🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC Commission decision Docket 05-0652 Decided June 9, 2006 Modified

Smoot Construction

Scaffold and trench violations affirmed with penalty reduction

Apply this precedent to your situation

This is citable Commission precedent from 2006, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2006
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Smoot was the prime contractor on a university construction project where employees worked from incompletely planked scaffolds and a subcontractor's employees entered an inadequately sloped trench. The Commission held that the full-planking exception did not apply because Smoot's employees were performing form work as well as erecting the scaffold. It also held Smoot responsible for the trench because Smoot created the noncompliant condition and failed to prevent a second subcontractor entry after learning of the first. The Commission affirmed the serious scaffold and trench violations, including the judge's midrail ruling. Because OSHA withdrew one instance of the planking item on review, the Commission reduced that item's penalty to $750 and assessed $1,875 for the trench item.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.451(b)(1); 29 C.F.R. § 1926.451(g)(4)(iii); 29 C.F.R. § 1926.652(a)(1)
  • Outcome: Three serious violations were affirmed; the planking penalty was reduced to $750, the midrail penalty remained $500, and the trench penalty remained $1,875.
  • Key point: A contractor that creates a hazardous trench remains responsible for exposed subcontractor employees, especially after learning that they have entered it.

Full text (OSHRC public release)

Smoot Construction, Docket No. 00-0336

DECISION

SECRETARY OF LABOR,

Complainant,

v.

OSHRC Docket No. 05-0652

SMOOT CONSTRUCTION.,

Respondent.

APPEARANCES:

Lee Grabel, Attorney; Charles F. James, Counsel for Appellate Litigation;
Joseph M. Woodward, Associate Solicitor; Howard M. Radzely, Solicitor;
U.S. Department of Labor, Washington, DC

For the Complainant

Jan E. Hensel, Esq., Buckingham, Doolittle & Burroughs, LLP

For the Respondent

DECISION

Before: RAILTON, Chairman; and ROGERS, Commissioner.

BY THE COMMISSION:

Before the Review Commission is a decision of Administrative Law Judge
Ken S. Welsch. Smoot petitioned for review of the judge’s findings and
conclusions that it seriously violated three Occupational Safety and Health
Administration (OSHA) standards. It was cited for not fully planking a scaffold in
violation of 29 C.F.R. § 1926.451(b)(1). It was also cited for not using mid rails
on the scaffold in violation of 29 C.F.R. § 451(g)(4)(iii). Lastly it was cited for not
fully protecting the side walls of a trench in violation of 29 C.F.R.
§ 1926.652(a)(1). For the reasons given below we affirm the judge’s decision.

STATEMENT OF FACTS AND ISSUES

The Scaffold

OSHA’s CSHO Richard Burns observed Smoot’s employees working from
a scaffold. They were also constructing formwork for a building under
construction. According to Smoot, the scaffold was of a type that is raised as the
formwork is raised. Smoot concedes that the scaffold in question was not fully
planked as section 1926.451(b)(1) requires, but argues that it was exempt from the
full planking requirement because the scaffold was under construction as it raised
the formwork.

The Trench

During the course of his inspection CSHO Burns observed an employee of
subcontractor Midwest Reinforcing Contractors (“Midwest”) “surfing” down the
slope of a trench to retrieve a tool. The CSHO was accompanied on his inspection
by Smoot safety director Angelo Giannakos. Mr. Giannakos also observed the
actions of the Midwest employee. Smoot’s representative immediately issued
orders to remove the employee from the trench. Later that day, CSHO Burns
observed two other Midwest employees in the same trench. The trench was
created two days earlier when Smoot erected formwork along one side wall of the
trench. It also created an egress ramp from the trench. The other side wall – the
one used for surfing by the Midwest employee – was sloped in part but not to the
degree required by OSHA’s standards.

Smoot claims that it could not have known that premature entries into the
trench would be made by Midwest’s employees. Midwest was the ironworker
subcontractor for Smoot and was responsible for installing the rebar for the form
walls. The Secretary claims that Smoot, as a general contractor, was responsible
for the entries by Midwest employees.

