🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 08-1225 Decided January 8, 2014 Procedural Judge Dennis L. Phillips

K.E.R. Enterprises, Inc. d/b/a Armadillo Underground

EAJA fees awarded after pipe citation was vacated

Apply this to your situation

This order from 2014 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 2014
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Armadillo Underground defended citations arising from a PVC water-pipe explosion that injured four workers. The underlying general duty clause item was vacated because OSHA did not prove that tightening the joint bolts while the line remained pressurized was a recognized hazard, and a separate safety-program item was withdrawn at the hearing. In this Equal Access to Justice Act proceeding, the judge found that OSHA lacked substantial justification for the general duty clause item because its case relied on a fundamental misunderstanding of the leak-repair procedure and a strained reading of the manufacturer's instructions and voluntary industry standard. The judge found OSHA was substantially justified in initially issuing and later withdrawing the safety-program item. After excluding pre-citation costs and allocating part of the shared work to the noncompensable item, the judge awarded Armadillo $30,048.17 in attorney fees and expenses.

Decision snapshot

  • Cited standard(s): 29 U.S.C. § 654(a)(1); 29 C.F.R. § 1926.20(b)(2)
  • Outcome: Armadillo was awarded $30,048.17 in EAJA attorney fees and expenses.
  • Key point: The government lacks substantial justification when reasonable prehearing investigation would have exposed the factual misunderstanding underlying its citation theory.

Full text (OSHRC public release)

                    UNITED STATES OF AMERICA
        OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION

SECRETARY OF LABOR,
Complainant,

             v.                                         OSHRC Docket No. 08-1225

K.E.R. ENTERPRISES, INC. d/b/a
ARMADILLO UNDERGROUND,
Respondent

ON BRIEFS:

Jeremy K. Fisher, Attorney Andrew N. Gross, General Counsel
Christopher D. Helms, Counsel HB Training & Consulting, LLC,
Office of the Solicitor 1255 Lakes Parkway
U.S. Department of Labor Suite 385
61 Forsyth Street, S.W. Lawrenceville, GA 30043
Room 7T10 For the Respondent
Atlanta, GA. 30303
For the Complainant

Before: Dennis L. Phillips
Administrative Law Judge

      DECISION AND ORDER GRANTING APPLICATION FOR FEES AND
      EXPENSES PURSUANT TO THE EQUAL ACCESS TO JUSTICE ACT

      K.E.R. Enterprises, Inc. d/b/a Armadillo Underground (“Armadillo” or “Petitioner”),

seeks attorneys’ fees and expenses pursuant to the Equal Access to Justice Act, 5 U.S.C. §504

(“EAJA”), for costs incurred in its defense of a two item citation issued by the Secretary on July

21, 2008. The application for fees and expenses is granted to the extent indicated herein.

                                         Background

      Armadillo is an underground utility excavation contractor that installs water, drainage

and sewer systems. On March 28, 2008 Armadillo was part of a multi-year project to install five
miles of PVC piping for Collier County, Florida. A small leak was found in a section of recently

installed 20-inch PVC pipe. To stop the leak, two crew members tightened the T-head bolts on

the mega lug with hand wrenches. The pipe exploded. Three workers were hit by pipe

fragments and received lacerations. Additionally, Armadillo’s foreman was struck by the pipe as

it exploded, knocking him over a rock ledge and breaking both of his legs.

      As a result of an inspection by OSHA, the Secretary issued a citation alleging two

violations on July 21, 2008. Item 1 of the citation alleged that Armadillo violated the General

Duty Clause, § 5(a)(1) of the Occupational Safety and Health Act, 29 U.S.C. § 651 et seq. (the

“Act”), on the grounds that “employees were exposed to the hazard of being struck by fragments

of a water main PVC pipe, whose mechanical joints and restraining glands were not being

installed in accordance with the manufacturer’s specifications.” According to the citation, “one

feasible and acceptable method to correct the hazard is to install the mechanical joints and

restraining glands in accordance with the manufacturer and as required by ANSI/AWWA1

C111/605.” A penalty of $3,000 was proposed for the alleged violation.

      Item 2 of the citation alleged a serious violation of 29 C.F.R. § 1926.20(b)(2) on the

grounds that “deficiencies in the safety and health program were [not] identified to include

hazard prevention and control, and worksite analysis.” The Secretary proposed a penalty of

$3,000.

      On August 8, 2008, Armadillo filed its notice of intent to contest the citation.

      On March 30, 2009, the Secretary withdrew Item 2 at the beginning of the hearing. The

hearing involved only Item 1, the alleged violation of the General Duty Clause. Central to the

Secretary’s case was the assertion that tightening the bolts to stop a leak without first

depressurizing the water line constituted a recognized hazard. The Secretary also asserted that
1
American Water Works Association.
employees violated the AWWA instructions by using hand wrenches rather than torque wrenches

when trying to stop the leak. As a result, they allegedly over tightened the T-bolts which

contributed to the explosion.

    On December 14, 2009, this Court issued a decision vacating Item 1, finding that the

Secretary failed to establish that the cited condition presented a hazard or that Armadillo or its

industry recognized the hazard. The Secretary failed to present adequate and persuasive

evidence that it is never appropriate under the manufacturer’s instructions or industry standards

to tighten the T-bolts while the water line is pressurized, or that tightening the T-bolts with a

hand wrench created a hazardous condition. To the contrary, the evidence was persuasive that

Armadillo’s procedures at the site on the day of the accident were proper and in accordance with

industry practice.

