🧪 TEST MODE ACTIVE Use test card: 4242 4242 4242 4242
OSHRC ALJ decision Docket 03-0693 Decided September 24, 2004 Citations affirmed Judge Michael H. Schoenfeld

Epernay Design and Construction, LLC

Willful anchor-bolt violation affirmed after column collapse

Apply this to your situation

This order from 2004 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 2004
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Epernay was the concrete and foundation subcontractor on a high school project where a 55-foot steel column fell shortly after being detached from a crane. Epernay's crew had cut off and replaced anchor bolts without first obtaining the project structural engineer's approval, and all four modified bolts at the column pulled out when it fell. The judge found that Epernay knew approval was required, did not properly supervise the repair work, and continued making unauthorized structural repairs even after the collapse and a later meeting about the approval requirement. The violation was willful because the company consciously disregarded the approval rule and showed plain indifference to employee safety. No one was injured in the collapse, and the judge assessed a $56,000 penalty.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.755(b)(1)
  • Outcome: The willful violation was affirmed with a $56,000 penalty.
  • Key point: Anchor rods may not be repaired, replaced, or field-modified without approval from the project's structural engineer of record.

Full text (OSHRC public release)

SECRETARY OF LABOR, :
:
Complainant, :
:
v. : DOCKET NO. 03-0693
:
EPERNAY DESIGN AND :
CONSTRUCTION, LLC, :
:
Respondent. :

Appearances:

            James Glickman, Esquire                                Scott K. DeMello, Esquire
            U.S. Department of Labor                               Newton, Massachusetts
            Boston, Massachusetts                                  For the Respondent.
            For the Complainant.

Before: Administrative Law Judge Michael H. Schoenfeld

                               DECISION AND ORDER

Procedural Background
This proceeding is before the Occupational Safety and Health Review Commission (“the
Commission”) pursuant to section 10(c) of the Occupational Safety and Health Act of 1970, 29
U.S.C. § 651 et seq. (“the Act”). The Occupational Safety and Health Administration (“OSHA”)
conducted an inspection of a high school additions and renovations project in Westwood,
Massachusetts during October 2002 after a 55-foot steel column collapsed at the site right after it was
set in place; the column collapsed on October 1, 2002, and OSHA began its inspection on October
4, 2002. As a result of the inspection, OSHA issued a one-item willful citation, alleging a violation
of 29 C.F.R. § 1926.755(b)(1), to Epernay Design and Construction, LLC (“Epernay”). Epernay filed
a timely notice of contest, bringing this matter before the Commission. Following a hearing in this
case in Boston, Massachusetts, both parties have submitted post-hearing briefs and the Secretary has
submitted a reply brief.
Jurisdiction
At all times relevant to this action, Epernay maintained a work site at the Westwood High
School in Westwood, Massachusetts, where it was the concrete and foundation subcontractor for the
additions and renovations project taking place at the school. The Commission has held that
construction is in a class of activity that as a whole affects interstate commerce. Clarence M. Jones,
11 BNA OSHC 1529, 1531 (No. 77-3676, 1983). In addition, Epernay admits in its Answer that it
is a business subject to the Act and that the Commission has jurisdiction of this matter. I find,
therefore, that Epernay is an employer engaged in a business affecting commerce within the meaning
of section 3(5) of the Act, and I conclude that the Commission has jurisdiction of this action.
Factual Background
The essential facts are as follows.1 The Westwood High School project involved the
construction of a new school building and the renovation of the existing building. Kaestle Boos
Associates (“KBA”), an architectural firm, was engaged to design the project and to provide
construction administration services. Laurence Trim, a project architect for KBA, was responsible
for the entire project from start to finish. Other KBA employees involved were Edward Monahan,
the construction administrator, and Edward Cifune, the “job captain.” Monahan was responsible for
the project’s paperwork and for recording and transcribing the minutes of the weekly job meetings
held at the site, while Cifune was responsible for assisting Trim. Trim, Monahan and Cifune attended
the weekly job meetings and also usually walked the project to observe its progress when they went
to the site for the job meetings. (Tr. 38-39, 311-12, 315-18, 330-31, 399-405, 449-55).
KBA hired Odeh Engineers (“Odeh”), an engineering firm, to provide the structural design
and drawings for the project. Larry Marini, a senior structural engineer with Odeh, was the structural
engineer of record for the project. Marini developed most of the structural design for the project, and
he and others in his office developed the drawings. Marini was also responsible for conducting site
inspections, answering questions from KBA and the contractors, and reviewing and approving shop
drawings and requests for changes submitted by the contractors. (Tr. 35-41, 45-48, 69-76).

   1
     Although Epernay disputes certain of these facts, my determination that these are the

essential facts in this case is based on the record as a whole and on my credibility findings set forth
in the discussion relating to Willful Citation 1, Item 1, infra. Furthermore, all findings of fact
necessary for a determination of all relevant issues have been made in this decision, see Fed. R. Civ.
P. 52(a), and any proposed findings of fact inconsistent with this decision are denied.