ANALYSIS

The Scaffold Violation

The language of the exception to compliance with the requirements of the
cited scaffold standard provides as follows:

Exception to paragraph (b)(1): The requirement in paragraph (b)(1) to
provide full planking or decking does not apply to platforms used solely as
walkways or solely by employees performing scaffold erection or
dismantling. In these situations, only the planking that the employer
establishes is necessary to provide safe working conditions is required.

29 C.F.R. § 1926.451(b)(1).

We find that the plain language of the regulation supports the interpretation
used by the judge and advanced by the Secretary. See Unarco Commercial Prods.,
16 BNA OSHC 1499, 1502-03, 1993-95 CCH OSHD ¶ 30,294, pp. 41,732-33
(No. 89-1555, 1993). The phrase used in the exception relied upon by Smoot,
“employees performing scaffold erection or dismantling” is modified by the term
“solely.” In our view, the modifier applies only to employees on scaffolding
whose sole work activity is the erection or dismantling of the scaffold. Additional
work done or performed while the employees are on the scaffold renders the
exception inapplicable.

It is undisputed that Smoot’s employees were also performing formwork in
addition to the scaffold erection work. The exception to the requirement of
paragraph (b) to fully plank the scaffold does not apply on the facts of this case.
Accordingly, we affirm the violation of 29 C.F.R. 1926.451(b)(1).

The Trenching Violation

It is undisputed that two days prior to the OSHA inspection Smoot placed
formwork into an existing excavation creating a trench that did not comply with
the requirements of 29 C.F.R § 1926.652(a)(1). The formwork created one
sidewall of the trench. The other sidewall was partially sloped but not to the
degree required for type C soil. Smoot does not rebut the Secretary’s allegation of
non-compliance. It also does not dispute the fact that Midwest employees were
exposed to the violative condition on two occasions during OSHA’s inspection.
Smoot only contends that it was not responsible for the entries by employees of
Midwest. It also argues that it took proper precautions to avoid those entries.
Smoot’s arguments are not persuasive.

The Commission has long held that the employer who creates a violative or
hazardous condition is obligated to protect its own employees as well as
employees of other contractors who are exposed to the hazard. We find that our
decision in Flint Engineering & Construction Co., 15 BNA OSHC 2052, 2055,
1993 CCH OSHD ¶29,923, p. 40,853 (No. 90-2873, 1992) is dispositive.

In Flint , as in this case the contractor created the non-compliant trench. In
Flint , as in this case, the contractor argued it lacked knowledge of the exposure of
a subcontractor’s employees. In Flint , we held the contractor liable because it
created the violative conditions. Similarly, we hold here that Smoot was
responsible for creating the non-compliant conditions and is responsible for the
violation.

Smoot argues, however, citing and contrasting Flint , that it took adequate
measures to prevent entry into the non-compliant trench. It is undisputed that
during the course of the inspection, Midwest employees entered the trench on at
least two occasions, separated by an hour to an hour and a half. The fact that the
second entry occurred, in light of Smoot’s full awareness of the first entry,
indicates that Smoot’s actions to keep Midwest employees out of the trench were
inadequate.

Accordingly, we affirm the violation of § 1926.652(a)(1).

Penalty

Smoot does not challenge the characterization of the citations as serious or
the assessed penalties. The Secretary withdrew instance a of item 1 on review,
however, so we reduce the penalty for item 1 on a pro rata basis because there is
no significant gravity difference between instances a and b of item 1. Therefore,
we assess a penalty of $750 for item 1 and $1,875 for item 4.

SO ORDERED.

/s/____

W. Scott Railton

Chairman

/s/____

Thomasina V. Rogers

Dated:     June 9, 2006                                       Commissioner

Secretary of Labor,

Complainant,  

v.

OSHRC Docket No. 05-0652

Smoot Construction,

Respondent.

