🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 04-1055, 04-1056 Decided September 16, 2005 Mixed result Judge Covette Rooney

E.P. Guidi, Inc. and Haines & Kibblehouse, Inc.

Trench citation affirmed for subcontractor and dismissed for construction manager

Apply this to your situation

This order from 2005 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 2005
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Haines & Kibblehouse installed a sewer line at a Philadelphia construction site where a trench collapsed and seriously injured one of its employees. The judge found that employees worked in a vertical-walled trench that was at least five feet deep without a protective system. H&K's foreman treated the trench as about five feet deep despite recent heavy rain and wet soil, and reasonable diligence required an accurate measurement. The cave-in protection violation against H&K was affirmed with a $4,500 penalty. The judge dismissed the corresponding citation against construction manager E.P. Guidi because the Secretary did not prove that it controlled H&K's work methods or knew of the trench depth and wet soil conditions.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.651(h)(1); 29 C.F.R. § 1926.652(a)(1)
  • Outcome: The cave-in protection item against H&K was affirmed with a $4,500 penalty, while the items against Guidi and the accumulated-water items were vacated.
  • Key point: The trenching subcontractor had to verify conditions near the five-foot threshold, but the construction manager was not liable without control over the work or knowledge of the violation.

Full text (OSHRC public release)

Haines & Kibblehouse, Inc., Docket No. 04-1055 & 04-1056

SECRETARY OF LABOR,

Complainant,

v.

E. P. GUIDI, INC.,

and

OSHRC DOCKET NOS.

04-1055 &
04-1056

HAINES & KIBBLEHOUSE, INC.,

Respondent.

APPEARANCES:

For the Complainant:

Judson H. P. Dean, Esq., Office of the Solicitor, U.S. Department of Labor, Philadelphia,
Pennsylvania

For the Respondent:  

James L. Curtis, Esq., Seyfarth Shaw LLP, Chicago, Illinois

Before: Administrative Law Judge: Covette Rooney

DECISION AND ORDER

This proceeding arises under the Occupational Safety and Health Act of 1970 (29 U.S.C.
Section 651-678; hereafter called the “Act”).

Respondents, E. P. Guidi, Inc. (Guidi) and Haines & Kibblehouse, Inc. (H&K), at all
times relevant to this action maintained a place of business at the site of a Walgreen’s store under
construction at 12052 Bustleton Avenue, Philadelphia, Pennsylvania, where they were engaged
in the installation of a sewer line . Respondents admit they are employers engaged in a business
affecting commerce and are subject to the requirements of the Act.

On April 15, 2004, a H&K employee was injured when a trench at the Walgreen’s
worksite collapsed. Following the accident, the Occupational Safety and Health Administration
(OSHA) initiated an inspection . As a result of that inspection, both H&K and the general
contractor on the site, E.P. Guidi, were issued citations alleging violations of the Act. By filing
a timely notice of contest Respondents brought this proceeding before the Occupational Safety
and Health Review Commission (Commission). Prior to the hearing, the Secretary withdrew
Citation 1, item 2. Citation 1, item 1, alleging a “serious” violation of §1926.652(a)(1) of the
Act remains at issue. On March 21-23, 2005, a hearing was held on that matter in Philadelphia,
Pennsylvania. The parties have submitted briefs on the issue and this matter is ready for
disposition.

OSHRC Docket 04-1056

FACTS

Prior to April 15, 2005, H&K completed a 12 foot deep sewer hookup to the sanitary
sewer main in Byberry Street running in front of the Walgreen’s building site (Tr. 451-52). On
April 15, H&K intended to run a gravity fed four inch cast iron sewer line up to the building
under construction (Tr. 54, 452). The line was to slope at a 1% or 2% slope, or 3/4 of an inch per
each three foot section towards the street (Tr. 456, 465). The trench, therefore, was up to a
couple of feet deeper at the Byberry end of the trench than at the building site (Tr. 82-83).
Charles Morgan, H&K’s general foreman (Tr. 385), testified that after the trench is dug, between
3 and 6 inches of stone bedding is placed in the trench (Tr. 453). The sling man sets the pipe in
the trench, and the pipesetter guides the pipe into the bell end of the previous length of pipe (Tr.
454-55, 457). A third man follows behind and smooths and compacts the backfill (Tr. 457).