    The Secretary’s Petition for Discretionary Review was granted by the Commission. On

January 9, 2013 the Commission issued its decision affirming this Court’s decision. The

Commission found that neither the manufacturer’s installation instructions nor the AWWA

standard contain a safety warning or suggest a link between noncompliance and a safety hazard.

The Commission also agreed that while the manufacturer’s instructions and the AWWA

standards recommend that a torque wrench be used, neither required the use of a torque wrench

under these circumstances. To the contrary, the AWWA standard contemplates that an

experienced employee could tighten the T-bolts to the proper torque without a torque wrench.

    The Secretary did not appeal the Commission’s decision and it became a final order sixty

days later, on March 11, 2013. On April 8, 2013 Armadillo filed a timely Petition for Fees and

Costs under the EAJA.2 The Secretary filed an Opposition to the Application and Armadillo

2
An Application for Fees and Expenses under the EAJA must be filed within 30 days of the final disposition of the
adversary adjudication. 5 U.S.C. § 504(a)(2); 29 C.F.R. § 2204.302(a).
filed a reply to the Secretary’s opposition.

                                         EAJA
       The Equal Access to Justice Act entitles eligible parties who prevail in litigation against

the government to receive related attorney's fees and expenses. 29 C.F.R. § 2204.101.

An EAJA eligible corporation is one with a net worth not exceeding $7 million that employs no

more than 500 employees. 29 C.F.R. § 2204.105. A prevailing party, who meets the financial

qualifications, may receive an award of attorney fees and expenses unless the Secretary's position

throughout the proceeding was substantially justified or special circumstances make an award

unjust. 29 C.F.R. § 2204.101.

                                         Eligible Party

       The Secretary asserts that Armadillo failed to establish that it is a party eligible to receive

an award under the EAJA. The Secretary observes that, under Commission rules, the employer

must demonstrate that, at the time that the Notice of Contest was filed, its net worth was not

more than $7 million. 29 C.F.R. § 2204.105(c). The Notice of Contest was filed on August 8,

  1. Armadillo produced Summary Balance Sheets for years 2007 through 2009. While each

of these statements demonstrated a net worth well under $7 million, the dates on the statements

were as of September 30 of each year.

       The relevant Commission rule, 29 C.F.R. § 2204.105(c) states:

       For the purpose of eligibility, the net worth and number of employees of an
       applicant shall be determined as of the date the notice of contest was filed, or, in
       the case of a petition for modification of abatement period, the date the petition
       was received by the Commission under § 2200.37(d).

       The Secretary argues that this rule requires a determination of the applicant’s actual net

worth on the precise date the Notice of Contest was issued.3 This Court finds the Secretary’s

3
The Secretary does not dispute that Armadillo had fewer than 500 employees.
reading of the rule to be overly technical and unreasonable. The rule clearly states that , “ [f]or

the purpose of eligibility, the net worth … of an applicant shall be determined as of the date the

notice of contest was filed.” Nothing in the rule requires the applicant to submit a net worth

exhibit only as of the date of the Notice of Contest.4 Rather, it is sufficient that the applicant

submit sufficient documentation to establish that its net worth was not greater than $7 million on

the date of the Notice of Contest.

     In Information Sciences Corp. v. U.S., 86 Fed. Cl. 269 (Fed. Cl. 2009) (amended on

denial of reconsideration,88 Fed. Cl. 626 (Fed. Cl. 2009), the adversary adjudication began on

October 29, 2007. On reconsideration, the court amended the award relating to attorney fees, but

left undisturbed the calculation regarding the company’s net worth. In this case, the employer

submitted financial reports establishing that it had a financial worth below $7,000,000 on

December 31, 2006 and December 31, 2007. Also submitted was an unaudited balance sheet as

of October 24, 2007 showing a net worth of under $7,000,000 and a statement by its accountant

that “it would not have been possible for [the company] to achieve a net worth of $7 [m]illion at

any time during the 2007 calendar year.” Id. at 281. Despite the government’s protestations that

the company failed to establish that its net worth did not exceed $7,000,000 on October 29, 2007,

the Federal Claims Court found that the company presented sufficient evidence to ascertain and

verify that its net worth was below $7,000,000 when the Complaint was filed. Id.

     In Sosebee v. Astrue, 494 F.3d 583 (7th Cir. 2007), the party seeking fees failed to submit

an application that adequately established its financial eligibility under standard accounting

practices. Also, it did not submit an affidavit attesting to its net worth. Instead, it filed a letter

4
In establishing the sufficiency of net worth exhibits as of the contest date, 29 C.F.R. § 2204.202, Net worth exhibit,
states that: “[t]he exhibit may be in any form convenient to the applicant that provides full disclosure of the
applicant’s assets and liabilities and is sufficient to determine whether the applicant qualifies under the standards in
this part.” [emphasis added].
setting forth its financial condition, asserting that its net worth fell well below the statutory

maximum. The court observed that the statute has been interpreted to require varying levels of

supporting evidence depending, in part, on whether there was a serious doubt about the

applicant’s eligibility. Id. at 588. The court also noted that EAJA is not intended to duplicate in

complexity a public commission’s rate of return proceeding. Rather it is intended to open the

doors of the courthouse to parties, not keep them locked in the courthouse disputing fees well

after the resolution of the underlying case. Id. at 588-89. The court concluded that:

       In denying Sosebee's EAJA application, the district court either applied an
    impermissibly high standard of proof or it improperly exalted form over
    substance. The court asserted that it “need not draw inferences” from the
    evidence, but this is exactly what factfinders do. Drawing inferences is not the
    same thing as speculation. Indeed, nothing but wild speculation would have
    supported a finding that Sosebee was worth more than $2,000,000. Nowhere in
    his brief does the Commissioner seriously suggest that Sosebee does not meet the
    EAJA’s net worth requirement.