Appearances:

Linda M. Hastings, Esq., U. S. Department of Labor, Office of the Solicitor, Cleveland, Ohio

For Complainant

Jan E. Hensel, Esq., Buckingham, Doolittle & Burroughs, Columbus, Ohio

For Respondent

Before: Administrative Law Judge Ken S. Welsch

DECISION AND ORDER

On March 17, 2005, Occupational Safety and Health Administration (OSHA)
compliance officer Richard Burns inspected a construction site supervised by Smoot
Construction in Athens, Ohio. On March 30, 2005, the Secretary issued a citation to
Smoot alleging serious violations of six construction standards under the Occupational
Safety and Health Act of 1970 (Act), regarding an inadequate scaffold and an unsafe
excavation. Smoot timely contested the citation and penalties. On May 18, 2005, the
Review Commission designated this case for EZ Trial under 29 C.F.R. § 2200.200 of the
Act.

Prior to the hearing, the Secretary withdrew items 2b, 3, and 5 of the citation
(alleging violations respectively of 29 C.F.R. §§ 1926.502(b)(2), 651(k)(1), and
1053(b)(16). Items 1, 2a, and 4 (alleging violations respectively of 29 C.F.R. §§
1926.451(b)(1), 451(g)(4)(iii), and 652(a)(1)) remain at issue. The court heard this case
on July 8, 2005, in Columbus, Ohio. The parties submitted post-hearing position
statements.

ISSUES

The Secretary contends Smoot violated the remaining three cited standards. The
issues are:

(1) Item 1–Did Smoot violate § 1926.451(b)(1) by failing to fully deck or plank
scaffold platforms?

(2) Item 2a–Did Smoot violate § 1926.451(g)(4)(iii) by failing to install structural
members between the top edge of a guardrail and a platform?

(3) Item 4– Did Smoot violate § 1926.652(a)(1) by failing to use an adequate
protective system to prevent a cave-in in an excavation?

Smoot argues its employees were erecting the scaffold at the time of the
inspection, so the cited scaffolding standards do not apply. Smoot also argues a
subcontractor assumed responsibility for the safety of the excavation. Smoot withdrew
its affirmative defenses of greater hazard and infeasibility during the hearing (Tr. 64).

FINDINGS OF FACT

The Secretary established the following facts by a preponderance of the evidence.

In March 2005, Smoot, as prime contractor, supervised its own employees and
several subcontractors constructing a new student union building for Ohio University in
Athens, Ohio. Smoot’s crew, along with the crews of other subcontractors, performed
form work on the project (Tr. 140). The student union building site covers five acres.
Smoot project superintendent Rodney Nelson described the building as a parking garage
“about one football field wide and three football fields long,” with “a six-story building
sitting on top of that” (Tr. 87).

Smoot and its subcontractors had completed approximately one-quarter of the
project’s construction when compliance officer Burns arrived at the site on March 17,
2005. Burns’s inspection was a programmed inspection based on the University of
Tennessee’s Dodge Report, which generates a random list of companies to be inspected
each month (Tr. 11-12). Burns arrived at approximately 9:30 a.m., and, at Smoot’s
request, waited for one hour until Smoot safety superintendent Angelo Giannakos arrived
at the site. Burns then held an opening conference with Giannakos and project
superintendent Nelson. Burns conducted employee interviews and photographed various
areas of the site, including scaffolding in the southeast stairwell and an excavation next to
the building. He held a closing conference with Giannakos and Nelson around 4:30 that
afternoon (Tr. 12-13).

PRINCIPLES OF LAW

To prove a violation of an OSHA standard, the Secretary must show by a
preponderance of the evidence that (1) the cited standard applies, (2) there
was noncompliance with its terms, (3) employees had access to the
violative conditions, and (4) the cited employer had actual or constructive
knowledge of those conditions.

Southwestern Bell Telephone Co., 19 BNA OSHC 1097, 1098 (No. 98-1748, 2000).