                                              2

Allan Miller was the “clerk of the works” for the project.2 His duties involved walking the
site on a continuous basis, recording the daily events that took place during the project, and attending
the weekly job meetings. Miller was also responsible for maintaining a full set of the plans and
specifications for the project, marking them as changes were made during construction, and verifying
that the requirements of the plans and specifications were being met. (Tr. 496-501, 507).
Alexandra Construction (“Alexandra”) was the general contractor of the Westwood High
School project, and the Alexandra employees involved with the project included Ronald Collins, the
project manager, David Pilcher, the on-site project manager, Daniel Campbell, the job
superintendent, Tahir Dizdari, the assistant superintendent, Daniel Turcotte, the job site foreman,
and Edmund Norton, the safety manager. Alexandra subcontracted the concrete and foundation work
to Epernay Design and Construction (“Epernay”), and William Baldwin was Epernay’s foreman at
the site. Alexandra subcontracted the structural steel fabrication and erection work to Trimax Steel
(“Trimax”); Trimax, in turn, subcontracted the steel erection work to Construction Welding Services
(“CWS”), and Mo Luckern was Trimax’s representative at the site. At some point in September
2002, both CWS and Luckern left the project, after which Trimax hired Northern Construction
Dynamics (“NCD”) to perform the steel erection. Marc Chauvin is NCD’s president. (Tr. 800-01,
807-08, 896-97, 903, 973, 989). See also Stip. Nos. 1-4, 15-16.3
When excavation of the site began in March of 2002, it was discovered that much of the soil
was “unsuitable.”4 That soil thus had to be removed and replaced with suitable soil, and, while
Alexandra was compensated for this work, it caused the project to be set back three to five months.
Further, when the foundation work began, Baldwin and his foundation crew made measuring errors,
causing certain concrete walls and piers to be poured in the wrong places in Area A.5 The errors also

   2
    The Permanent Building Committee of the town of Westwood hired Miller to be the clerk

of the works; the committee also hired KBA to work on the project. (Tr. 315, 498-99).
3
The parties’ amended joint pre-hearing statement includes, on pages 9-12, a number of
agreed-upon facts; in this decision, each of these is referred to as “Stip. No. ___.”
4
All dates herein will refer to the year 2002, unless otherwise stated.
5
The project consisted of seven areas, referred to as Areas A through G; Area A was the
auditorium and the music and art rooms. The discussion herein relates to Area A. (Tr. 39).

                                                3

caused anchor bolts in at least 20 column areas to be set in incorrect locations. One of these was the
Column M-1 area (“M-1”), which was located at the rear of the auditorium, stage right; the four
anchor bolts at M-1 were in the wrong locations as the pier had been poured 2 inches too short.6 (Tr.
52, 77-82, 97, 332, 386-88, 454, 500-01, 545, 744-45, 811-12, 815-18). See also Stip. Nos. 5-6, 12.
Anchor bolts are the structural components that serve to attach a steel column to the concrete
foundation, and anchor bolts are particularly important during erection, when they are the only things
holding up the column. The design for the project required the anchor bolts to be set into the piers
when the concrete was poured, and their precise placement was essential for the steel to be erected
properly. 7 It was also essential to use the anchor bolts specified, which, in the case of M-1, were 30
inches long (to be embedded 26 inches in the concrete) with a 4-inch threaded top and a head at the
bottom to prevent the bolt from being pulled out; the column to be set at M-1, however, was one of
the largest and tallest of the columns to be used at the site, and specifications for the anchor bolts
varied at different locations, depending upon the size of the column and the load it would bear. (Tr.
41-43, 54-66, 92-94, 366-67, 570).
Baldwin’s crew made repairs to the anchor bolts in at least the 20 locations referenced above.
This was accomplished by cutting off the anchor bolts and placing threaded rod or cut anchor bolts,
along with epoxy, into newly-drilled holes in the proper locations; the newly-placed bolts were much
shorter than the original 30 inches, and the repairs at M-1 resulted in two of the bolts being set at
depths of only 3.75 inches and 5.5 to 6 inches, respectively. In regard to the two other bolts at M-1,
two new 30-inch anchor bolts were placed in the proper locations in a 2-inch-wide grout extension
that was added on to the pier. The grout, a form of concrete, was not tested for compressive strength
prior to the accident on October 1. (Tr. 112-13, 123, 130-31, 596-97, 635-40). See also Stip. Nos. 5-6.

    6
    Column M-1 is the column that fell on October 1, 2002; it was one of four 55-foot columns

that formed the back of the auditorium. See Stip. No. 12.
7
Also used at the site were leveling plates, which would be put on the piers to denote
precisely where the columns would go, and a base plate welded onto the bottom of the column would
sit on top of the leveling plate. The leveling and base plates at M-1 were to be the same size (1 foot
2 inches square), and both had corresponding holes through which the anchor bolts would fit; further,
the bolts were to be 1.5 inches from the leveling plate edges. (Tr. 42, 56-59).

                                              4

The repairs that Baldwin’s crew made to the anchor bolts were structural in nature, and,
according to the project’s procedures, KBA and Odeh were required to approve structural repairs.
Exhibit 26, the manual for the project, states at section 05120, paragraph 3.2D: “Do not field cut or
alter structural members without approval of Architect.” Similarly, Exhibit 92, Alexandra’s field
manual for superintendents, states on page 13 that “[i]f it should become necessary to cut a structural
element, no action is to be taken by any Company personnel and no authorization is to be given to any
subcontractor without the prior written approval of the specific cutting by the Owner, Architect and
the Owner’s or Architect’s Engineer.” Thus, a contractor intending to deviate from the structural plans
and specifications was to propose the modification, usually in the form of a “request for
information”(“RFI”), and to provide a sketch or a written description. The RFI went first to KBA,
where it was reviewed; the RFI next would go on to Marini, who would review it and approve it or
not, after which it would go back to KBA and then on to the contractor. (Tr. 69-75, 78-79, 90, 101-02,
108, 130, 258, 264-65, 324-30, 367-68, 383-85, 504-05, 935-36).
Marini made his first site visit on August 1. He saw several problems he had not been told
about, one of which was a concrete wall poured in the wrong place and anchor bolts that were too
close to the wall edges; in Exhibit 7, his report to Trim dated August 1, he advised how the contractor
should address this problem and the others he had seen.8 Monahan had also noticed some problems
with anchor bolts at the site, and, at the August 8 job meeting, he asked Alexandra to provide “as-built
locations for any [anchor bolts] that [Alexandra] knows are out of tolerance.” Further, Miller had seen
some cut-off anchor bolts that looked “suspect,” prompting him to ask, at the August 22 job meeting,
“that Odeh’s field inspection include footings, walls, piers, and [anchor bolt] locations.” Alexandra
did not provide the information that Monahan had requested before the collapse of Column M-1 on
October 1. (Tr. 77-89, 407-08, 511-13; Exh. 34, p. 11, No. 17.17; Exh. 38, p. 11, No. 17.17).
Marini’s next visit was on August 28, when he saw two items he should have been told about;
one was a concrete patch on some foundation work that did not meet the structural plans and
specifications, and the other was concrete that had been added onto the side of a footing. Marini also