Id. at 589.

    Here, Armadillo submitted summary balance sheets as of September 30 for years 2007

through 2009. Armadillo’s net worth (total equity) was $4,214,497.06 as of September 30, 2007;

$4,932,460.09 as of September 30, 20008; and $3,723,652.02 as of September 30, 2009. At no

time during this period is there any suggestion that Armadillo’s net worth equaled or even

approached the $7,000,000 threshold. Significantly, the summary balance sheet for 2008

established Armadillo’s net worth less than two months after the August 8, 2008 Notice of

Contest. The Secretary produces no evidence to suggest that the summary balance sheets are

inaccurate, or that some unusual circumstance temporarily raised the applicant’s net worth above

the $7,000,000 limit. This Court finds that the evidence submitted by Armadillo establishes that

the net worth of the company was less than seven million dollars as of August 8, 2008.

    Accordingly, this Court finds that Armadillo established that it was an “eligible party”

under the EAJA.

                            Substantial Justification

    Once an eligible applicant establishes that it is the prevailing party, the Secretary bears

the burden of establishing that his position was substantially justified. Joseph Watson, d/b/a

Joseph Watson Masonry, 21 BNA OSHC 1649, 1651 (No. 00-1726, 2006); See Consol. Constr.

Inc., 16 BNA OSHC 1001, 1002 (No. 89-2389, 1993) (EAJA). A position is substantially

justified if it has a “reasonable basis in both law and fact” or is “justified in substance or in the

main - that is, justified to a degree that could satisfy a reasonable person.” Pierce v. Underwood,

487 U.S. 552, 563-66 (1988); C.J. Hughes Constr. Inc., 19 BNA OSHC 1737, 1740 (No. 93-

3177, 2001) (EAJA). The Secretary bears the burden to show that: (1) there exists a reasonable

basis for the facts alleged, (2) there exists a reasonable basis in law for the theory he propounds,

and (3) the facts alleged reasonably support the legal theory. Joseph Watson, 21 BNA OSHC at

1651; Contour Erection & Siding Sys. Inc., 18 BNA OSHC 1714, 1716 (No. 96-0063, 1999).

A. Item 1- 5(a)(1)(Respondent’s employees were exposed to being struck by fragments of a
water main PVC pipe, whose mechanical joints and restraining glands were not being
installed in accordance with the manufacturer’s specifications.)

    The underlying basis for the citation was the Compliance Officer’s (the “CO”)

assumption that the bolts were overstressed when tightened to stop a leak in a pipe that was not

first depressurized. The evidence revealed that virtually every basis for the Secretary’s issuance

of the 5(a)(1) allegation was not only unsupported by the record, but also fundamentally flawed

as outlined below.

    1. At the beginning of the hearing, the CO contended that the AWWA standard requires

that, when a pipe leaks, the pipe needs to be depressurized and dismantled. According to the

CO, if the bolts are torqued within their acceptable range, the only reason why a leak would
occur is that the pipe was improperly installed. (Tr. 68-71).

    Contrary to the CO’s testimony, the evidence established that the most common reason

for a pipe to leak is that the bolts are not tight. The AWWA standard clearly requires that a

leaking pipe should be disassembled only if the leak continues when the bolts are tightened to

“maximum torque.” Therefore, the first step to resolve a leak is to tighten the bolts to maximum

torque. Only if that fails is the pipe depressurized and dismantled to ensure that the seals are set

correctly. The relevant AWWA instruction clearly states that “[i]f effective sealing is not

attained at the maximum torque indicated, the joint should be disassembled, thoroughly cleaned,

and reassembled.” The CO admitted that he had no evidence that the bolts on the leaking pipe

were at maximum torque before they were tightened. The CO refused to concede that, if the

bolts are torqued to the minimum part of the range, a leak might be resolved by further tightening

the bolts. (Tr. 70-71).

    Engineer Michael Shea, introduced as an expert on behalf of the Secretary, also disagreed

that it is routine practice to tighten bolts while the pipe is still under pressure. In his expert

report, Mr. Shea testified that:

            [a]ccording to the manufacturer’s specifications and industry standards
    relied upon by the utility pipe installation industry, the installers, upon learning of
    a leak during a pressure and/or leak test, should have depressurized the line.
    Then, rather than tightening the hex head shank bolts on the mechanical joint
    restraining gland, the mechanical joint restraining gland should have been
    disassembled, and the installation procedure repeated until an effective seal was
    attained.

(Ex. G-26, at p.3)

    Mr. Shea’s report continued that

    the water line should have been de-pressurized, the Sigma ONE-LOK system
    disassembled, and then reassembled by tightening the hex head shank bolts with a
    torque wrench to the recommended torque. This is common sense and is in
    agreement with industry standard ANSI/AWWA C111/21.11-00, Rubber-Gasket

Joints for Ductile-Iron Pressure Pipe and Fittings, Appendix A, page 1122, which
states, “If effective sealing is not attained at the maximum torque indicated, then
the joint should be disassembled, thoroughly cleaned, and reassembled.
Overstressing the bolts to compensate for poor installation practice is not
acceptable.

