New Blue Shield Construction Inc.
Six-month filing delay was not excusable neglect
Apply this to your situation
This order from 2007 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
OSHA inspected a New Blue Shield Construction work site in the Bronx and issued a citation on August 8, 2006. The company did not file a notice of contest by the 15-working-day deadline, then waited nearly six months after OSHA explained the late-contest procedure before writing to the Commission. The company attributed the delay to attempted negotiations, corrective work, and a miscommunication about retaining counsel. The judge found that those circumstances did not excuse the delay and that the company had control over timely handling of the citation. The Secretary's motion to dismiss was granted, relief was denied, and the citation was affirmed in all respects.
Decision snapshot
- Cited standard(s): No specific OSHA standard number is identified in the decision.
- Outcome: The late notice of contest was dismissed, and the citation was affirmed in all respects.
- Key point: Waiting nearly six months after learning how to file a late contest was not excusable neglect under Federal Rule of Civil Procedure 60(b).
Full text (OSHRC public release)
United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington, DC 20036-3457
SECRETARY OF LABOR, :
:
Complainant, :
:
v. : OSHRC DOCKET NO. 07-0455
:
NEW BLUE SHIELD CONSTRUCTION, :
INC., :
:
Respondent. :
Before: Chief Judge Irving Sommer
DECISION AND ORDER
This matter is before the Occupational Safety and Health Review Commission (“the
Commission”) pursuant to section 10(c) of the Occupational Safety and Health Act of 1970, 29
U.S.C. § 651 et seq. (“the Act”), for the purpose of determining whether Respondent’s late-filed
notice of contest (“NOC”) should be accepted pursuant to Federal Rule of Civil Procedure 60(b).
Background
The Occupational Safety and Health Administration (“OSHA”) inspected a work site of
Respondent, New Blue Shield Construction, Inc., located in the Bronx, New York, from February
to June 2006. As a result, OSHA issued to Respondent a Citation and Notification of Penalty
(“Citation”) on August 8, 2006. On August 8, 2006, the OSHA compliance officer (“CO”) who had
inspected the site hand-delivered the Citation to Respondent’s vice-president, David Snir, and Mr.
Snir signed a certification he had received the Citation. Section 10(a) of the Act requires an employer
to notify the Secretary of its intent to contest a citation within 15 working days of receipt, and the
failure to file a timely NOC results in the citation becoming a final order of the Commission by
operation of law. Based on the date it received the Citation, Respondent was required to file an NOC
on or before August 29, 2006. However, Respondent did not file an NOC by that date. On September
6, 2006, the OSHA CO contacted Mr. Snir and John Aburus, Respondent’s president, and requested
that the company submit documentation of abatement of the violations set out in the Citation. On
September 18, 2006, OSHA received a letter verifying abatement of the cited conditions. On
September 29, 2006, OSHA contacted Mr. Aburus to set up a payment plan in regard to the penalty
due; OSHA also advised Mr. Aburus of the procedure to file a late NOC directly with the
Commission. A copy of the payment plan was faxed to Mr. Aburus. On March 9, 2007, Respondent
filed an NOC letter with the Commission that set out the reasons for the late filing and requested an
appeal of this matter. On May 25, the Secretary filed a motion to dismiss Respondent’s late notice
of contest. On July 13, 2007, Respondent filed an affidavit and an affirmation in opposition to the
motion to dismiss, and on July 24, 2007, the Secretary filed a reply.
Discussion
The record in this case plainly shows that Respondent did not file its NOC within the
requisite 15-day period set out in the Act. However, an otherwise untimely NOC may be accepted
where the delay in filing was caused by deception on the part of the Secretary or her failure to follow
proper procedures. A late filing may also be excused, pursuant to Federal Rule of Civil Procedure
60(b) (“Rule 60(b)”), if the final order was entered as a result of “mistake, inadvertence, surprise or
excusable neglect” or “any other reason justifying relief” including “circumstances such as absence,
illness, or a similar disability [that would] prevent a party from acting to protect its interests.” See
Branciforte Builders, Inc., 9 BNA OSHC 2113, 2117 (No. 80-1920, 1981) (citations omitted). The
moving party has the burden of proving that it is entitled to Rule 60(b) relief.
There is no allegation, and no evidence, that the delay in filing in this case was due to
deception on the part of the Secretary or her failure to follow proper procedures. However,
Respondent’s letter of March 9, 2007, will be construed to be a request for relief pursuant to Rule
60(b) on the basis that its failure to file a timely NOC was due to excusable neglect.