    8
     Marini generally spoke to a representative of the contractor about any problems he saw

before leaving the site; in addition, the field reports that he gave to KBA were passed on to the
contractor. (Tr. 79, 84-86).

                                               5

looked at M-1 and discussed it with Baldwin, who proposed using a smaller leveling plate to take care
of the fact that the M-1 pier had been poured 2 inches too short. Marini replied that he would consider
the idea; however, Trimax rejected the idea later that same day, and Marini was aware that Trimax
had done so. The grout extension to the M-1 pier was not there on August 28, and Baldwin and
Marini did not discuss such an extension. (Tr. 98-111, 255).
On September 5, Monahan and Cifune were at the site and saw Baldwin and a laborer adding
a grout extension to the M-1 pier. Monahan and Cifune asked what they were doing, and Baldwin said
that they were fixing the foundation and that they were told to perform the work. Monahan and Cifune
informed Baldwin that the work was a structural repair and that Marini should be involved. Later that
day, Monahan and Cifune talked to Collins about the work they had seen; they told him that it was
a structural repair, that KBA had not gotten anything about it, and that the repair did not look proper.
Collins responded that he would look into it. (Tr. 409-10, 413-14, 455-63, 473).
Marini made another visit to the site on September 12. He saw that a grout extension had been
added to the M-1 pier and that two anchor bolts had been set into the extension; in addition, the four
original anchor bolts at M-1 had been cut off, and two more bolts had been drilled into new locations
on the pier. Marini had not been told about these fixes and had not approved them. Further, because
the work was not done pursuant to the plans and specifications, and because he could not tell what
type or how long the new bolts were or what kind of reinforcing steel, if any, was inside the
extension, he concluded that the repair work was unacceptable. Marini saw a number of other
problems, including about a half dozen more column locations where all four anchor bolts had been
cut off and bolts had been drilled into new locations. (Tr. 111-25).
Later that day, Marini wrote Exhibit 17, a field report about his site visit, and sent it to Trim
at KBA; Trim faxed the report and his own cover letter to Collins at Alexandra on September 16. In
his report, Marini set out 14 bulleted items detailing the construction problems he had observed. Item
8 addressed the repair work at M-1 and noted it had been done without the general contractor first
having submitted sketches of the proposed repair work to the architect/engineer for approval; the item
also noted that the repair work appeared unacceptable.9 Item 14 addressed the various anchor bolts

    9
     This item and three other items specifically stated that “[t]he General Contractor must

submit sketches to the Architect/Engineer for review and approval of all repair work to correct

                                               6

that had been cut off and replaced with drilled-in bolts and stated that the “Architect/Engineer must
be informed of all field corrections such as these before any repairs are made.” The last page of the
report stated that the quality of the foundation construction needed to be improved and recommended
that the general contractor provide greater supervision of the concrete contractor; the report also
recommended an anchor bolt survey prior to erection. Trim’s cover letter requested that Alexandra’s
plan for correcting “the deficient work” be forwarded to KBA within seven days. In addition,
Monahan sent Pilcher an e-mail on September 24, requesting that Alexandra “get something
underway as soon as possible re: sketches etc. for any locations where there are problems w/ A.B.’s”
and that it “address the issues brought up in Odeh’s site visit as quickly as possible.” (Tr. 126-36,
344-45, 423-24, Exhs. 18, 27).
Alexandra responded to the 14 items in Marini’s report in a memo signed by Pilcher and sent
to KBA on September 23, 2002; the memo included a sketch for M-1 that proposed two additional
anchor bolts, for a total of six, two of which would be set in the grout extension. Baldwin and Dizdari
assisted Pilcher with the response, and Campbell reviewed it before it was sent. Marini did not receive
the response until October 1 and, accordingly, did not address it until after Column M-1 had fallen.
Marini in any case did not agree with the proposed fix set out in the sketch for M-1, particularly since
two of the anchor bolts were still shown as being set in the grout extension. Marini also did not have
a favorable reaction to the response as to the cutting of anchor bolts and replacing them with drilled-in
bolts; the response did not include M-1 in the list of locations, and it had insufficient information for
him to be able to give his approval. (Tr. 138-44, 250, 907-09, 921, 936-37; Exh. 19).
On September 26 and 27, NCD, the steel erection company that had replaced CWS, was on
site. Chauvin, NCD’s president, was also on site, and he and his crew were using a large crane to
unload the steel and to place it in the locations where it was going to be erected.10 The steel columns
that were placed in the auditorium stage area, where M-1 was located, were about 55 feet in length.

construction mistakes or errors.”
10
On September 26, Pilcher advised Monahan that NCD and Chauvin would be doing the
erection and that some steel had been delivered and unloaded. On that same day, when Monahan was
at the site and was at M-1 with Campbell, Monahan told Campbell to inform the erector of the
conditions at M-1 before any erection took place there. (Tr. 389, 415-16; Exh. 28).