(Id., at p. 4)(emphasis in original).

    Not only was Mr. Shea’s expert testimony directly at odds with the AWWA standard,

which requires disassembly only when the bolts are at maximum torque, but he also quoted that

precise section of the standard to support his position that any leak during a pressure test requires

the depressurization and disassembly of the water line. When it became clear that neither the

ANSI/AWWA standard nor the manufacturer’s instructions supported his position, Mr. Shea

deemphasized the ANSI/AWWA standard and the manufacturer’s instruction. He relied heavily

on “common sense” which he asserted mandated that the lines be depressurized before tightening

the bolts. The evidence not only failed to support the Secretary’s basic theory of the case, but

directly contradicted it. (Tr. 173, 176, 193-94).

    2. The Secretary asserted that Armadillo should have used a torque wrench to tighten

the bolts. At the hearing, the Secretary’s witnesses admitted that neither the AWWA procedure

nor the Sigma (manufacturer) specifications required the use of a torque wrench, as long as the

employees were properly trained. There is nothing in the record to suggest that either Armadillo

or any reasonable employer in its industry would have recognized that the failure to use a torque

wrench constituted a hazard.

    3. The Secretary’s expert, Michael Shea, produced an analysis of the accident after

identifying the bolts as hex head shank bolts, whose heads break off when turned to the proper

talk. The bolts were T-bolts that do not break off. That Mr. Shea believed that the crew was

working with hex head bolts underscores the lack of justification in the Secretary’s position. If
Armadillo was tightening hex head bolts, the heads on the bolts would have snapped off when

the crew got to the proper torque. It would have been impossible for the crew to have tightened

the bolts beyond the prescribed tolerance. (Tr. 121-22; Ex. G-26, at p. 3).

   Despite Mr. Shea’s belief that hex head bolts were being used, critical to the Secretary’s

theory of the case was that the bolts were tightened beyond their maximum tolerance. Similarly,

the Secretary asserted that Armadillo’s failure to use a torque wrench constituted a recognized

hazard. However, the purpose of a torque wrench is to prevent an employee from over-

tightening a bolt. If, as the Secretary believed, Armadillo was tightening hex head nuts, using a

torque wrench would have been redundant.

   4. Both the CO and the Secretary’s expert, Michael Shea, conceded that the AWWA

C111, which the Secretary alleged Armadillo was required to follow, was neither a specification,

nor incorporated into OSHA’s standards and that the document itself stated that its use was

entirely voluntary.

   Of particular relevance is Paramount Advanced Wireless, LLC, 23 BNA OSHC 1634

(No. 09-0178, 2011) (ALJ). After an employee fell from a communication tower, the Secretary

cited the employer for a violation of 29 C.F.R. § 1926.501(b)(1), in the alternative, on the

grounds that employees “were working on a communication tower 60 feet above the ground

without any fall protection.” Id. at 1636. Employees were using a device called a “Fisk

Descender” for fall protection. The Secretary alleged that the employer failed to provide

adequate fall protection because it improperly used the Fisk Descender to perform controlled

descents without back-up protection consisting of a hooked up second line with a rope grab. In

her initial decision, Judge Rooney concluded that at the time of the accident, the employee was

using the device to position himself and was not engaged in a controlled descent. The evidence
established that, while being used as a positioning device, a Fisk Descender need not be

accompanied by a second line, but with a shock absorbing lanyard which the employee was

using. The judge observed that the Secretary based her case on the assumption that the sole use

of a Fisk Descender was as a device used in a controlled decent. At the hearing, it became clear

that the Secretary’s position was based on a misunderstanding of the uses of a Fisk Descender

and the type of back-up equipment that should be used with it. Granting the employer’s petition

for EAJA fees and expenses, the Judge noted that, had the Secretary consulted the Fisk

Descender Manual, he would have learned that one of the uses of a Fisk Descender is as a

positioning device. Moreover, had the Secretary consulted the Training Manual, he would have

learned that a secondary line with a rope grab is the most frequently used, but not the only

acceptable method of back-up when using a Fisk Descender. Both of these documents were

available to the Secretary and, with the exercise of reasonable diligence, he could have learned of

the multiple uses of a Fisk Descender and the appropriate use of back-up devices other than a

secondary line with rope grab. Much of the Secretary’s case was based on the testimony of the

CO which the judge found to be tainted by this fundamental misunderstanding of the Fisk

Descender; a misunderstanding that had no basis in fact and, as noted, could have been easily

cured by doing appropriate pre-hearing preparation.. Accordingly, the Judge found that the

Secretary lacked substantial justification and granted an award of EAJA fees and expenses.

   The parallels between the instant case and Paramount are striking. In both cases, the

backbone of the Secretary’s case was a fundamental misunderstanding of the procedure used at

the worksite and a failure to properly accurately read the instructions for the respective devices.

In both cases, the CO was inexperienced in the nature of the work and had he properly read those

instructions, he would have learned that the basis of the cases was erroneous. Here, the CO had
no field experience in installing pipes and had never conducted inspections dealing with water

pipe explosions or installations of mechanical joint assemblies for water pipes. Despite this lack

of experience, he testified that, in forming his opinion, he did not speak to any pipe or gland

manufacturers, or to any utility contractors.