On April 15, 2005, George Illingworth a laborer employed by H&K (Tr. 44), testified that
no bedding was used in this trench (Tr. 57; Exh. R-13, pp. 2, 3, 4, 5; R-12, pp. 3, 4, 6).
Illingworth stated that he used the Ramex, or compactor to compact the dirt (Tr. 71). It was also
his job to break up the backfill after it was dumped onto the pipe to make it easier for Morgan to
run the Ramex over it (Tr. 55, 58, 60, 68). Illingworth testified that he was in every portion of
the trench at some point on April 15 (Tr. 71, 130; Exh. GX6-14). He stood away from the front
end loader, standing either on the backfill on the Byberry end of the trench, or on the trench floor
nearer the building site, while backfill was added to the trench (Tr. 130, 133, 137). In addition
to Charles Morgan, he observed another laborer, Jimmy Evers, and a plumber also working in the
trench (Tr. 80; Exh. GX6-18). Illingworth worked in the trench for approximately three hours,
entering and exiting the trench a number of times during the day (Tr. 69-71, 80). He would
climb out from either the Byberry end or the building end of the trench, depending on his reason
for exiting (Tr. 69-71).

The trench walls were vertical, and no protective measures were in place (Tr. 87).
Illingworth noted that, as one faced Byberry, a portion of the right hand wall of the trench was
wet (Tr. 91). Illingworth, who is 5'9", did not know how deep the trench was, but stated that it
came approximately to his chin (Tr. 84-85, 118-21). Illingworth’s chin was measured at 61" (Tr.
128). Illingworth testified that he was working in the trench watching the backhoe operator
throw backfill into the trench when he saw the trench start to crack (Tr. 55, 58, 60-61, 77). When
the trench collapsed, Illingworth was buried up to the bottom of his rib cage, and suffered serious
injuries including a lacerated liver, a bruised spleen, a cracked rib and four lumbar fractures of
his back (Tr. 61-63).

Wylie Hinson, the OSHA Compliance Officer (CO) testified that when he arrived at the
Walgreen’s worksite at noon on April 15, 2005, after the accident, he measured and diagramed
the cited trench (Tr. 187; Exh. R-3, p. 8). According to Hinson, the trench was excavated in
Type B soil (Tr. 219). It was 63 feet, 6 inches from the building to the street, and was between
42 and 45 inches wide (Tr. 187). Hinson used a tape measure to measure the depth and width of
the trench while standing on an area of “blacktop” across the trench from the portion of the
trench which collapsed. At that point, the trench was 32 feet in from the street (Tr. 188-89, 193,
279, 306, 353, 365, 463; Exh. GX6-3, GX6-4). Hinson found that the trench was 5 feet, 6 inches
at that point (Tr. 182, 189, 194). Hinson further testified that he took a second measurement
three feet towards Byberry Street; at that point the trench was 4 feet, 6 inches deep (Tr. 192).
The trench walls were not benched, sloped or shored (Tr. 201, 222). A portion of the trench wall
on the side which collapsed was wet, and a small amount of water pooled in the bottom of
another portion of the trench (Tr. 211, 214, 223; Exh. GX6-6, GX6-7, GX6-8).

Charles Morgan, the foreman, identified himself as the “competent person” on the site
(Tr. 296-97, 359, 443-48; Exh. R-25). Morgan testified that he was responsible for the job safety
of H&K employees (Tr. 387), and conducted an inspection of the trench the morning of the
collapse (Tr. 298, 449). Though CO Hinson testified that Morgan told him that his thumb test
showed the soil to be type C, Morgan testified at the hearing that he found the soil was Type B
(Tr. 299, 413, 450). Morgan testified that without bedding or backfill, the trench at the
Walgreen’s site was 5 feet deep (Tr. 391). He did not measure the trench, but believed he could
tell the depth of the trench from his previous experience in trenches (Tr. 459-60). Morgan
further stated that the trench was necessarily less than 5 feet deep once the bedding and fill was
added (Tr. 391). Morgan stated that there was no reason for anyone to be in the trench before the
fill was added (Tr. 453-454). After observing the condition of the soil and estimating the depth
of the trench at 5 feet, Morgan determined that it was unnecessary to use any protective system in
the trench (Tr. 392-93, 407-08).