The Secretary alleges Smoot violated the following construction standards:

Item 1–§ 1926.451(b)(1)

Each platform on all working levels of scaffolds shall be fully planked or
decked between the front uprights and the guarded supports as follows:

(i) Each platform unit (e.g., scaffold plank, fabricated plank,
fabricated deck, or fabricated platform) shall be installed so that the space
between adjacent units and the space between the platform and the
uprights is no more than 1 inch (2.5 cm) wide, except where the employer
can demonstrate that a wider space is necessary (for example, to fit around
uprights when side brackets are used to extend the width of the platform).

(ii) Where the employer makes the demonstration provided for in
paragraph (b)(1)(i) of this section, the platform shall be planked or decked
as fully as possible and the remaining open space between the platform
and the uprights shall not exceed 9½ inches (24.1 cm).

Exception to paragraph (b)(1): The requirement in paragraph (b)(1)
to provide full planking or decking does not apply to platforms used solely
as walkways or solely by employees performing scaffold erection or
dismantling. In these situations, only the planking that the employer
establishes is necessary to provide safe working conditions is required.

Item 2a– § 1926.451(a)(4)(iii)

When midrails, screens, mesh, intermediate vertical members, solid
panels, or equivalent structural members are used, they shall be installed
between the top edge of the guardrail system and the scaffold platform.

Item 4–§ 1926.652(a)(1)

Each employee in an excavation shall be protected from cave-ins by an
adequate protective system designed in accordance with paragraphs (b) or
(c) of this section.

The Secretary alleges the violations committed by Smoot were serious. Under §
17(k) of the Act, a violation is serious “if there is a substantial probability that death or
serious physical harm could result from” the violation.

[T]he Secretary need not establish that an accident is likely to occur in
order to prove that the violation is serious. Rather [s]he must show that
“an accident is possible and there is a substantial probability that death or
serious physical harm could result from the accident.” Consolidated
Freightways Corp., 15 BNA OSHC 1317, 1324, 1991 CCH OSHD
P29,500, p. 39,813 (No. 86-351, 1991)[.]

Flintco, Inc., 16 BNA OSHC 1404, 1405 (No. 92-1396, 1993).

ANALYSIS

Item 1: Alleged Serious Violation of § 1926.451(b)(1)

Item 1 alleges two instances of Smoot violating this standard:

a. In the southeast stairwell where carpenters worked on carpenters
scaffold, the scaffold was not fully planked and there was a nine and a half
inches opening to the back of the scaffold.

b. In the south stairwell where carpenters built forms on the carpenter
scaffold, there was [an] approximately two foot opening in the planking.

1. Application of Standard

Section 1926.450(a), the scope and application section of Subpart L
(Scaffolds) of the construction standards, provides Subpart L “applies to all scaffolds
used in workplaces covered by this part.” Section 1926.450(b) defines “scaffold” as “any
temporary elevated platform (supported or suspended) and its supporting structure
(including points of anchorage) used for supporting employees or materials or both.”
The cited standard applies to the scaffold at issue.

2. Noncompliance with Terms of the Standard

Burns photographed the 9½ inch opening at the back of the exterior scaffold in
the southeast stairwell (Exhs. C-2 and C-3) and the 2-foot opening in the planking on the
interior platform (Exhs. C-4 and C-5). Smoot does not dispute the existence of the
openings in the platforms of the scaffolds. Smoot contends the exception to paragraph
(b)(1) applies in this case because Smoot’s employees were in the process of erecting the
scaffolds cited in instances (a) and (b).

Burns observed Smoot carpenter foreman Larry Danileson and other employees
standing on the exterior scaffold performing form work for the stairwell (Tr. 17-18).
Danielson explained at the hearing that the scaffolding and form work proceed
simultaneously (Tr. 161): “[T]he scaffold goes up as the wall goes up.” Burns also
observed Smoot employee Darwin May performing form work while standing on the
interior scaffold with the 2-foot opening in the planking. He interviewed May, who told
Burns he did not know why the board had been pulled out, exposing the opening (Tr. 25).

In its post-hearing statement, Smoot acknowledges its employees were
performing form work while standing on the cited scaffolds (Smoot’s statement, p. 7):
“[Erecting a scaffold] is a fluid process: the form wall is erected, the scaffold is set; the
second panel of the form is added and the scaffold is then raised to the next level.”