   Similarly, in D.C. Pagers, Inc., d/b/a Superior Service, 19 BNA OSHC 1804 (No. 01-

0162, 2002, Judge Schoenfeld found a lack of substantial justification where the Secretary issued

the citation “without a sufficient understanding of the electrical equipment involved …, and on

his failure to fairly evaluate the employer’s training, both of which could have been discovered

well before the hearing with the exercise of reasonable diligence.” (emphasis added). On

another item, the judge noted that “[w]ith the exercise of reasonable diligence, the secretary,

through her solicitors, could have discovered well before the hearing that the CO’s conclusions

... were without a sound basis.” Id. at 1807.

   The evidence demonstrates that the Secretary did not exercise reasonable diligence

during its pre-hearing preparation leading up to the hearing in this case with regard to Item 1.

The evidence strongly suggests that the Secretary assumed that the accident ipso facto

established that a violation occurred and read both the AWWA and the manufacturer’s

instructions in a strained manner to support his theory of the case. The Secretary relied on the

CO and Mr. Shea who maintained a seriously flawed reading of the AWWA standard and the

manufacturer’s instructions. Had the Secretary exercised reasonable diligence during his pre-

hearing investigation, he would have learned that Armadillo was acting reasonably and in a

manner accepted by the industry. The record fails to establish that the Secretary took these

reasonable measures. For example, there is no indication that the Secretary or his expert spoke

with a representative of the mechanical joint restraining gland’s manufacturer who could, as a
representative did at the hearing, explain the nature of the work and why the Secretary’s theory

of the case was seriously flawed.5 Instead, the Secretary’s representatives and his expert

seemingly ascertained the particulars of pressure testing during the hearing and seemed

genuinely surprised that little more than tightening bolts to their maximum torque could stop a

leak without requiring dismantling the entire line.

     In the Answer to the EAJA Application, the Secretary makes several arguments, all of

which are unconvincing:

     1. As discussed supra, Mr. Shea disagreed with Armadillo that it is routine practice to

tighten bolts while the pipe is still under pressure. The Secretary argues that this Court

discounted Mr. Shea’s opinion and instead credited the testimony of Respondent’s non-expert

witnesses. He contends that had this Court credited Mr. Shea, he would have won the case.

Therefore, the case turned on a credibility finding. The Secretary notes that a case hinging on

credibility determinations are not typically eligible for an EAJA award. Consol. Constr., Inc., 16

BNA OSHC at 1006. (SOL Reply at p. 8).

     The Commission has held that cases that truly turn on credibility issues are inappropriate

for an EAJA award. Id. The key word is “truly.” While Armadillo’s witnesses were credited

over Mr. Shea, the Court’s findings were not based solely on the traditional credibility factors

uniquely within the province of the judge to evaluate, such as demeanor. Waste Mgmt. of Palm

Beach, 17 BNA OSHC 1308, 1309-10 (No. 93-128, 1995) (Giving deference to judge’s findings

based upon demeanor as those factors are peculiarly observable by the hearing judge at the

hearing.). Here, credibility was only incidental to this Court’s findings. This Court was more

persuaded by the overwhelming weight of the evidence that the pipes would be depressurized

5
The Secretary’s expert testified that he did not speak to any pipe or gland manufacturer, or to any utility contractor,
when formulating his opinion in this case. (Tr. 182-202).
and dismantled only when the bolts are already set to maximum torque. Another determining

factor in the decision was the Secretary’s obvious misreading of both the AWWA standards and

the manufacturer’s instructions and his erroneous assumption that they constituted mandatory

safety warnings rather than recommendations. See also Paramount Advanced Wireless, LLC, 23

BNA OSHC at 1637 (holding that the EAJA award of attorney’s fees and expenses appropriate

when witness credibility only incidental to findings.).

   2. The Secretary relies heavily on Young Sales Corp., 7 BNA OSHC 1297 (No. 8184,

1979), where the Commission found that a manufacturer’s warnings constituted an explicit

safety warning that establish recognition of a hazard. The Secretary asserts that here, rather than

analogizing the facts to Young Sales, the Commission erroneously cast this case in the mold of

Oberdofer Industries, Inc., 20 BNA OSHC 1321 (No. 97-0469, 2003), where a citation for

violation of § 5(a)(1) was vacated for lack of recognition because the relevant industry standard

did not establish that noncompliance with its instructions created a hazard. Id. at 1326-27.

Taking exception to the Commission decision on review here, the Secretary asserts that the

AWWA warning against overstressing the bolts by exceeding the maximum torque constituted

an implicit warning that overstressing the bolts could result in a catastrophic failure.

   Although the Secretary recognizes that, on review, the Commission rejected this

argument, he improperly attempts to re-litigate a finally decided issue in this EAJA application.

(SOL Reply at pp. 15-18). Cleaver v. Shinseki, No. 10-0830 E, 2013 WL 364212, at *2

(Vet.App. Jan. 31, 2013) (holding it improper for the Secretary of Veterans Affairs to attempt to

re-litigate a finally decided issue through an EAJA response); McCormick v. Principi, 16 Vet.

App. 407, 411 (2002) (ruling that the court should not revisit the logic of the merit’s decision at

the EAJA stage.); Abramson v. U.S., 45 Fed. Cl. 149, 153 (1999) (holding that application of the
EAJA “should not require the court to re-litigate the merits and reassess the competence of

defendant’s legal theories in terms not only of their legal merit, but also in terms of their margin

of failure.”); Nat’l. Law Ctr. on Homelessness and Poverty v. U.S. Dept. of Veterans Affairs, 799

F. Supp. 148, 152 (D.D.C., 1992) (“It is not the purpose of the EAJA to re-litigate issues that

have already been decided.”).