Morgan testified that backfill had already been placed over the pipe in the portion of the
trench which collapsed, but admitted that photographs showed that the area which should have
been about 4 feet deep actually appeared to be approximately 5 feet deep (Tr. 476-85; Exh. GX8-7; see also testimony of Joseph Pyott, Tr. 612-615). Morgan further admitted that there did not
appear to be any bedding underneath or beyond the end of the pipe in the cited trench (Tr. 503-04; Exh. R-13, p. 3).

Joseph Pyott, H&K’s risk manager (Tr. 599), testified that he measured and photographed
the cited trench on April 15, 2004 (Tr. 601). Pyott testified that the walls of the trench were
vertical and that there was no benching or sloping visible in the area of the collapse (Tr. 606-608,
619). He also stated that an area on the same side of the trench which collapsed was wet, and
that he could see water dripping down the wall (Tr. 609-10). Pyott testified that although the
photograph of the trench measurement in the area of the collapse appears to show that the trench
was 5 feet deep, the tape measure actually read 4 foot, 9 inches (Tr. 615-16, 640; Exh. GX8, p.
5). Pyott further stated that a photograph showing the depth of the trench at 5 feet, 1 inch (Exh.
GX8, p. 6) was inaccurate, because the shovel handle he was using to mark the lip of the trench
was “concave” and was not sitting flush (Tr. 632-33, 644). Pyott testified that had he wanted to
take a specific measurement of the depth of the trench he would not have used the shovel handle
(Tr. 633). Pyott testified that he did not believe that there was any three foot stretch of the trench
where the depth would have varied a foot in depth, except at the end of the pipe (Tr. 642-43). He
testified, however, that where the backfill ended, at “the point where they were working it would
have dropped off, yes.” (Tr. 642).

John Edwards, the site superintendent for E.P. Guidi, filled out an accident report on
April 15, 2004, in which he estimated the depth of the vertical trench at between 4 feet, 6 inches
and 5 feet, 6 inches (Tr. 341; Exh. GX4, HKG000324). During the inspection, he told CO
Hinson that he had seen Illingworth working in the trench, which, at that point, was
approximately shoulder height, or around 5 feet deep (Tr. 340). At the hearing Edwards testified
that he did not inspect the trench until after the collapse, and never actually measured the trench
(Tr. 665, 701). Finally, Edwards’ reports describe heavy rain throughout the day on the two days
preceding the accident (Tr. 691, 695-97; Exh. GX4, HKG000322, HKG000323).

DISCUSSION

Serious citation 1, item 1 alleges:

29 CFR 1926.652(a)(1): Each employee in an excavation was not protected from cave-ins by an
adequate protective system designed in accordance with 29 CFR 1926.652(c):

a) 12052 Bustleton Avenue – An employee making a connection in an excavation
with vertical walls approximately 5 feet 3 inches in depth

was not protected from
cave-ins by an adequate protective system on or about 4/15/04.

The cited standard provides:

Each employee in an excavation shall be protected from cave-ins by an adequate
protective system designed in accordance with paragraph (b) or (c) of this section
except when:

(i) Excavations are made entirely in stable rock; or

(ii) Excavations are less than 5 feet (1.52m) in depth and examination of the
ground by a competent person provides no indication of a potential cave-in.

In order to prove a violation of section 5(a)(2) of the Act, the Secretary must show by a
preponderance of the evidence that (1) the cited standard applies, (2) there was a failure to
comply with the cited standard, (3) employees had access to the violative condition and (4) the
cited employer either knew or could have known of the condition with the exercise of reasonable
diligence.

Respondent’s argue that the cited standard is not applicable in this case because the cited
trench meets the criteria of subparagraph (ii), in that it was less than 5 feet in depth, and gave no
indication of having a potential to cave in.

In order to establish the applicability of §1926.652(a)(1) the Secretary has the initial
burden of showing that an employee in an excavation was not protected from cave-ins by a
protective system. The record establishes that H&K’s employees moved freely throughout the
trench. Illingworth testified that he worked in the trench all morning, exiting from both the street
and the building ends of the trench. See, Kaspar Electroplating Corp., 16 BNA OSHC 1517,
1521, 1993 CCH OSHD ¶30,303, p. 38,886, (No. 86-0274, 1993)(Exposure element is shown
when employees have been, are, or will be in zones of danger during either their assigned
working duties, their personal comfort activities while on the jobsite, or their movement along
normal routes of ingress to or egress from their assigned workplaces). Illingworth testified that
another laborer, and the foreman, Morgan, also worked in the trench. Morgan testified that, as
the pipesetter, he fit the new sections of pipe into the previously laid section while standing in the
trench. Employee exposure has been established.