                                               7

Chauvin introduced himself to Campbell and Pilcher, and he also met Collins, who indicated to
Chauvin that NCD “needed to get going.” Chauvin and Campbell walked Area A, and Chauvin told
Campbell where he would start erecting, which was in the auditorium stage area, and to keep the trade
workers out of the fall radius of the columns. Chauvin then asked if the anchor bolts were where they
belonged, and Campbell indicated that they were except for some that were not in the same area
where erection was to begin. (Tr. 513-15, 553-64; Exhs. 1, 41-42). See also Stip. Nos. 7, 12.
On October 1, NCD began steel erection. Prior to starting, however, Chauvin asked Campbell
for a letter certifying the anchor bolts were in accord with the plans, or, if they were not, specifying
the modifications performed and approved; Chauvin also asked for a letter certifying the concrete
strength. Campbell asked how to do the letters, and Chauvin told him how. Campbell then told
Chauvin that he would prepare the letters, to “go ahead and erect,”and that Chauvin was “all set.”
Chauvin then began erecting the steel, without being aware of any problems with the anchor bolts in
the area where he was working. NCD erected four columns without incident, with Chauvin operating
the crane, but the fifth column erected, Column M-1, fell about 30 seconds after it was detached from
the crane. All four of the anchor bolts that had been installed at M-1, that is, the two in the grout
extension and the two in the actual pier, pulled out when Column M-1 fell. Fortunately, no one was
injured when the column collapsed. (Tr. 564-70; Exh. 1). See also Stip. Nos. 8-13.
On October 2, Campbell gave Chauvin a handwritten letter that stated that “all base plates and
anchor bolt modifications have been completed with the approval of the structural engineer of record
in Area A, except (M-1, D-1, D-4, D.9-14 and C-12.9). The five for mentioned [sic] anchor bolts and
plates are awaiting approval.” The same letter, in typewritten form, was sent to Trimax on October 3.
On October 2, Campbell sent a letter to Trimax stating that “[a]ll concrete in area A of the building
... has reached or surpassed 75% of the compressive strength per spec.” All of Campbell’s letters in
this regard, including the handwritten one, were addressed to Danny Savoie at Trimax; Trimax,
however, sent copies of the letters it had received from Campbell to Chauvin’s office by facsimile.
(Tr.153-59, 587-91; Exhs. 20-21, 52-54).

                                              8

A structural steel preconstruction meeting was held on the site on October 3.11 At the meeting,
the collapse of Column M-1 was discussed, as was the requirement that any proposed structural repairs
be approved by Marini; also discussed was the need for the contractors to provide details on any
proposed structural repair sketches sufficient for Marini to determine if the proposed repair was
acceptable. On October 7 and afterwards, pullout testing, which tests if an anchor bolt will hold when
a specified force is exerted upon it, was done of the modified anchor bolts at the site. Certain of the
modified anchor bolts failed the pullout testing. (Tr. 152-53, 349-54, 913-15; Exhs. 28, V-2).
Despite the foregoing, Marini saw drilled-in anchor bolts and rebar in new locations on October
10, and these repairs had been done without sketches being submitted. Monahan also noticed new
repairs, of which KBA had had no prior notice, after the date the column fell; the repairs included
numerous anchor bolts that were cut off and a repair involving angle iron at the auditorium entrance.
Marini and KBA documented the continuing problem of unauthorized repairs and sketches that were
missing necessary information. Alexandra ultimately submitted acceptable sketches for M-1 and the
other the repairs at issue, which were approved on October 22. In addition, on November 1, Campbell
sent new notification letters to Chauvin with respect to anchor bolt modifications and concrete
compressive strength. (Tr. 165-66, 171-73, 430-31; Exhs. 23, 25, 29-32, 55-56).
Willful Citation 1 - Item 1
This item alleges a willful violation of 29 C.F.R. 1926.755(b)(1), which states that:
Anchor rods (anchor bolts) shall not be repaired, replaced or field modified without the
approval of the project structural engineer of record.
To establish a violation of a specific OSHA standard, the Secretary has the burden of proving
by a preponderance of the evidence that (1) the cited standard applies, (2) there was a failure to comply
with the standard, (3) employees had access to the violative condition, and (4) the employer either
knew of the condition or could have known of it with the exercise of reasonable diligence. Astra
Pharmaceutical Prod., 9 BNA OSHC 2126, 2129 (No. 78-6247, 1981).
Epernay contends that it did not violate the cited standard because the standard does not require
written approval and Marini verbally approved the anchor bolt modifications made at the site. Epernay

     11
      The structural steel preconstruction meeting should have been held before steel erection

began at the site. (Tr. 346-47).