Danielson testified the scaffold, though incomplete, was safe for his carpenter crew to
stand on while performing form work (Tr. 162-163): “I feel it was completed enough for
the carpenters to do their work that they had to do on that side of the wall.”

Smoot’s employees performed form work while erecting the scaffold. The
exception to paragraph (b)(1) states “the requirement in paragraph (b)(1) to provide full
planking or decking does not apply to platforms used . . . solely by employees performing
erection or dismantling.” Smoot does not argue that its employees were using the
platforms solely to erect the scaffold. The company argues its employees used the
platforms to erect the scaffold, while at the same time performing form work. The dual
nature of the employees’ work removes the exception to paragraph (b)(1) for Smoot.

Smoot points out § 1926.451(b)(1) allows for spaces between the platform and
the uprights to exceed 1 inch “where the employer can demonstrate that a wider space is
necessary.” Nelson testified his crew needed a wider space on the platform in order to
drop the “plumb bobs down in there to do the alignment and plumb it up” (Tr. 104).
Danielson also mentioned the plumb bobs, but Smoot adduced no evidence of the
frequency or duration of dropping the plumb bobs. There is no indication Smoot
required continuing gaps in the scaffold platforms while its employees stood on them to
perform form work. Danielson stated the plumb bobs measured 3 to 4 inches long and 2
inches in diameter (Tr. 168). He offered no explanation why Smoot required gaps of 9½
inches and 2 feet in the platforms to accommodate the plumb bobs.

Smoot adduced evidence demonstrating its employees received safety training in
scaffolding and the applicable scaffolding standards. The company’s foreman, however,
revealed a willingness to ignore the standards when he disagreed with their efficacy.
Smoot’s counsel asked Danielson if it was necessary to have a gap in the scaffold
platform. Danielson replied, “I’ve always felt that the two-plank wide was enough plank
for us to work off of. I didn’t feel there was really a fall hazard there” (Tr. 163).

Nelson testified the scaffold planks measured 9½ inches wide, and only two
planks would fit across the width of the scaffold brackets (Tr. 105-106). Smoot abated
the hazard on the southeast stairwell scaffold while Burns was still on site by placing a
third plank across the gap. Nelson stated the plank did not fit flush with the other planks
and created a tripping hazard (Tr. 104-105).

The Secretary has established Smoot failed to comply with the terms of §
1926.451(b)(1). Smoot has failed to meet the requirements of the exception to paragraph
(b)(1) because its employees were not engaged solely in erecting the scaffold; they were
also performing form work at the same time. Smoot also failed to show that a space
wider than 1 inch was necessary. The element of noncompliance is established.

3. Employee Access to Hazardous Conditions

Burns observed Danielson and another Smoot employee standing on the defective
exterior scaffold platform. He observed May standing on the defective interior scaffold
platform. Smoot exposed these three employees to the hazard of stepping into the gaps
and tripping or falling from the scaffolds.

4. Employer Knowledge

As carpenter foreman, Danielson supervised the other Smoot employees. He
supervised the building of the scaffolds. Project superintendent Nelson inspected the site
on a daily basis. The scaffolds were in plain view of anyone on the construction site.
The scaffolds had been up for at least two days (Tr. 20, 22). The court imputes the
knowledge of these two supervisory employees to Smoot.

The Secretary has established Smoot violated § 1926.451(b)(1). If an accident
occurred and an employee stepped into or tripped over one of the gaps, the resulting
injury would likely be a broken leg or fractured ankle (Tr. 22). Smoot committed a
serious violation.

Item 2a: Alleged Serious Violation of § 1926.451(a)(4)(iii)

Item 2a alleges: “In the southeast stairwell where forms were built, midrails were
not installed on the scaffold.” Burns photographed a Smoot employee standing on the
interior scaffold that had no midrails installed (Exh. C-6).