The Secretary’s assertion that the vertically walled trench had no protective systems in
place is uncontested.

Once these facts are established, the burden of proof shifts to H&K to establish by a
preponderance of the evidence that it falls under the exception provided in subparagraph (ii). See
C.J. Hughes Constr., Inc., 17 BNA OSHC 1753, 1996 CCH OSHD ¶31,129 (No. 93-3177,
1996); Revoli Constr. Co, Inc. , 19 BNA OSHC 1262, 2000 CCH OSHD ¶32,189 (No. 00-315,
2001)(ALJ); Drum Constr., 18 BNA OSHC 1927, 1999 CCH OSHD ¶31,900 (No. 98-1501,
1999)(ALJ). CO Hinson testified that he measured the trench at 5 feet 6 inches at one point. The
Secretary provided the COs contemporaneous documentation of his measurements. Hinson had
no reason to fabricate his testimony, and appeared sincere on the witness stand. Respondent
itself provided photographs documenting that the trench was, at one point at least, 5 feet 1 inch
deep. Respondent’s attempts to impeach the accuracy of its own documentation are
unconvincing. Respondent’s witnesses were not forthcoming during their testimony, which
appeared rehearsed. Moreover, it is inconceivable that H&K’s own risk manager would not try
to get an accurate measurement of the trench depth during an accident investigation. It is further
noted that the measurements provided at the hearing were taken near the area of the collapse, 32
feet in from Byberry Road. The record shows that H&K tied the line being buried into the deeper
main in the street. The witnesses testified that the gravity fed sanitary sewer was laid at a 1% to
2% grade, and that the trench was shallower at the point where it collapsed, and where it was
measured, than it had been nearer the street, where the employees had been working earlier that
morning.

Taken in the light most favorable to Respondent, the evidence does not show that the
cited trench was less than 5 feet in depth. The standard, therefore, is applicable. Because
employees worked in the trench without benefit of a protective system designed in accordance
with paragraph (b) or (c) of the standard, non-compliance with the standard is established.
Finally, it is clear that H&K’s foreman knew, or should have known of the violative condition.
In order to show employer knowledge of a violation the Secretary need only show that the
employer knew, or with the exercise of reasonable diligence, could have known of a hazardous
condition. Dun Par Engd. Form Co. , 12 BNA OSHC 1962, 1986-87 CCH OSHD ¶27,651 (No.
82-928, 1986). Reasonable diligence involves several factors, including an employer's
"obligation to inspect the work area, to anticipate hazards to which employees may be exposed,
and to take measures to prevent the occurrence." Frank Swidzinski Co. , 9 BNA OSHC 1230,
1233, 1981 CCH OSHD ¶25,129, p. 31,032 (No. 76-4627, 1981). Morgan and his pipe crew
were working in a trench which Morgan himself judged to be about 5 feet deep. It had been
raining heavily during the two days preceding April 15, and a portion of the trench wall was wet.
Under these conditions, a reasonably diligent employer would have ascertained the exact depth
of the trench to make sure that its employees were protected and that the requirements of
§1926.652(a)(1) were being met.

The violation is established.

H&K stipulates that the violation is “serious” (Tr. 63). The
record establishes that the gravity of the violation is high. Three H&K employees worked in the
cited trench throughout the morning of April 15, 2004. No means were taken to protect
employees, resulting in a cave-in, which caused severe injuries to one of H&K’s employees. The
proposed penalty of $4,500.00 is deemed appropriate and will be assessed.