                                               9

asserts that an OSHA compliance directive relating to structural steel erection specifically states that
the engineer’s approval need not be in writing and, moreover, that the approval need only occur prior
to erection. (R. Brief, p. 11). Even assuming arguendo that the Secretary is bound by the statements
made in the compliance directive, Epernay’s contention is not relevant because, based on my findings
below, verbal approvals of anchor bolt and other structural repairs were not permitted on the subject
project and Marini did not give such approvals.12
The required procedure on the subject project, for when a contractor intended to deviate from
the structural plans, is set out on page 5 of this decision. Marini and Trim testified in this regard, and
Miller, the clerk of the works, confirmed their testimony about the procedure. (Tr. 69-75, 78-79, 90,
101-02, 108, 130, 324-27, 367-68, 504-05). Alexandra’s field manual for superintendents is consistent
with the testimony of Marini, Trim and Miller, stating that “[i]f it should become necessary to cut a
structural element, no action is to be taken by any Company personnel and no authorization is to be
given to any subcontractor without the prior written approval of the specific cutting by the Owner,
Architect and the Owner’s or Architect’s Engineer.” (Tr. 935-36, Exh. 92, p. 13). Marini, Trim and
Miller all testified to the effect that a contractor could not make structural changes in the field without
the written approval of the architect and engineer and that this was the standard procedure in the
construction industry. (Tr. 69-75, 258-59, 264-65, 324-27, 367-68, 505).
Marini’s testimony about his three visits to the site, and the modifications he saw that he had
not been told about and had not approved, including the modifications at M-1, is set out on pages 5
and 6 of this decision. (Tr. 77-89, 98-125, 255). The testimony of Marini in this regard is supported
by the testimony of Monahan, Miller and Cifune. (Tr. 407-14, 455-63, 473, 511-13). Marini’s
September 12 visit to the site resulted in Exhibit 17, his report about that visit, the details of which are
described on pages 6 and 7 of this decision. The report sets out 14 items addressing the problems
Marini had seen, including the repair work at M-1 and other locations where anchor bolts had been cut
off and replaced with drilled-in bolts. Item 8, the item relating to M-1, and three other items state that
“[t]he General Contractor must submit sketches to the Architect/Engineer for review and approval of

      12
       At the hearing, Epernay presented Exhibit rr, a draft of the compliance directive, and

Exhibit ss, the actual directive. Exhibit rr was received in evidence, but Epernay never sought
admission of Exhibit ss. (Tr. 1006-09, 1037-40).

                                                10

all repair work to correct construction mistakes or errors.” Item 14, the item pertaining to the other
locations where anchor bolts had been cut off, states that “[t]he Architect/Engineer must be informed
of all field corrections such as these before any repairs are made.” Marini specifically testified that he
had not approved the repairs addressed in Items 8 and 14 before October 1. (Tr. 145-46).
Epernay disputes Marini’s testimony, noting Baldwin’s testimony that he discussed repairs
with Marini either on the phone or in the field and that Marini verbally approved such repairs; Baldwin
also testified that he never made any repairs, including those at M-1 and the other anchor bolt repairs,
without first consulting Marini and that he had not had to submit sketches or written proposals.13 (Tr.
817-30, 835-39, 855, 886). In support of Baldwin’s testimony, Epernay presented phone records
showing numerous phone calls during the relevant period between Odeh’s office and either
Alexandra’s site phone or Baldwin’s cell phone. See Exhibits W-1-7.
As a preliminary matter, I agree with the Secretary that the phone records noted above are not
probative of the content of conversations that took place between Odeh and either Baldwin or
Alexandra personnel; the project was a large one, the calls could have involved any number of topics,
and while it is clear that Marini spoke to Baldwin and Alexandra representatives on the phone and
when he was at the site, and that he gave them verbal direction, these facts do not prove that Marini
gave verbal approvals as Epernay claims. (Tr. 79, 231-33, 237, 276; Exh. 7, p. 1) At most, the
importance of otherwise unidentified telephone calls between the two numbers amounts to a minor
quodlibet. Beyond that, I conclude that Epernay’s contention simply makes no sense, in light of the
evidence of record. As the Secretary points out, if Marini had been verbally approving the repairs at
the site, then Epernay and Alexandra would surely have protested upon receiving Exhibit 17, Marini’s
September 12 report, which clearly expressed Marini’s disapproval of how both Epernay and
Alexandra were proceeding at the site and stated four times the requirement that the contractor submit
sketches and obtain the engineer’s approval for all repair work. There is no evidence of any such
protest in the record, including in Exhibit 19, Alexandra’s response to Exhibit 17. As the Secretary also
points out, Alexandra’s own field manual for superintendents prohibited the cutting of structural
elements without the “written approval” of the architect or engineer. (Exh. 92, p. 13). Further, the