       Commission judges are bound to follow precedents set by the Commission. See Dun-

Par Engineered Form Co., No. 82-0928,1983 WL 142530, at *7 (O.S.H.R.C.A.L.J., June 17,

1983) (aff’d 12 BNA OSHC 1962 (1986). This Court is unwilling to hold that the Commission’s

decision in this case was erroneously decided.

       3. The Secretary asserts that he was reasonable in interpreting the instructions as a means

to avoid the failure of the bolts through overstressing, “which would logically mean that the bolts

might fail and lead to an explosion.” The problem with the Secretary’s position is that it relies

on assumptions, not evidence. There may be many reasons other than the possibility of

catastrophic failure why bolts should not be over tightened. For example, over tightening might

strip the bolts and make them difficult to remove if necessary. Also, it might crack or damage

the pipe leading to further leaks, rather than lead to a catastrophic failure.

       4. The Secretary’s cites to Exhibit C-17, which is a memorandum prepared by an AIM6

engineer and utility coordinator, requiring that the pressure rating for pipes be raised from 165

psi to 250 psi. The memorandum also stated that the “Recent incident was caused by improper

torque applied to mega lug. It is imperative that mega bolts be tightened in rotation with equal

torque to all bolts.” This memorandum was dated April 2, 2008, nearly four months before the

citation was issued. This memorandum has virtually no probative value and was not sufficient to

justify either the citation or the lack of diligence by the Secretary in her pre-hearing investigation
6
AIM was the inspection company at the job.
of this matter. Armadillo asserts that the memorandum was prepared to protect other parties in

litigation. The memorandum is little more than a short and conclusory statement attempting to

place blame of the accident on Armadillo. At the hearing, the Secretary did not make even a

cursory attempt to authenticate the memorandum. Neither of the authors testified, and the

Secretary made no attempt to establish methodology or the basis for the authors’ conclusion.

Despite its lack of probative value, the Secretary used this memorandum to support his

conclusion that Armadillo improperly tightened the bolts. (Tr. 40).

   Considering the Secretary’s fundamental misunderstanding of the leak stoppage

procedure, his misinterpretation of the relevant industry standards and manufacturer’s

instructions, and the lack of reasonable diligence in investigating these procedures and standards

prior to the hearing, the Court finds it difficult to find that the Secretary could have reasonably

expected that he could meet his burden of proof. The Secretary failed to show that: (1) there

existed a reasonable basis for the facts alleged, (2) there existed a reasonable basis in law for the

theory he propounds, and (3) the facts alleged reasonably supported the legal theory. Finally,

there is no evidence to suggest that an EAJA award would be unjust.

   Accordingly, the Court finds that the Secretary was not substantially justified in either

law or fact in issuing Item 1 for violation of the General Duty Clause. Armadillo is entitled to

recover its reasonable fees and expenses for defending itself against this item.

     B. Item 2- § 1926.20(b)(2)(deficiencies in the safety and health program were [not]
     identified to include hazard prevention and control, and worksite analysis)

    Because the item was withdrawn prior to the hearing, the Secretary never put on any

evidence directly relevant to the item. Neither did the Secretary provide any explanation for the

withdrawal. However, at the hearing the Secretary introduced evidence directed at Item 1 that

does explain the reason why Item 2 was issued:
1. During the inspection, employees were not able to explain to the CO the procedure

used to stop the leak. (Tr. 35).

   2. Respondent’s foreman, Mr. Davis, could not describe the AWWA standard. (Tr. 38).

   3. Mr. Davis was also unfamiliar with the manufacturer’s specifications. (Tr. 38).

   4. When discussing the daily safety meetings held with the crew, Mr. Davis could not

locate any meetings where the topic involved dealing with a leak when a pipe is under pressure.

(Tr. 147).

    Armadillo counters that this Court’s December 14, 2009 decision complimented it on its

training program. The decision noted that “Mr. Davis testified he had worked with the same

crew for over six months before the accident. He trained the crew, including in tightening bolts.

He checked their work by watching them and by using a torque wrench at times to check bolts

they had tightened.”

   The decision concluded that Armadillo takes safety very seriously. In particular, it was

noted that Mr. Davis’ holds safety meetings in the field and has received safety training and

certifications while working for Armadillo. The decision also took note of the evidence regarding

the safety orientation and training employees receive, the safety meetings held in the field, and

the site inspections conducted by Armadillo’s management and outside safety consultants. The

decision also noted that although Mr. Davis was somewhat familiar with the AWWA, he could

not explain or define AWWA. He had not reviewed, or been trained in, the AWWA standards.

He was not aware of an AWWA procedure to disassemble a pipe if the pipe had not attained an

effective seal, and he had no knowledge of AWWA describing a recommended procedure. He

was also not aware of a written pressure test procedure, but he described the unwritten procedure

he followed in the field. (Tr. 93-94, 113-14, 117-19, 142-49, 208-18, 275-78).
Even though the AWWA standards are voluntary, it was not unreasonable for the

Secretary to expect that Armadillo’s employees be familiar with them. The Occupational Safety

and Health Administration’s belief that Armadillo’s employees, including the foreman, were

uninformed about the AWWA is suggestive of improper training.7 It was not unreasonable for

the Secretary to issue the citation for Item 2 on the grounds that employees were improperly

trained. Armadillo asserts that, even if justified in issuing the Item 2 citation, the Secretary was

not justified in not waiting to withdraw it until the start of the hearing. Armadillo suggests that

the Secretary should have realized that the item was untenable upon review of Armadillo’s safety

materials. (EAJA Application at p. 17).