OSHRC Docket 04-1055

FACTS

Respondent E.P. Guidi, Inc. was the controlling, or prime contractor on the Walgreen’s
site (Tr. 50, 177; Exh. GX5). Guidi acted as the contract manager for the developer, scheduling
the work, and coordinating the subcontractors’ performance (Tr. 423-25, 473, 475; Exh. GX5).
Guidi’s superintendent, John Edwards, was on the site every day (Tr. 51, 178, 473). Edwards
ensured that the work was done according to the drawings, helping H&K identify existing piping
and directing H&K’s placement of the new pipe they were burying (Tr. 51, 102-03). H&K’s
contract with Guidi provides that Guidi has the authority to direct H&K in the time, order, and
manner of its performance of the contract (Tr. 561-62; Exh. GX5, p. 5. Art. 13). It had authority
to direct changes in the work (Exh. GX5, p. 4, Art. 10). It has the express authority to determine
whether H&K’s performance might delay the completion of the project, and to withhold payment
in that event (Exh. GX5, p. 3 ¶E.6). In regard to employee safety, the contract states that:

. . . it is the responsibility of the SUBCONTRACTOR to proceed with all
operations in accordance with the prescribed accident prevention program, and
GUIDI will monitor such compliance.

The SUBCONTRACTOR shall be responsible for the safety of persons and
property, and compliance with all Federal State, and Local statutes, rules
regulations and orders, relating to the conduct of his work, and shall not wait for,
or expect, direction from GUIDI for compliance with said statutes, rules
regulations and orders. The SUBCONTRACTOR shall be responsible for the
payment of fines, levied against the Principal A/E or GUIDI for deficiencies
relating to SUBCONTRACTOR’s conduct of his work. The
SUBCONTRACTOR shall indemnify and hold harmless the Principal, A/E or
GUIDI in accordance with the provisions of this article.

Dennis Detweiler, an estimator/project manager with H&K (Tr. 543), testified that he
negotiated H&K’s contract with Guidi (Tr. 544; Exh. GX5). According to Detweiler, it was the
parties intent that H&K be responsible for the safety of its own employees at the Walgreen’s site
(Tr. 545). H&K did not intend to give any control or authority to Guidi on safety issues (Tr.
545).

The subcontract between EPG and H&K incorporates the prime contract between Guidi
and the developer, BB Development (Exh. GX5, p. 3, Art. 2). The prime contract states, inter
alia , that:

10.1.1The contractor [GUIDI] shall be responsible for initiating, maintaining and
supervising all safety precautions and programs in connection with the
performance of the Contract.


10.2The Contractor [GUIDI] shall take reasonable precautions for safety of,
and shall provide reasonable protection to prevent damage, injury or loss
to:

  1. employees of the work and other persons who may be affected thereby;
    . . .

10.2.6The Contractor [GUIDI] shall designate a responsible member of the
Contractor’s organization at the site whose duty shall be the prevention of
accidents. This person shall be the Contractor’s superintendent unless
otherwise designated . . .

(GX7, Exh. H at p. 34-35).

John Edwards testified that it was his job to make sure that the work at the Walgreen’s
site was proceeding in accordance with the plans (Tr. 671-72). Edwards was not designated as a
safety coordinator at the site, though he had the authority to make safety recommendations
should he observe a dangerous condition (Tr. 673-75, 684, 704). Although he had the authority
to do so, Edwards did not believe he had any responsibility to ensure that H&K complied with its
own safety program (Tr. 678-69, 681). Edwards, Guidi’s sole representative on the site, did not,
in fact, advise H&K’s pipe crew in safety matters (Tr. 103, 674, 676, 682). Specifically,
Edwards did not make any recommendations about using protective measures in the cited trench
prior to its collapse, as he did not observe a hazardous condition (Tr. 674, 710). Moreover, had
he observed a hazardous condition, he did not believe he had the authority to stop H&K’s work
(Tr. 704). Although Edwards observed the trench on April 15, he did not inspect it until after the
collapse had occurred (Tr. 700-01, 708). Edwards told CO Hinson that he was not a trencher,
and was not familiar with OSHA trenching regulations (Tr. 326). He relied on H&K to comply
with the safety regulations specifically applicable to their industry (Tr. 709, 719). Finally,
H&K’s foreman did not believe that Guidi had the authority to order him to take additional safety
precautions (Tr. 474).

Christopher Bleeker, a project manager with Guidi, testified that Guidi performs no
construction work, and acts solely as a construction manager, not a general contractor (Tr. 736-38). It subcontracted out all the work on the Walgreen’s site; its sole function was to monitor
schedules and costs and to act as the owners’ intermediary (Tr. 739). Bleeker testified that it did
not attempt to monitor H&K’s compliance with its safety program (Tr. 731).