     13
          Baldwin testified that he also discussed repairs with Monahan. (Tr. 817-19, 825, 835).

                                               11

Secretary points out that Epernay’s answer to Interrogatory No. 11, relating to anchor bolt repairs, was
as follows:
Depending on the repairs being performed, prior to September 16, 2002 the requested
fix was either communicated verbally or in writing to Larry Marini or Ed Monahan,
and RFI was sent or a fix would be provided by Larry Marini in his field reports. After
September 16, 2002 Larry Marini requested sketches of proposed repairs and these
would be submitted for approval. (Tr. 1035; Exh. 93, Ans. #11).
Turning to some of the specifics of Baldwin’s testimony, Baldwin testified that he had asked
Marini at the very beginning what the standard procedure was for fixing anchor bolts on the project.
Baldwin said he had always made anchor bolt repairs by drilling down 8 to 10 inches, cleaning the hole
thoroughly, and then setting the bolt into the hole along with the approved epoxy; he also said that he
had advised Marini of this method and that no one had ever told him before October 1 that it was not
an approved fix for anchor bolts. Baldwin further testified that when he discovered that the wall at M-1
was 2 inches too short, he spoke to Marini and Monahan and suggested adding a grout extension and
installing two anchor bolts in the grout and two more in the correct locations on the pier. As a result
of his discussions with Marini and Monahan, this repair work was done, but, according to Baldwin,
he concluded upon viewing the repair that “it was just a shoddy piece of work.” He again contacted
Marini, telling him he was not comfortable with the repair, and he asked Marini to visit the site to look
at it. Marini visited the site for that purpose, although Baldwin was not sure of the date, and while
Marini and Baldwin talked about other possible fixes, such as adding two more anchor bolts, the
matter was not resolved. Baldwin was “vaguely” familiar with Exhibits 17 and 19, Marini’s September
12 report and Alexandra’s response to the report, respectively, and he indicated he might have gone
over some of the items in the documents with Pilcher; he also stated that page 3 of Exhibit 19 showed
the two additional bolts he and Marini had discussed. Baldwin indicated that his manner of dealing
with Marini, that is, calling him to get approval for a fix over the phone or having Marini look at a
particular problem at the site and then getting his verbal approval to fix it, was consistent with his
experience on previous projects. (Tr. 817-30, 835-39).
I find the foregoing testimony not credible for several reasons. First, Baldwin’s testimony about
getting verbal approvals from Marini for repair work at the site is directly contrary to the testimony
of Marini, Trim and Miller, to the statement from Alexandra’s manual for superintendents, and to

                                               12

Epernay’s answer to Interrogatory No. 11, all of which are set out supra; similarly, Baldwin’s
indicating that the verbal approvals he allegedly received on the project were consistent with how he
had worked at other sites is contrary to the testimony of Marini, Trim and Miller that written approval
was the standard procedure in the construction industry. Second, Baldwin’s testimony indicating there
was a standard procedure for anchor bolt fixes contradicted the testimony of Marini and Trim that
proposed “typical” anchor bolt fixes were not acceptable because a particular column, even if it looked
similar to a column next to it, could have different loads bearing on it and the engineer had to evaluate
the fix for the specific column.14 (Tr. 92-94, 366-67). Third, Baldwin’s “vague familiarity” with
Exhibits 17 and 19 is at odds with Campbell’s testimony that Baldwin and Dizdari had assisted Pilcher
to provide the answers in Exhibit 19.15 (Tr. 907-09, 921, 937). Fourth, Baldwin’s testimony about how
the M-1 repairs came about is at odds with the testimony of Marini, Monahan and Cifune; their
testimony in this regard is on page 6 of this decision. (Tr. 111-25, 409-10, 413-14, 455-63, 473).
In addition to the above, I observed the demeanors of Marini and Baldwin as they testified, as
well as the demeanors of Trim, Cifune, Monahan and Miller. In so doing, I noted their facial

     14
       Marini approved essentially the same repair that Baldwin described for the anchor bolts

noted in his report of August 1, and on October 11 he approved this repair for M-1 and the other
modified anchor bolts at the site. Marini said the October 11 approval included the epoxy to use, an
embedment depth of 9 inches, and a pullout strength of 11,120 pounds; he also said an anchor bolt
repair done with epoxy could have in certain cases a lesser embedment than a bolt that was set in
concrete as per the original specifications. (Tr. 270-74, 291-92; Exh. F). Although Epernay points
to this evidence in support of its position, I have found Marini and Trim to be believable witnesses,
as set out infra, and I therefore credit their testimony that the engineer had to evaluate the fix for the
particular column. That this is so is apparent from the faulty repairs at M-1, where the extension was
added to the pier, and the accident that occurred; stated another way, an anchor bolt fix could entail
more than simply cutting off the bolts and re-drilling them in new locations. Moreover, Marini
testified that the repair requirements set out in his October 11 approval were “what would be
acceptable,” thereby setting out the minimum requirements for the anchor bolt repairs, and it is
reasonable to infer he based those requirements on his professional engineering judgment. (Tr. 291-
92). Finally, that Marini ultimately approved a single fix for the many anchor bolts that required
repair does not support Epernay’s contention that he gave verbal approvals, in view of the other
evidence of record, and had no effect on Epernay’s obligation to obtain written approval from Marini
before performing anchor bolt repairs at the site.
15
On cross-examination, Baldwin first denied any familiaritywith Exhibit 19, but he then said
that Pilcher “may have” talked to him about it. (Tr. 877-78).

                                               13

expressions, attitudes, tones of voice, eye contact, posture and body movements. I also noted the
consistency and reasonableness of their testimony, or lack thereof, in view of the record as a whole,
as well as the motivation of each witness for testifying in a particular way. I found Marini, Trim,
Cifune, Monahan and Miller16 to be credible and convincing witnesses, and their testimony is also
supported by documentary evidence in the record.17 On the other hand, I found significant parts of
Baldwin’s testimony evasive and/or equivocal, besides being contrary to that of other witnesses and
documentary evidence. In sum, I found Baldwin an unreliable witness, and his testimony, to the extent
that it is inconsistent with that of other witnesses or documentary evidence, is not credited.
For all of the foregoing reasons, I conclude the Secretary has met her burden of proof in regard
to this item. Specifically, I find that the standard applies and that its terms were violated. Besides the
evidence noted supra, Baldwin admitted at the hearing that the fix at M-1 was not an approved
condition when erection began; he also admitted that he had stated at the preconstruction meeting on
October 3 that he knew the M-1 location was not ready to have a column erected.18 (Tr. 851, 879; Exh.
28, Item PCSS-14). I further find that employees were exposed to the cited hazard; in this regard,
Epernay has stipulated that employees of NCD were exposed within the fall radius of Column M-1 in
Area A at the project on October 1. (Tr. 8). Finally, I find that Epernay had knowledge of the cited
conditions. Baldwin, Epernay’s foreman, clearly knew of the repairs at M-1 and the other anchor bolt