     That the Secretary withdrew a citation prior to hearing does not create the presumption

that he was not substantially justified. Ashburn v. United States, 740 F.2d 843, 850 (11th Cir.

1984). Rather, withdrawing a citation item is the proper action to avoid liability under the EAJA

when the Secretary is initially justified in issuing the item, but later discovers that her position

lacks substantial justification. See K.D.K. Upset Forging, Inc., 12 BNA OSHC 1856, 1859 (No.

81-1932, 1986).

      In his Opposition to the Fee Award, the Secretary asserts that the decision to withdraw

Item 2 was made following a final review of the item in an effort to streamline the issues to be

presented at the hearing. The Court finds the Secretary’s explanation to be reasonable. The

Court finds that the Secretary was substantially justified in both issuing Item 2 and in

withdrawing the item at the beginning of the hearing.

                                                     Fee Award

     Armadillo submits attorney fees and expenses dating from the time of the accident. Fees

7
As part of OSHA’s pre-citation investigation, the CO interviewed the crew members and foreman that had been
injured. The crew members were not able to explain to the CO the procedure they had used and stated that the day
of the accident was the first time they had tightened the bolts with the pipe pressurized. (See ALJ Decision, at p. 4).
and expenses are recoverable only from the beginning of the adversary adjudication. For

proceedings before the Commission, the adversary adjudication begins with issuance of the

citation in most cases. Cent. Brass Mfg. Co. 14 BNA OSHC 1904, 1906 (No. 86-978,

1990)(consolidated). To allow fees for legal services incurred before issuance of the citation

would be tantamount to holding that the Secretary was not substantially justified in investigating

a workplace injury. Armadillo is not entitled to any fees and expenses incurred before the

citation was issued on July 21, 2008.

   To determine an appropriate award, the judge must determine the “lodestar,” which is the

number of hours reasonably expended multiplied by a reasonable hourly rate. Action on

Smoking & Health v. C.A.B., 724 F.2d 211, 221 (D.C. Cir. 1984). When determining the

“lodestar” the judge should consider the complexity and novelty of the issues based on his own

knowledge, experience and expertise of the time required to complete similar activities. Cent.

Brass Mfg. Co., 14 BNA OSHC at 1907; William B. Hopke, 12 BNA OSHC 2158, 2160 (No. 81-

206, 1986).

   In support of its petition, Armadillo has submitted detailed billings setting forth the

relevant fees and expenses. The Court finds the hourly billings submitted by Armadillo’s

attorneys’ are reasonable given the complexity of the issues in this case. However, the invoices

do not indicate which hours were relevant to Item 1, and which were pertinent to Item 2. Finding

that Armadillo is only entitled to fees and expenses incurred in its defense of Item 1, it is

necessary to determine an appropriate apportionment of the fees and expenses incurred.

   To prepare for Item 2, Armadillo needed to gather its training materials and documents

relating to its training programs. Because the item was not withdrawn until the start of the

hearing, it also had to interview and prepare its witnesses. The pre-hearing witness lists show
that Armadillo intended to call several employees who were to testify largely about their

training. Armadillo also intended to introduce several documents related directly to its training

program. It is reasonable that Armadillo spent some time preparing witnesses to testify directly

to Item 2. A significant portion of Armadillo’s case revolved around its training of employees to

stop leaking pipes, which was also relevant to Item 1. Even if Item 2 had never been cited,

Armadillo would have adduced some evidence related to its training program.

    Item 1 was the far more complex of the two items. It required statutory interpretation,

learning the procedures and techniques involved in leak repair and relating those procedures and

techniques to the accident. Considering these factors, the Court concludes that 20% of the

claimed attorney fees and compensable expenses incurred prior to the hearing are reasonably

allocated to Armadillo’s preparation to defend Item 2. Hensley v. Eckerhart, 461 U.S. 424, 436-

37 (1983) (noting that the court may use its equitable judgment in eliminating hours for

noncompensable hours).

    In his opposition to the Fee Application, the Secretary states that Respondent seeks to

recover “non-compensable items on its “expenses” sheets.” (Opposition at p. 23). However, he

fails to specify which of the expenses are non-compensable. The EAJA states, in pertinent part

that:

    “fees and other expenses” includes the reasonable expenses of expert witnesses,
    the reasonable cost of any study, analysis, engineering report, test, or project
    which is found by the agency to be necessary for the preparation of the party’s
    case, and reasonable attorney or agent fees.

5 U.S.C. § 504(b)(1)(A).

    The Commission has held that the list of compensable expenses set forth in the 5 U.S.C.

§ 504(b)(1)(A) are only examples and that other costs such as travel and transcript expenses are

compensable. Ruhlin Co., 17 BNA OSHC 1068, 1069 (No. 93-1507, 1995) (EAJA)
(Commission held that EAJA awards include “the reasonable and necessary expenses of an

attorney in a specific case which are customarily charged to the client.”). This issue arose in the

11th Circuit which similarly holds that the list of expenses provided in 28 U.S.C. § 2412(d)(2)(A)

was not meant to be all-inclusive. Jean v. Nelson, 863 F.2d 759, 777 (11th Cir. 1988), aff’d 496

U.S. 154 (1990), Hoopa Valley Tribe v. Watt, 569 F. Supp. 943, 947 (N.D. Cal. 1983).