1. Application of Standard

Smoot contends § 1926.451(g)(4)(iii) does not apply to the condition cited. The
company argues, as is did under item 1, that the scaffold was not completed. Smoot
insists it was in the process of erecting the scaffold at the time of Burns’s inspection.
The company argues employee May was installing midrails on the scaffold when Burns
photographed him. Because the scaffold was under construction, Smoot contends, the
more specific standard at § 1926.451(g)(2) should apply.

The Secretary case rests on Burns’s testimony regarding his interview with May.
Burns testified May told him he was building forms while on the scaffold the day of the
inspection (Tr. 60). Burns denies May said anything about installing midrails on the
scaffold (Tr. 61). Burns stated May told him he had been working on the scaffold for
three days and had not gotten around to installing the midrails yet (Tr. 63).

Smoot’s position and the testimony of its own witnesses was contradictory on this
point. Smoot concedes in its post-hearing statement its employees built scaffolds and
performed form work at the same time. Nelson stated he heard May tell Burns, “We’re
in the process of completing the handrails” during Burns’s interview (Tr. 110).
Danielson testified he told Burns he had two employees on the scaffold installing
midrails, even though May stated he was working alone (Tr. 166). Burns took notes of
his conversations with Smoot’s employees. Danielson acknowledged he read and signed
the statement taken down by Burns, but denied he told Burns he did not know why the
midrails had not been installed on the scaffold after two days, as Burns wrote in his notes
(Tr. 169).

May’s testimony did little to bolster Smooot’s case. Smoot’s counsel asked May
what he was doing the day of Burns’s inspection. May replied, “I was in the process of
finishing this scaffold from where I left off the day before. . . . I was finishing the
handrail and the railing on the –the side rail, I call it– and I was going over it for safety to
make sure I had everything complete” (Tr. 174). But then Smoot’s counsel asked May
what he told Burns “about what was going on on the scaffold” (Tr. 175). May stated, “I
told him that–he asked what I was doing, what we was building. I said we’re forming a
wall , and then he asked had I had safety training, and I told him just what I told you;
through Smoot” (Tr. 175). Smoot’s counsel questioned May on the disparity in his
testimony (Tr. 176):

Q. I think you said something to Mr. Burns about you were putting
up the form wall. Did you just say that, or did I mishear you? I’m
sorry.

May:     No, no, I put up the scaffold.

On cross-examination, May’s testimony again became confused (Tr. 179):

Q.          And, did you tell [Burns] that you had been working on the forms?

May:     Yes. When he came to me, he wanted to know what we were doing, and I
told him we were forming up a wall to pour concrete. So, he said, “How
long have you been doing this?”

I said, “We started yesterday, and we’re going to finish it up today.”

Q.          Building the forms?

May:     Building the scaffold. The forms are built–the forms are already up before
the scaffold comes out. We stand on the walls, and then we put our
scaffold up after the walls are up.

May knew the company’s position is Smoot was in the process of installing
midrails when Burns observed him. Yet twice when asked what he was doing at that
time, May stated he was doing form work before correcting himself.

Burns also photographed a bucket on the scaffold on which May was working
(Exhs. C-7 and C-8). The bucket contained parts for form work and not for scaffolding
(Tr. 79).

Contrary to Smoot’s assertion, it was not still in the process of erecting the
scaffold before performing any work from it. Smoot may have intended to install
midrails at some point, but the record establishes May had done form work from the
scaffold without the midrail in place. The cited section of the standard applies to the
scaffold.

2. Noncompliance with Terms of the Standard

The applicability discussion above resolves this element as well. Smoot did not
equip its scaffold with a midrail as required by § 1926.451(g)(iii). The scaffold was 11
feet above a concrete floor (Tr. 31). Smoot failed to comply with the terms of the
standard.

3. Employee Access to Hazardous Condition

Smoot’s failure to install a midrail exposed May to an 11-foot fall onto a concrete
floor.

4. Employer Knowledge

Danielson and Nelson both knew May was working on the scaffold and that it
was not equipped with a midrail. The court imputes the knowledge of the supervisory
personnel to Smoot.