In determining whether an employer’s failure to file a timely NOC was due to excusable
neglect, the Commission follows the Supreme Court’s test in Pioneer Inv. Serv. v. Brunswick Assoc.
Ltd. P’ship, 507 U.S. 380 (1993). See Northwest Conduit Corp., 18 BNA OSHC 1948, 1950 (No.
97-851, 1999). Under that test, the Commission takes into account all relevant circumstances,
including the danger of prejudice to the opposing party, the length of the delay and its potential
2
impact on judicial proceedings, the reason for the delay, including whether it was within the
reasonable control of the movant, and whether the movant acted in good faith. Id. at 1950, quoting
507 U.S. at 395. The Commission has held that the “reason for the delay, including whether it was
within the reasonable control of the movant,” is a “key factor” and, in appropriate circumstances, the
dispositive factor. A.W. Ross, Inc., 19 BNA OSHC 1147, 1148 (No. 99-0945, 2000); Calhar Constr.,
Inc., 18 BNA OSHC 2151, 2153 (No. 98-0367, 2000).
In this case, Respondent did not file an NOC until nearly six months after OSHA advised it
of the procedure to file an NOC directly with the Commission. I agree with the Secretary that this
delay is patently unreasonable, and I further agree that accepting the late-filed NOC in these
circumstances would prejudice the Secretary, given the extended period of time that has elapsed.
While I find no particular impact on judicial proceedings, I do question Respondent’s good faith, in
light of the amount of time that passed before Respondent sent its letter to the Commission.
As to the reason for the delay, Respondent’s counsel states in the March 9, 2007 letter that
her client did not file the NOC within the 15-day period because he was negotiating with OSHA in
an attempt to resolve this matter.1 The Secretary disputes this statement, pointing out that OSHA
contacted Respondent in September 2006, after the Citation was already a final order. The March
9 letter also states that Respondent was buying new equipment and educating its workers in regard
to the cited conditions. Respondent did certify that it had abated the cited conditions, based on the
letter OSHA received on September 18, 2006. However, this fact does not explain or excuse the
almost six-month delay in filing the NOC. Finally, the March 9 letter states that while Respondent
had contacted counsel in September or October of 2006, counsel was only recently retained due to
“miscommunication.” Again, this circumstance does not excuse a nearly six-month delay in filing.
As to whether the delay was within the reasonable control of Respondent, I find that it was.
The Citation itself, on page 2 and in bold letters, advised Respondent the NOC was required to be
filed within 15 working days of receipt. The Commission has held that the OSHA citation clearly
states the requirement to file an NOC within the prescribed period and that an employer “must bear
the burden of its own lack of diligence in failing to carefully read and act upon the information
1
The circumstances set out in the March 9 letter also appear in the affidavit submitted by
Respondent.
3
contained in the citations.” Roy Kay, Inc., 13 BNA OSHC 2021, 2022 (No. 88-1748, 1989); Acrom
Constr. Serv., Inc., 15 BNA OSHC 1123, 1126 (No. 88-2291, 1991). The Commission has also held
that ignorance of procedural rules does not constitute “excusable neglect” and that mere carelessness
or negligence does not justify relief. Acrom Constr. Serv., Inc., 15 BNA OSHC 1123, 1126 (No. 88
2291, 1991); Keefe Earth Boring Co., 14 BNA OSHC 2187, 2192 (No. 88-2521, 1991). Finally, the
Commission has held that a business must maintain orderly procedures for the handling of important
documents and that when the lack of such procedures results in an untimely NOC, the late filing will
be deemed to be simple negligence and not excusable neglect. Louisiana-Pacific Corp., 13 BNA
OSHC 2020, 2021 (No. 86-1266, 1989).
Based on the foregoing precedent and the circumstances of this case, I find that the failure
to file a timely NOC was due to simple negligence and not to excusable neglect within the meaning
of Rule 60(b). There is accordingly no justification for the granting of relief in this matter. The
Secretary’s motion to dismiss is GRANTED, the request for relief is DENIED, and the Citation is
AFFIRMED in all respects.2 SO ORDERED.
/s/
Irving Sommer
Chief Judge
Dated: August 10, 2008
Washington, D.C.
2
In support of its claim it is entitled to relief, Respondent contends the citations in this
matter were not willful and repeated as it had not been previously cited by OSHA. However, as
the Secretary notes, this contention is at best a meritorious partial defense; having a meritorious
defense to a Citation is an additional element an employer must show after it has shown its late
filing was excusable neglect. As found here, the late filing was not excusable neglect.
4
Get today's answer for your situation
You just read what one judge decided for one employer in 2007, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.