Respondent lists travel expenses, including parking and travel meals, which this Court finds to be

reasonable and compensable under the EAJA. Accordingly, this Court awards fees and expenses

as follows:

A. Attorney Fees and Expenses expended before Judge

  1. Attorney Fees

a) Pre-citation fees (before 7/21/2008) (invoices from 5/20/2008 to 5/30/2008): $1,022.50

                                                                                 Compensable:        0.00

b) Fees from 7/21/2008 up to hearing date (invoices from 7/31/2008 - 4/16/2009 for hours

expended through March 29, 20098):

       claimed 126.25 hours @ $125 = $15,781.25, compensable at 80% =                           $12,625.00

c) Fees incurred from the hearing date through the filing of briefs to the Judge (invoices

from 4/16/2009 through 12/31/2009 for hours expended from 3/30/2009 – 12/14/2009 date of

ALJ Decision):

       Fully compensable 67.25 hours @ $125 =                                                    $8,406.25

                                            Recoverable attorney fees before judge: $21,031.25
  1. Expenses:

8
The withdrawal of Item 2 occurred at the start of the trial on March 30, 2009.
a) Expenses prior to citation: $748.419

                                                                               Compensable:             0.00

b) Expenses from citation to hearing: $ 863.23, compensable @ 80% = $690.58

c) Fully compensable expenses from hearing on: $1,169.1410

                                                Compensable expenses before judge: $1,859.72

B. Costs on Review Before the Commission

       Armadillo included the time and expense sheets for its work done when the case was

reviewed by the Commission.11 In its billings from 12/31/2009 to 4/19/2010, Armadillo sets

forth 43 hours devoted to its work on Review before the Commission which, at $125 per hour,

comes out to $5,375. Additionally, Respondent lists $32 in postage charges. This comes out to a

total of $5,407. An ALJ has the authority to determine a fee award that includes fees and

expenses expended on review before the Commission. See Saipan Koreana Hotel, 21 BNA

OSHC 1403, 1406 (No. 02-2129, 2006) (Judge can assess reasonableness of EAJA request where

company entitled to the award of fees incurred in matter pending before Commission).

                Attorney Fees and expenses for work before the Commission:                        $5,407.00

C. Attorney Fees/Expenses of EAJA Petition

       Fees incurred preparing a petition for fees and costs under EAJA are compensable.

Timothy Victory, 18 BNA OSHC 1023, 1027-28 (No. 93-3359, 1997); See also Gonzalez v. City

of Maywood, 729 F.3d 1196, 1210 (9th Cir. 2013) (finding that fees and expenses incurred in

preparing fee petition under Civil Rights Act are compensable).

9
This amount is calculated as follows: $408.42 + $369.49 - $29.50 non-billing, including 2/23 airfare.
10
The April 30, 2009 invoice for attorney fees also includes $1,024.29 identified as “Court Costs/Fees.” The
expense sheets show that this amount is for the hearing transcript ($1,021.65) and a pre-hearing phone call made on
3/15/09 ($2.64). This Court treats costs relating to the transcript and phone call as expenses and not attorney fees.
11
Armadillo’s did not specifically list those fees and expenses in its summary sheet.
Armadillo is entitled to recover for its preparation of the EAJA petition as to Item 1. It is

not entitled to recover for the attorney fees and expenses incurred in its preparation of the

petition as to Item 2, which includes Armadillo’s presentation of the reasons why it alleged that

the Secretary was not substantially justified in issuing Item 2. As before, the Court finds that

20% of the fees and expenses spent in preparing the EAJA petition as to Item 2 represent a

reasonable allocation of the expended costs.

   In its EAJA petition, Respondent lists fees and expenses from its invoice of 4/8/2013,

which was for costs associated with the EAJA application.

   Attorney Fees 13.25 hours at $125 =            $1,656.25 @ 80% =                $1,325.00

   Expenses (copying and mailing):                $94.00 @ 80% =                      $75.20

   Review of the various billings sent by Armadillo’s attorney also reveals that certain

preliminary work in anticipation of a future EAJA application was performed while the case was

still in litigation. The billing of 12/31/2009 lists a total of 1.5 hours spent on work compiling

material for the preparation of a future fee award application. The billing of 1/15/2010 lists a

total of two hours similarly spent. At $125 per hour, these 3.5 hours yield a total of $437.50.

This Court finds that Armadillo is entitled to recover 80% of these fees as part of its recovery for

the preparation of its EAJA petition, or $350.00.

   Attorney Fees 3.5 hours @ $125 = $437.50 @ 80% =                                   $350.00

   Accordingly, the Court awards the following to Armadillo for costs incurred in the

preparation of its EAJA petition:

                                                   Compensable Attorney Fees:       $1,675.00
                                                   Compensable Expenses:               $75.20

   Attorney fees and expenses for the preparation of EAJA Petition:                 $1,750.20

ORDER

   Accordingly, Complainant is ORDERED to compensate Respondent in the amount of

$30,048.17 for attorney fees and expenses pertaining to this case that the Court finds are justly
due pursuant to the EAJA.
SO ORDERED.

                                            /s/
                                            The Honorable Dennis L. Phillips
                                                 U.S. OSHRC JUDGE

Date: Dec. 9, 2013
Washington, DC

Get today's answer for your situation

You just read what one judge decided for one employer in 2014, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.