The Secretary has established Smoot violated § 1926.451(g)(iii). A fall from 11
feet onto a concrete floor could result in a serious injury (Tr. 32-33). The Secretary
properly classified item 2a as serious.

Item 4: Alleged Serious Violation of § 1926.652(a)(1)

Item 4 alleges, “On the site the general contractor did not ensure the employer
(Midwest Reinforcing) provided a protective system for employees tieing [sic] rebar in
the nine foot trench from a struck-by/cave-in hazard.”

Luburgh, Inc., a subcontractor, had excavated an area 800 feet long and 300 feet
wide (Tr. 111). The original shape of the excavation was like a “very large bathtub” (Tr.
112). When Smoot built the form wall two days before Burns’s inspection, it created a
trench. Prior to the day of Burns’s inspection, no employees had worked in the trench
area (Tr. 113).

Midwest’s employees were on site to install the rebar forms. A crane operator
lifted rebar forms into the trench. Midwest employees would then enter the trench to tie
the rebar to the forms so they could be poured (Tr. 35).

While Burns and Giannokos were on the roof of the student union building, they
observed an employee from Midwest slide down the wall of the excavation to retrieve a
tool. Burns told Giannokos the employee should not be in there. Giannokos agreed and
told Nelson “to get ahold of somebody to get the guy out of the trench and tell him not to
climb the sides of the wall” (Exhs. C-10 and C-11; Tr. 35-36).

Later that day Burns observed two Midwest employees in the trench tying rebar
to the forms (Tr. 37). Burns determined, and Smoot agreed, the soil in the trench was
Type C soil (Tr 38). Burns measured the trench as 9 feet deep and 8½ feet wide at the
top in the area where Midwest’s employees were working (Tr. 38-39). The width at the
bottom of the trench measured 3 feet (Tr. 40).

1. Application of Standard

Section 1926.652(a)(1) is part of Subpart P (Excavations). Section 1926.650(a)
provides Subpart P “applies to all open excavations made in the earth’s surface.
Excavations are defined to include trenches.” There is no dispute § 1926.652(a)(1)
applies to the trench cited in this case.

2. Noncompliance with Terms of the Standard

The chosen protective system to protect employees from cave-ins on the site was
sloping. A properly sloped trench wall excavated 9 feet deep in Type C soil would be 13
or 14 feet wide at the top. The trench wall at issue fell at least 4½ feet short of
compliance (Tr. 40).

Smoot does not dispute any of Burns’s measurements or his conclusion the trench
was unsafe. It argues, however, that it was not the company’s responsibility to ensure the
trench was adequately sloped and otherwise safe. Smoot contends Midwest had assumed
responsibility for complying with OSHA’s excavation standards. Smoot asserts its
contract with Midwest shifted all responsibility for compliance with the standards to
Midwest.

The Review Commission has held that a general contractor is responsible for
violations of other employers where it could reasonably be expected to prevent or detect
and abate the violations due to its supervisory authority and control over the worksite.
Centex-Rooney Construction Co., 16 BNA OSHC 2127, 2130 (No. 90-0851, 1994). This
duty applies to an employer even if its own employees are not exposed to the hazard.
Flint Engineering & Construction Co, 15 BNA OSHC 2052, 2055 (No. 90-2873, 1992).

Smoot maintained strong control over the subcontractors on the project. Smoot’s
standard subcontract required subcontractors to “immediately correct any unsafe action
or condition, specifically brought to his attention by Smoot. If this is not done, the
unsafe condition may be corrected by Smoot and backcharged appropriately” (Exh. C-1).

Giannakos and Nelson ordered Midwest to get its employee out of the excavation.
To abate the hazard, Giannakos ordered a Smoot employee to use a backhoe to properly
slope the excavation (Tr. 204). Nelson walked the site every day and was in a position to
detect violative conditions. He stated if anybody observed a safety infraction committed
by a subcontractor, “They come directly to me” (Tr. 93).