Discussion

The facts tend establish that Guidi had overall contractual authority for all aspects of the
project management. In terms of the breadth and scope of the functions which Guidi contracted
to perform, its role at the site was not appreciably different from that of the employers in the
other cases whom the Commission found to have broad administrative and coordination
responsibility. Guidi’s responsibility for the administration and coordination of the construction
work, inspection for conformity to contract specifications, certification of work for payment,
processing of change orders, and monitoring the schedule and maintaining job progress, are all
indicia of what the Commission has termed “far-reaching or global responsibility for diverse
activities at the site”. See, Kulka Constr. Mgmt. Corp., 15 BNA OSHC 1870, 1991-93 CCH
OSHD ¶29,829 (No. 88-1167, 1992); Fleming Constr. Inc., 18 BNA OSHC 1708, 1999 CCH
OSHD ¶31,809 (No. 97-0017, 1999).

Nonetheless, its contractual authority lacks those indicia of control on which the
Commission has relied in those cases in which the construction standards were found applicable
to employers performing solely administrative duties on a construction site. While it is true that
Guidi’s contract with BBD includes an obligation to review and approve the safety programs
developed by its subcontractors, there is no evidence that Guidi was expected to examine the
subcontractor’s safety programs for either content or substantive adequacy. In practice, Guidi did
not prescribe safety measures for the worksite; it merely ensured that the subcontractors had their
own safety programs, in the course of performing its contractual obligations to inspect the work
and to "coordinate" the safety programs of the trade contractors. The contract does not establish
that Guidi had any authority to stop work, or was empowered in any way to compel compliance
by contractors even in those areas for which it had contractual responsibility. Neither Guidi and
H&K employees believed that Guidi’s superintendent had any authority to direct the means or
methods by which H&K accomplished its work. See, Kulka Constr. Mgmt, Corp., Fleming
Constr. Inc., supra.  

The Secretary has not shown that Guidi was a “controlling employer” for purposes of
liability under the Act.

Moreover, assuming arguendo, that Guidi was ultimately responsible for safety on the
Walgreen’s site, Guidi can only be held liable for H&K’s violation of §1926.652(a)(1), if the
Secretary establishes that Guidi knew or should have known of the violative conditions. The
Secretary asserts that Guidi had constructive knowledge of the violations because Edwards could
have known of the hazard if he had inspected the trench. However, a controlling employer is not
required to make continuous inspections of the worksite to fulfill its supervisory responsibilities.
When a task is routine and employees are experienced, a supervisor should normally be
permitted to rely upon the employees to perform their work correctly without the need to inspect
their work in every instance. Cf. Jones & Laughlin Steel Corp ., 10 BNA OSHC 1778,1982 CCH
OSHD ¶26,128, (No. 76-2636, 1982). It is particularly unnecessary to impose an inspection duty
upon a supervisor when there is no indication that employees in the past had failed to perform
their tasks correctly. H&K was an experienced trenching firm. Guidi had no trenching expertise.
H&K had the primary responsibility for the safety of its employees, in this case, to ascertain the
integrity of the soil, and to ensure that the depth of the trench did not exceed 5 feet. Nothing in
the record suggests that H&K had shown themselves to be incompetent. The record establishes
only that Edwards observed employees working in the cited trench, which appeared to be
approximately shoulder height. Nothing in the record suggests that the violation should have
been readily apparent at that point, or that the sight of an employee in the trench should have
triggered further investigation.

Because there is no evidence that Edwards was should have been aware that H&K had
exceeded the 5 foot limit imposed by the cited standard, or that he knew of the wet soil
conditions in the trench, Guidi’s knowledge of the violation has not been established, and
citation 1, item 1 must be dismissed.

ORDER

OSHRC Docket 04-1055

  1. Citation 1, item 1, alleging violation of 29 CFR 1926.652(a)(1) is AFFIRMED and a
    penalty of $4,500.00 is ASSESSED.

  2. Citation 1, item 2, alleging violation of 29 CFR 1926.651(h)(1) is VACATED.

OSHRC Docket 04-1056

  1. Citation 1, item 1, alleging violation of 29 CFR 1926.652(a)(1) is VACATED.  

  2. Citation 1, item 2, alleging violation of 29 CFR 1926.651(h)(1) is VACATED .  

/s/

Covette Rooney

Judge, OSHRC

Dated: August 16, 2005

Get today's answer for your situation

You just read what one judge decided for one employer in 2005, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.