     16
      In finding Miller a credible witness, I have noted the fact that he was hired by the town of

Westwood. I have further noted his considerable experience and the fact that his professional duty
lay in having the work on the project done correctly. (Tr. 496-501).
17
In finding Marini a credible witness, I have considered and rejected all of Epernay’s
arguments that he was not. In particular, I have noted that Marini agreed that a number of errors were
made in the project drawings. See, e.g., Tr. 190-208. He also testified, however, that there were
“thousands and thousands” of items on any given project and that the number of errors he made was
not unusual considering the size and complexity of this project. (Tr. 300-04). Further, on this record,
Marini has not been shown to have made errors of judgment. I have also noted the many e-mails in
the record that, according to Epernay, support its position that Marini did give verbal approvals in
this matter. Given the substantial evidence in the record that is contrary to Epernay’s position, as set
out above, the e-mails are accorded little weight.
18
In addition, Campbell admitted, in his October 2 letter to Chauvin of NCD, that anchor bolt
modifications had not been completed with the approval of the structural engineer of record at M-1
and four other locations in Area A. See Exhibit 52.

                                               14

modifications, and Campbell testified that Baldwin had helped Pilcher prepare Exhibit 19, Alexandra’s
response to Exhibit 17, Marini’s September 12 field report. (Tr. 907-09, 921, 937). Baldwin was a
foreman with Epernay, and his knowledge of the violative conditions is imputable to Epernay.
In regard to the willful classification of the violation, it is the Secretary’s burden to show that
the violation was committed “with intentional, knowing or voluntary disregard for the requirements
of the Act or with plain indifference to employee safety.” Williams Enter., Inc., 13 BNA OSHC 1249,
1256 (No. 85-355, 1987) (citation omitted). As Williams further explains:
It is not enough for the Secretary to show that an employer was aware of conduct or
conditions constituting a violation....A willful violation is differentiated by a
heightened awareness–of the illegality of the conduct or conditions–and by a state of
mind–conscious disregard or plain indifference. There must be evidence that an
employer knew of an applicable standard or provision prohibiting the conduct or
condition and consciously disregarded the standard. Without such evidence of
familiarity with the standard’s terms, there must be evidence of such reckless disregard
for employee safety or the requirements of the law generally that one can infer that if
the employer had known of the standard or provision, the employer would not have
cared that the conduct or conditions violated it. Id. at 1256-57.
It is reasonable to infer that Epernay, as a subcontractor at the subject site, was aware of the
prohibition in the project manual against the cutting or altering of structural members without the
approval of the architect. (Exh. 26, § 05120, ¶ 3.2.D). It is also reasonable to infer that Baldwin, who
had many years of construction experience, was aware that the standard practice in the industry was
for contractors to make no structural changes in the field without the written approval of the architect
and engineer, as Marini, Trim and Miller testified. (Tr. 69, 326, 505, 799-807). Despite this awareness,
Baldwin’s crew made modifications to anchor bolts in numerous locations at the site before October
1 without first obtaining Marini’s approval. (Tr. 115-16, 145-46, 511-13; Exh. 17; Stip. No. 5).
Further, on September 5, Monahan and Cifune saw Baldwin and a laborer adding the grout extension
to the M-1 pier, and Monahan and Cifune told Baldwin the work was a structural repair and that
Marini should be involved. Later that day, Monahan and Cifune talked to Collins, Alexandra’s project
manager, about the work at M-1, noting that it was a structural repair, that KBA had not gotten
anything about it, and that the repair did not look proper; Collins told them he would look into it. (Tr.
409-10, 413-14, 455-63, 473). Notwithstanding these circumstances, Marini knew nothing about the
repair work at M-1 until he saw it during his site visit on September 12. Marini specifically referred

                                               15

to the repairs at M-1 as “unacceptable” in his September 12 field report, and Baldwin was aware of
that report because he assisted Pilcher with the responses to the report. (Tr. 111-15, 907-09, 921, 937;
Exhs. 17, 19). Baldwin himself testified that the grout repair at M-1 was a “shoddy piece of work,” and
he stated at the preconstruction meeting on October 3 that he knew that the M-1 location was not ready
to have a column erected. (Tr. 826, 851; Exh. 28, Item PCSS 14).
In addition to the foregoing, the record shows that Baldwin did not properly supervise the
anchor bolt repairs. Baldwin testified that he assigned Epernay employee Robert Mercurio to make the
repairs by cutting off the misaligned bolts and installing new bolts in the proper locations by drilling
down 8 to 10 inches, cleaning the holes out thoroughly, and then setting new threaded rods in the holes
with epoxy.19 He also testified that Mercurio told him he had performed anchor bolt repairs before and
that he “knew what he was doing.” Baldwin admitted, however, that he had not reviewed Mercurio’s
work, that he had not actually known whether Mercurio had repaired anchor bolts before, and that he
was at fault for assuming that Mercurio would do the work properly. He also admitted that he had
worked with Mercurio a total of only about two weeks; he had supervised him a day or two at a
previous site and about two weeks at the subject site. Finally, he admitted that he had known that
Mercurio had hit rebar about 3 inches down when trying to install an anchor bolt at M-1. Baldwin said
he viewed M-1 after the accident, at which time he discovered that Mercurio had drilled the holes
down only about 3 inches and had not adequately cleaned them out.20 He confronted Mercurio the day
after the accident about the repairs and then fired him. (Tr. 839-47, 887-88, 893-94).
In view of Baldwin’s awareness of the requirement that he was to obtain Marini’s approval
before making anchor bolt repairs and that he and his crew nonetheless made such repairs without that
approval, I conclude that Epernay had knowledge of the cited requirement and consciously disregarded
it. I further conclude that Baldwin’s handling of the anchor bolt repairs at the site is best described as
gross negligence and that, therefore, Epernay acted with plain indifference to employee safety. There
is also an additional reason for finding that this item was willful. At the preconstruction meeting on

     19
     Although the transcript refers to Mercurio as “Bobby McKeon” and “Mr. Mecurio,” Robert

Mercurio is the correct name of the individual. (Tr. 839-47, Exh.84).
20
The two drilled holes were actually 3.75 inches and 5.5 to 6 inches deep. (Tr. 640).

