.S.C. §§ 666(b) & (c).
The Secretary proposed a penalty of $2,200.00 for each of the two serious
violations and no penalty for the two “other” violations.
Section 17(j) of the Act, 29 U.S.C. § 666(j), requires that in assessing penalties,
the Commission give “due consideration” to four criteria: the size of the employer’s
business, the gravity of the violation, the employer’s good faith, and its prior history of
violations. Gravity is the primary consideration among these four statutory criteria, and
is determined by “such matters as the number of employees exposed, the duration of the
exposure, the precautions taken against injury, and the likelihood that any injury would
result.” J.A. Jones Constr. Co., 15 BNA OSHC 2200, 2214 (No. 87-2059, 1993).
The Respondent is a small employer that variably employs between five and 20
employees. (Tr. 174). The record supports the Secretary’s reduction of the proposed
penalty to account for the size of the Respondent’s business.
25
The record does not demonstrate circumstances supporting any penalty
adjustment for the statutory “good faith” factor.
The proposed penalty for the two serious violations included an enhancement of
10% upon the determination that the Respondent had committed a willful violation in
- (Ex. 1; Tr. 55). The evidence does not support the Secretary’s stated basis for this
10% enhancement. Although OSHA had originally cited the Respondent in 2009 for two
alleged willful violations, those allegations were withdrawn as the result of an informal
settlement agreement. (Ex. F, p. 4; Tr. 170).
The Secretary determined the two serious violations were both of high severity in
that the standards violated could potentially result in death or serious injury, as discussed
above. (Ex. 1). He considered the probability for injury for the violation of 29 C.F.R. §
1926.1051(a) to be “lesser” due to the brief duration of exposure. He considered the
probability for injury for the violation of 29 C.F.R. § 1926.1408(a)(2) to be “lesser”
because of other precautions that had been implemented. (Ex. 1; Tr. 57-58).
The evidence supports the proposed penalty for the violation of the crane
standard, 29 C.F.R. 1926.1408(a)(2), except for the 10% enhancement for history.
Accordingly, a penalty of $2,000 is assessed for this violation.
The Secretary fairly determined there was a “lesser” probability of injury for the
violation of 29 C.F.R. § 1926.1051(a), but accorded this factor insufficient weight. Also,
as discussed above, the record does not support the 10% enhancement for history. A
penalty of $750 is assessed for this violation.
The Secretary determined the “other” violations to be of “minimal” severity and
“lesser” probability. As to the violation of 29 C.F.R. § 1926.351(e), the only exposed
26
worker wore safety glasses. As to the violation of 29 C.F.R. § 1926.352(d), there were
no combustibles in the immediate work area. (Ex. 1; Tr. 59-60).
The decision to propose no penalties for the two “other” violations was proper.
Findings of Fact and Conclusions of Law
The foregoing decision constitutes the findings of fact and conclusions of law in
accordance with Federal Rule of Civil Procedure 52(a).
ORDER
Based on the above Findings of Fact and Conclusions of Law, it is hereby
ORDERED that:
1. Citation 1, Item 1, alleging a serious violation of 29 C.F.R. § 1926.1051(a), is
AFFIRMED, and a penalty of $750.00 is assessed.
2. Citation 1, Item 2, alleging a serious violation of 29 C.F.R. § 1926.1408(a)(2),
is AFFIRMED, and a penalty of $2,000.00 is assessed.
3. Citation 2, Item 1, alleging an other-than-serious violation of 29 C.F.R. §
1926.351(e), is AFFIRMED, and no penalty is assessed.
4. Citation 2, Item 2, alleging an other-than-serious violation of 29 C.F.R. §
1926.352(d), is AFFIRMED, and no penalty is assessed
_/s/________________________________
WILLIAM S. COLEMAN
U.S. OSHRC JUDGE
Date: September 9, 2013
Washington, D.C.
27
Get today's answer for your situation
You just read what one judge decided for one employer in 2013, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.