The court determines Smoot could reasonably be expected to prevent or detect
and abate violations. The company maintained a constant presence on the site, and
dictated the progression of the work and the manner in which it was done. Smoot is held
responsible for noncompliance with the terms of the standard.

3. Employee Access to Hazardous Condition

Burns observed a total of three employees in the trench the day of his inspection.
They were exposed to the hazard of a cave-in.

4. Employer Knowledge

Smoot argues it had no actual knowledge the excavation was improperly sloped,
nor could it have known about it with the exercise of reasonable diligence. No
employees had been in the excavation until the day of the inspection. Giannakos stated
the excavation looked safe to him (Tr. 191).

Reasonable diligence on the part of Smoot would have made the company aware
the excavation was unsafe. No employees had entered the excavation until March 17, but
the wall that created the excavation had only been built two days before. Giannakos
stated he did not know employees would enter the excavation, but he conceded he knew
“[ a]t some point, someone would have to go in there” (Tr. 204). Giannakos had
observed a Midwest employee in the excavation earlier on the day of the inspection.
Nelson testified that, as project superintendent, his job was “to organize all the
subcontractors and work the schedule with the prime contractors” (Tr. 87). He had to
have known Midwest’s entry into the excavation was imminent.

Nelson testified he viewed the trench area from the street but did not perceive a
problem with its slope. He stated, “It looked to me like it was very, very stable and close
to or at the degree it should be” (Tr. 121). Considering the trench’s width fell 4½ feet
short of “the degree it should be,” Nelson’s assessment does not support a finding of
reasonable diligence.

The Secretary has established Smoot had constructive knowledge the excavation
was improperly sloped.

The Secretary has established a violation of § 1926.652(a). An employee in a
trench during a cave-in would likely be crushed to death. The violation is serious.

PENALTY DETERMINATION

The Commission is the final arbiter of penalties in all contested cases. In
determining an appropriate penalty, the Commission is required to consider the size of
the employer’s business, history of previous violations, the employer’s good faith, and
the gravity of the violation. Gravity is the principal factor to be considered.

Smoot employed over 250 employees. The Secretary had not cited Smoot for
OSHA violations within the three years previous to Burns’s inspection. Smoot
demonstrated good faith with its written safety program and its safety training program
for employees (Tr. 28-29).

The gravity of items 1 and 2, the scaffolding violations, is moderate. The hazards
created were not likely to produce severe injuries. The gaps in the scaffold platforms
presented tripping hazards. The scaffold lacking a midrail was equipped with a toprail,
which afforded some protection. The court determines the appropriate penalty for item 1
is $1,500.00, and for item 2a is $500.00.

The gravity of item 4 is more severe. Three employees were in a 9-foot trench.
The wall of the trench was well above their heads. A cave-in (a not unlikely occurrence
in Type C soil) would bury them. The penalty for item 4 is $1,875.00.

FINDINGS OF FACT AND

CONCLUSIONS OF LAW

The foregoing decision constitutes the findings of fact and conclusions of law in
accordance with Rule 52(a) of the Federal Rules of Civil Procedure.

ORDER

Based upon the foregoing decision, it is ORDERED that:

1.           Item 1 of the citation, alleging a violation of § 1926.451(b)(1), is affirmed
and a penalty of $1,500.00 is assessed;

2.           Item 2a of the citation, alleging a violation of § 1926.451(g)(4)(iii), is
affirmed and a penalty of $500.00 is assessed;

3.           Item 2b of the citation, alleging a violation of § 1926.502(b)(2), is
withdrawn by the Secretary;

4.           Item 3 of the citation, alleging a violation of § 1926.651(k)(1), is
withdrawn by the Secretary;

5.           Item 4 of the citation, alleging a violation of § 1926.652(a)(1), is affirmed
and a penalty of $1,875.00 is assessed; and

6.           Item 5 of the citation, alleging a violation of § 1926.1053(b)(16), is
withdrawn by the Secretary.

s/ Ken S. Welsch         

KEN S. WELSCH  

Judge

Date: August 22, 2005

Get today's answer for your situation

You just read Commission precedent from 2006. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.