                                                16

October 3, Marini reiterated the requirement that any repair needed must have a sketch showing the
proposed repair and that the proposed repair had to be approved before it took place. (Exh. 28, Item
PCSS-08). During a site visit on October 10, however, Marini saw drilled-in anchor bolts and rebar
in new locations, and these repairs had been done without sketches being submitted. (Tr.165-66, Exh.
23, Item 1). Monahan also noticed new repairs, of which KBA had not had previous notice, after the
date the column fell; these included numerous anchor bolts that were cut off and a repair involving
angle iron at the auditorium entrance. (Tr. 430-31). Trim wrote several letters to Alexandra following
the October 3 meeting. Exhibits 29 and 30, both dated October 8, addressed, respectively, the
continuing problem of unauthorized repairs and anchor bolts and base plates being out of tolerance.
Exhibit 31, dated October 10, stated that proposed repairs must be on a case-by-case basis, that
“typical” repairs would not be reviewed, and that, as noted previously, no anchor bolts were to be cut
or removed unless directed by Odeh. Exhibit 32, dated October 15, noted that sketches Alexandra had
submitted as proposed solutions for various columns were incomplete and could not be properly
evaluated. Alexandra ultimately submitted acceptable sketches for M-1 and the other repairs at issue,
and these were approved on October 22. (Tr. 171-73, Exh. 25).
Based on the above, I find that Epernay continued to make unauthorized repairs to anchor bolts
and other structural members at the site after the accident and after the October 3 meeting, which
Baldwin attended. See Exhibit 28. This conduct exhibited both conscious disregard of the cited
standard and plain indifference to employee safety. Item 1 of Willful Citation 1 is accordingly
AFFIRMED as a willful violation; the violation was also serious, in that it clearly could have caused
death or serious injury.21 See section 17(k) of the Act.
Penalty Assessment
In assessing penalties, the Commission must give “due consideration” to the four criteria set
out in section 17(j) of the Act, that is, the size of the employer’s business, the gravity of the violation,
and the employer’s good faith and previous history of OSHA violations. These criteria are not

      21
        I have noted Epernay’s contention that it relied on Mo Luckern, Trimax’s representative

at the site, to tell the erector about the anchor bolt conditions before erection began at the site and
that it (Epernay) did not know that Luckern had left the project when Trimax replaced CWS with
NCD. (R. Brief, pp. 22-23). This contention is not relevant, however, in light of the manner of
disposition of this item.

                                                17

necessarily accorded equal weight, and the gravity of the violation is usually the primary factor to be
considered. Nacirema Operating Co., 1 BNA OSHC 1001 (No. 0004, 1972). I find the gravity of the
violation in this case to be high. Epernay performed anchor bolt repairs at the site that it knew were
not authorized, and, in particular, it performed the repairs at M-1, which it knew were unacceptable.
Epernay also failed to supervise properly the employee who performed the anchor bolt cutting and
redrilling work, and Epernay continued to make unauthorized changes to anchor bolts and other
structural members after the accident and the October 3 preconstruction meeting. The condition at M-1
clearly could have resulted in death or serious injury, and Chauvin and his crew of five to eight
employees were exposed to the hazard of the M-1 column falling; fortunately, however, the column
injured no one when it fell. (Tr. 558). I find that a reduction in penalty for the employer’s relatively
small size is appropriate but that no reduction is appropriate for good faith or history. (Tr. 761-70). I
also find that the Secretary’s proposed penalty of $56,000.00 for the violation is appropriate. A penalty
of $56,000.00 is consequently assessed for Item 1 of Willful Citation 2.

                                               18

FINDINGS OF FACT
All findings of fact necessary for a determination of all relevant issues have been made within
the text above. Fed. R. Civ. P. 52(a). All proposed findings of fact and conclusions of law inconsistent
with this decision are hereby denied.

                                CONCLUSIONS OF LAW
   1. Respondent Epernay was, at all times pertinent hereto, an employer within the meaning of

section 3(5) of the Act.
2. The Commission has jurisdiction over the parties and the subject matter.
3. Respondent Epernay was in violation of section 5(a)(2) of the Act in that it failed to comply
with 29 C.F.R. § 1926.755(b)(1), as alleged in Willful Citation 1, Item 1.
4. The violation found above was willful and serious within the meaning of the Act.
5. A total civil penalty of $56,000.00 for the violation affirmed in Item 1 of Willful
Citation 1 is appropriate.

                                           ORDER
   1. Item 1 of Willful Citation 1 is AFFIRMED.
   2. A total civil penalty of $56,000.00 is assessed.




                                                   /s/
                                                    Michael H. Schoenfeld
                                                    Judge, OSHRC

Dated: April 23, 2004
Washington, D.C.

                                              19

Get today's answer for your situation

You just read what one judge decided for one employer in 2004, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.